Question

In: Finance

Project A and Project B have a cost of $30,000,000 today. Project A will have cash...

Project A and Project B have a cost of $30,000,000 today. Project A will have cash flows of $12,000,000 per year for three years, while Project B will have cash flows of $15,000,000 the first year, $10,000,000 the second year, and $11,000,000 the third year.

1. Calculate the NPV and the IRR for Project A using a 10% cost of capital and show your work by using TWO of the following methods: (1) using the formula, (2) identifying all variables using the calculator’s function keys, (3) using the steps on the calculator to calculate NPV and IRR. SHOW WORK

2. Calculate the NPV and the IRR for Project B using a 10% cost of capital and show your work by using TWO of the following methods: (1) using the formula, (2) identifying all variables using the calculator’s function keys, (3) using the steps on the calculator to calculate NPV and IRR. SHOW WORK

3. Should A, B, both A and B, or neither be accepted if the projects are independent. Circle your choice

4. Should A, B, both A and B, or neither be accepted if the projects are mutually exclusive. Circle your choice

Solutions

Expert Solution

NPV=Present value of future cash inflows-Cash ouflow

Project A, NPV=((12000000/(1+10%))+(12000000/(1+10%)^2)+(12000000/(1+10%)^3))-30,000,000

Project A, NPV=-157,776.11

We can also use EXCEL

NPV(rate, values)

NPV(rate, year1 to year3 cashflows)-Cash outflow

NPV(10%,Year1 to Year3 cashflows)-30,000,000

NPV=-157,776.11

IRR can be used with function in EXCEL

IRR, Project A=IRR(values)=IRR(cashflows from Year 0 to Year3)=9.70%

In similar way, NPV and IRR for Project B can be solved

NPV, Project B=(15000000/(1+10%))+(10000000/(1+10%)^2)+(11000000/(1+10%)^3))-30,000,000

NPV, Project B=165,289.26

IRR, Project B=IRR(Year 0 to Year3 cahflows)=10.33%

3. If projects are independent: We have select only Project B because of positive NPV and IRR>cost of capital. Despite projects are independent, we should not select Project A because it eats way the shareholders wealth because of negative NPV

4. If projects are mutually exclusive: We should select only Project B and avoid Project A. Project B increases the shareholders wealth


Related Solutions

A project will cost $50,000 today and produce equal after tax cash flows for the next...
A project will cost $50,000 today and produce equal after tax cash flows for the next seven years (these will be the only cash flows from the project). Your discount rate is 13%. If it turns out your payback period is four years, what is the net present value of this project?  
Project Cash Flow Today (millions) Cash Flow in One Year (millions) A -$10 $20 B $6...
Project Cash Flow Today (millions) Cash Flow in One Year (millions) A -$10 $20 B $6 $4 C $18 -$12 Suppose all cash flows are certain and the​ risk-free interest rate is 5%. a. What is the NPV of each​ project? b. If the firm can choose only one of these​ projects, which should it​ choose? c. If the firm can choose any two of these​ projects, which should it​ choose?
3. You have a third project that will cost 1700 to invest in today, will generate...
3. You have a third project that will cost 1700 to invest in today, will generate cash flows of 50, 100, 200, and 250 at the end of each of the next four years, with cash flows continuing to grow at a constant rate of 3% starting with the fourth cash flow and continuing forever. If the discount rate is 15%, what is the NPV and should you accept the project based on the NPV? Please show all your work.
2. You also have a second project that will also cost 1750 to invest in today,...
2. You also have a second project that will also cost 1750 to invest in today, and will generate cash inflows of 300, 500, 590, and 1000 at the end of each of the next four years. If the discount rate is 10%, what is the MIRR and should you accept the project based on the MIRR? 2. You also have a second project that will also cost 1750 to invest in today, and will generate cash inflows of 300,...
You are considering two mutually-exclusive projects: Project A and Project B. The initial cash outlay (cost)...
You are considering two mutually-exclusive projects: Project A and Project B. The initial cash outlay (cost) associated with Project A is $60,000, whereas the initial cash outlay associated with Project B is $80,000. The required rate of return for both projects is 10%. The expected annual free cash flows from each project are as follows: Year Project A Project B 0 - 60,000 -80,000 1 13,000 15,000 2 13,000 15,000 3 13,000 15,000 4 13,000 15,000 5 13,000 15,000 6...
The following are the mixed stream of cash flows for project A and project B: Cash...
The following are the mixed stream of cash flows for project A and project B: Cash flow stream (in rands) Year A B 1 50 000 10 000 2 45 000 25 000 3 35 000 35 000 4 25 000 45 000 5 10 000 50 000 Totals 165 000 165 000 Required: 5.1. Find the present value of each stream, using a 12% discount rate. [6] 5.2. Compare the calculated present values and discuss them in the context...
Projects A and B are mutually exclusive and have an initial cost of $78,000 each. Project...
Projects A and B are mutually exclusive and have an initial cost of $78,000 each. Project A provides cash inflows of $32,000 a year for three years while Project B produces a cash inflow of $44,400 a year for two years. Which project(s) should be accepted if the discount rate is 10 percent? What if the discount rate is 12.5 percent?
Suppose the expected sales volume of a company is $30,000,000, if the salary and administration cost...
Suppose the expected sales volume of a company is $30,000,000, if the salary and administration cost of the company sales force equals to $700,000 and they receive a commission of 2.5%, while the commission for the independent sales force equals 5%, should the company hire independent sales force or use internal sales force?
10) Fairfax Paint is evaluating a project that would cost 6,728 dollars today. The project is...
10) Fairfax Paint is evaluating a project that would cost 6,728 dollars today. The project is expected to have the following other cash flows: 2,220 dollars in 1 year, 2,506 dollars in 3 years, and 3,169 dollars in 4 years. The internal rate of return for the project is 5.89 percent and the cost of capital for the project is 5.22 percent. What is the net present value of the project?
A project requires $1000 to be invested today, and is expects to generate cash flows in...
A project requires $1000 to be invested today, and is expects to generate cash flows in the future years: CF1=$500, CF2=$400, CF3=$200. What is the REGULAR payback period of this project? a) 2.5 years b) 3 years c) 1.25 years d) 0.5 years e) Never pay back the cost
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT