Question

In: Finance

You are considering two mutually-exclusive projects: Project A and Project B. The initial cash outlay (cost)...

You are considering two mutually-exclusive projects: Project A and Project B. The initial cash outlay (cost) associated with Project A is $60,000, whereas the initial cash outlay associated with Project B is $80,000. The required rate of return for both projects is 10%. The expected annual free cash flows from each project are as follows:

Year

Project A

Project B

0

- 60,000

-80,000

1

13,000

15,000

2

13,000

15,000

3

13,000

15,000

4

13,000

15,000

5

13,000

15,000

6

13,000

15,000

A.  Calculate the payback period for each project.

B. Calculate the NPV and the IRR for each project. Which project (if any) should be accepted if they are mutually exclusive? Explain your answer.

C. What are the implications for a firm that selects the wrong project?

Solutions

Expert Solution

Solution:-

To Calculate Payback Period of Projects-

Project A-

Payback Period =

Payback Period =

Payback Period = 4.62 years

Project B-

Payback Period =

Payback Period =

Payback Period = 5.33 years

To Calculate NPV of the Project-

To Calculate IRR of the Project-

Net Present Value of the Project is accepted when it is greater than or equal to zero. In the Given Case NPV of Both Project is negative by which we can not accept any project.

If you have any query related to question then feel free to ask me in a comment.Thanks.


Related Solutions

Mutually exclusive Projects Project A Project B Project C Initial cash Outlay        (50,000)       (60,000)...
Mutually exclusive Projects Project A Project B Project C Initial cash Outlay        (50,000)       (60,000)        (40,000) Required Rate of Return 11% 8% 13% Cash Flows:       Inflow Year 1 10,000 30000 8,000 Inflow Year 2 15,000 50000 20,000 Inflow Year 3 20,000 5000 20,000 Inflow Year 4 25,000 5000 20,000 Inflow Year 5 30,000 2000 15,000 Step 1 Your first assignment as a financial analysis manager at Caledonia Products is to evaluate three new capital budget proposals. You have...
A company is considering two mutually exclusive projects requiring an initial cash outlay of $100 each...
A company is considering two mutually exclusive projects requiring an initial cash outlay of $100 each and with a useful life of 5 years. The company required rate of return is 10% and the appropriate corporate tax rate is 40%. The projects will be depreciated on a straight line basis. The before depreciation and taxes cash flows expected to b generated by the projects are as follows. Year 1 2 3 4 5 Project A ($) 4,000 4,000 10,000 2,000...
Projects A and B are mutually exclusive and have an initial cost of $78,000 each. Project...
Projects A and B are mutually exclusive and have an initial cost of $78,000 each. Project A provides cash inflows of $32,000 a year for three years while Project B produces a cash inflow of $44,400 a year for two years. Which project(s) should be accepted if the discount rate is 10 percent? What if the discount rate is 12.5 percent?
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0&
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0                  -$35,000                  -$35,000     1                     22,000                     13,000     2                     20,000                     21,000     3                     13,000                     22,000 What is the internal rate of return of PROJECT A?
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0&
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0                  -$35,000                  -$35,000     1                     22,000                     13,000     2                     20,000                     21,000     3                     13,000                     22,000 What is the crossover point?
Universal PLC is considering two mutually exclusive project proposals for new investment. The initial outlay of...
Universal PLC is considering two mutually exclusive project proposals for new investment. The initial outlay of both projects is £300,000 but will yield different levels of cash flows over the life of the project. The projects are estimated to last for five years. They will have no residual value at the end of their lives. Depreciation is charged on a straight-line basis. The company uses a 6% discount rate for the cost of capital. The cash flows of both projects...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates cash flows of $10,000 for 10 years. Project B costs $80,000 and generates cash flows of $2,000 for six years and then cash flows of $28,000 for four years. Report rates in percentage form to two decimal places i.e. 10.03% not 10% At what discount rate would make you indifferent between choosing one project or another? What is the highest discount rate in which...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates...
You are considering two mutually exclusive projects, A and B. Project A costs $70,000 and generates cash flows of $12,000 for 10 years. Project B costs $60,000 and generates cash flows of $2,000 for six years and then cash flows of $29,000 for four years. Which project would you accept if your discount rate was 10%? Which project would you accept if your discount rate was 5%?
Q Corporation is considering investing in the following projects: Project A Project B Initial cash outlay...
Q Corporation is considering investing in the following projects: Project A Project B Initial cash outlay $(200,000) $(140,000) Future cash inflows: Year 1 $ 50,000 $ - Year 2 50,000 - Year 3 50,000 - Year 4 50,000 40,000 Year 5 50,000 90,000 Year 6 50,000 140,000 Total cash inflows $300,000 $ 270,000 The company’s cost of capital is 8%, which is an appropriate discount rate. Required: Compute the net present value of each project. Use a clear presentation of...
You are considering the following two mutually exclusive projects. Project A Project B Year 0 -$10,000...
You are considering the following two mutually exclusive projects. Project A Project B Year 0 -$10,000 -$20,000 Year 1 $ 3,000 $ 5,000 Year 2 $ 8,000 $ 7,000 Year 3 $ 4,000 $12,000 Year 4 $ 2,000 $10,000 The required return on each project is 12 percent. Which project should you accept and what is the best reason for that decision? a. Project B; because it has the higher net present value b. Project A; because it pays back...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT