In: Accounting
Skootin’ Along Company manufactures skateboards in a local warehouse in Suburbia Conway. Manufacturing has 20 employees. Each employee presently provides 35 hours of productive labor per week. Information about a production week is as follows:
Standard wage per hour $10.60
Standard labor time per skateboard 15 minutes
Standard number of feet of board per skateboard 4.0 feet
Standard price per foot of board $2.90
Actual price per foot of board $3.05
Actual feet of board used during the week 14,200 feet
Number of skateboards produced 3,500
Actual wage per hr. $10.00
Actual hours worked per week 700 hrs.
Determine the price variance, quantity variance, and overall variance for both direct material and direct labor. Explain what the variances indicates and what are some possible causes for the variances?