Question

In: Finance

The cash flows for two projects, A and B, are shown in the table, below. Notice...

The cash flows for two projects, A and B, are shown in the table, below. Notice that Project A has a life of 5 years and Project B has a 3 year life. Calculate the NPV of each project and calculate which should be adopted using the replacement chain approach. Assume that the cost of capital is 10%.

Project CFs

Project CFs

Time

A

B

0

-100

-150

1

20

75

2

25

60

3

30

50

4

30

5

40

NPV

6.7097

5.3343

answer is -2.85
How to get this number?

Solutions

Expert Solution

PROJECT A NEEDS REPLACEMENT EVERY 5 YEARS AND PROJECT B NEEDS REPLACEMENT EVERY 3 YEARS

SO I HAVE PREPARED CFs ACCORDINGLY.

SEE IMAGE. AT THE END OF 5TH YEAR, WE HAVE TO BUY AGAIN PROJECT A FOR WHICH COST IS 100. SO NET CF = 40 -100 = -60

SAME WAY FOR PROJECT B. AT THE END OF 3RD YEAR : CF=50 AND PROJECT COST = 150, SO NET CF = -100.

HAPPY TO HELP YOU.


Related Solutions

Exercise 6.7: Projects A to E have cash flows as shown in the table below. The...
Exercise 6.7: Projects A to E have cash flows as shown in the table below. The Marr used to evaluate project is also shown. Calculate NPW, NFW, and EUAW for each of these projects? MARR 12% 7% 18% 6% 13% Year Project A Project B Project C Project D Project E 0 ($36,000) ($56,000) ($25,000) ($278,000) ($321,000) 1 $5,000 $15,000 $5,000 $3,500 $40,000 2 $8,800 $17,400 $5,800 $40,600 $46,400 3 $10,208 $20,184 $6,728 $47,096 $53,824 4 $11,841 $23,413 $7,804 $54,631...
You are analyzing two projects with the cash flows shown below. Year:                        0       &nb
You are analyzing two projects with the cash flows shown below. Year:                        0                     1                  2                 3               4                    5            Project 1:     -$6,000       $1,000      $1,000    $1,500    $2,000    $4,000      Project 2:     -$6,000       $2,500      $2,000    $1,500    $1,000    $1,500 Construct an NPV chart with discount rates from 1% - 25%.   On your NPV chart, please identify and label the following points: a) The IRR of project 1 (calculate the value and label the...
Mary Inc. is considering mutually exclusive Projects A and B, whose cash flows are shown below....
Mary Inc. is considering mutually exclusive Projects A and B, whose cash flows are shown below. If the decision is made by choosing the project with the higher IRR, will there be any value loss due to the IRR-based decision? If there is a loss, how much value will be forgone? The WACC is assumed to be 9.5%. WACC: Year 9.5% 0 1 2 3 4 CFA −$2,020 $730 $730 $740 $740 CFB −$4,100 $1,400 $1,500 $1,520 $1,530 Use a...
Brian Cliff is evaluating two mutually exclusive projects                    (expected cash flows shown below). The...
Brian Cliff is evaluating two mutually exclusive projects                    (expected cash flows shown below). The firm's cost of capital is 12.25 percent.                                                                               Year                Project A             Project B                                                    0                       (600)                                      (600)                                                    1                           200                                        400                                                    2                           310                                        260                                                      3                           400                                        100                                                                 NPV?                     _____                                   _____                                                                 IRR?                       _____                                   _____                 Calculate the NPVs and IRRs for Projects A and B. Project A's NPV is $107.02, and Project B's...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 6.75% 0 1 2 3 4 CFS -$1,025 $380 $380 $380 $380 CFL -$2,150...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 7.75% 0 1 2 3 4 CF S -$1,025 $380 $380 $380 $380 CF...
A company is considering Projects S and L, whose cash flows are shown below. These projects...
A company is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO believes the IRR is the best selection criterion, while the CFO advocates other methods. If the decision is made by choosing the project with the higher IRR, how much, if any, value will be forgone, i.e., what's the: NPV and IRR of the chosen project(s). What is the Payback period, discounted payback period, and...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 6.75% 0 1 2 3 4 CFS -$1,025 $380 $380 $380 $380 CFL -$2,150...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? Interest rate: 10.00% Year 0 1 2 3 4 CFS -$1,000 $380 $380 $380 $380...
The cash flows for four projects are shown below, along with the cost of capital for...
The cash flows for four projects are shown below, along with the cost of capital for these projects. If these projects are mutually exclusive, which one should be taken? A. Year:                         0                1            2              3            4                  5 Cash flow:                     -$12,000    $4000    $4000      $4000    $4000          $4000 Cost of Capital: 5.0% B. Year:                              0                1            2              3            4                  5 Cash flow:                     -$15,000    $4000    $4000      $4000    $4000          $4000 Cost of Capital: 7.0% C. Year:                              0                1            2              3            4                  5 Cash flow:                     -$20,000    $6000    $6000      $6000    $6000          $6000 Cost of Capital: 8.2% D. Year:                              0               ...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT