Question

In: Finance

Exercise 6.7: Projects A to E have cash flows as shown in the table below. The...

Exercise 6.7: Projects A to E have cash flows as shown in the table below. The Marr used to evaluate project is also shown.
Calculate NPW, NFW, and EUAW for each of these projects?
MARR 12% 7% 18% 6% 13%
Year Project A Project B Project C Project D Project E
0 ($36,000) ($56,000) ($25,000) ($278,000) ($321,000)
1 $5,000 $15,000 $5,000 $3,500 $40,000
2 $8,800 $17,400 $5,800 $40,600 $46,400
3 $10,208 $20,184 $6,728 $47,096 $53,824
4 $11,841 $23,413 $7,804 $54,631 $62,436
5 ($13,736) ($27,160) ($9,053) ($63,372) ($72,426)
6 $15,934 $31,505 ($10,502) $73,512 $84,014
7 $18,483 $36,546 $12,182 $85,274 $97,456
8 $21,440 $14,131 $98,918 ($113,049)
9 ($24,871) $114,745 $131,137
10 $33,824 $178,346

Solutions

Expert Solution

Present Worth PW = Cash Flow * PV Factor

PV Factor for Year n = 1/(1+r)n, where r is the MARR and n is the year

NPW = Σ Present Worth

Future Worth PW = Cash Flow * FV Factor

FV Factor for Year n = (1+r)n, where r is the MARR and n is the year

NFW = Σ Future Worth

Let the Equal Annual worth be P

=> P * sum of FV factor = NFW

MARR 12% 7% 18% 6% 13%
Year Project A FV Factor Project B FV Factor Project C FV Factor Project D FV Factor Project E FV Factor
0 -36000 1.00 -56000 1.00 -25000 1.00 -278000 1.00 321000 1.00
1 5000 1.12 15000 1.07 5000 1.18 3500 1.06 40000 1.13
2 8800 1.25 17400 1.14 5800 1.39 40600 1.12 46400 1.28
3 10208 1.40 20184 1.23 6728 1.64 47096 1.19 53824 1.44
4 11841 1.57 23413 1.31 7804 1.94 54631 1.26 62436 1.63
5 -13736 1.76 -27160 1.40 -9053 2.29 -63372 1.34 -72426 1.84
6 15934 1.97 31505 1.50 -10502 2.70 73512 1.42 84014 2.08
7 18483 2.21 36546 1.61 12182 3.19 85274 1.50 97456 2.35
8 21440 2.48 14131 3.76 98918 1.59 -113049 2.66
9 -24871 2.77 114745 1.69 131137 3.00
10 33824 3.11 178346 3.39
20.65 10.26 19.09 13.18 21.81

Project A
Sum of FV Factor = 20.65
NFV = 150883.28
=> 20.65P = 150883.28 => P = $7306.70

Project B
Sum of FV Factor = 10.26
NFV = 103259.29
=> 10.26 = 103259.29 => P = $10064.26

Project C
Sum of FV Factor = 19.09
NFV = 58020.55
=> 19.09 = 58020.55 => P = $3039.32

Project D
Sum of FV Factor = 13.18
NFV = 395602.87
​​​​​​​=> 13.18 = 395602.87 => P = $30015.39

Project A
Sum of FV Factor = 21.81
NFV = 1574473.41
​​​​​​​=> 21.81 = 1574473.41 => P = $72190.44


Related Solutions

The cash flows for two projects, A and B, are shown in the table, below. Notice...
The cash flows for two projects, A and B, are shown in the table, below. Notice that Project A has a life of 5 years and Project B has a 3 year life. Calculate the NPV of each project and calculate which should be adopted using the replacement chain approach. Assume that the cost of capital is 10%. Project CFs Project CFs Time A B 0 -100 -150 1 20 75 2 25 60 3 30 50 4 30 5...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 6.75% 0 1 2 3 4 CFS -$1,025 $380 $380 $380 $380 CFL -$2,150...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 7.75% 0 1 2 3 4 CF S -$1,025 $380 $380 $380 $380 CF...
A company is considering Projects S and L, whose cash flows are shown below. These projects...
A company is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO believes the IRR is the best selection criterion, while the CFO advocates other methods. If the decision is made by choosing the project with the higher IRR, how much, if any, value will be forgone, i.e., what's the: NPV and IRR of the chosen project(s). What is the Payback period, discounted payback period, and...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 6.75% 0 1 2 3 4 CFS -$1,025 $380 $380 $380 $380 CFL -$2,150...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? Interest rate: 10.00% Year 0 1 2 3 4 CFS -$1,000 $380 $380 $380 $380...
The cash flows for four projects are shown below, along with the cost of capital for...
The cash flows for four projects are shown below, along with the cost of capital for these projects. If these projects are mutually exclusive, which one should be taken? A. Year:                         0                1            2              3            4                  5 Cash flow:                     -$12,000    $4000    $4000      $4000    $4000          $4000 Cost of Capital: 5.0% B. Year:                              0                1            2              3            4                  5 Cash flow:                     -$15,000    $4000    $4000      $4000    $4000          $4000 Cost of Capital: 7.0% C. Year:                              0                1            2              3            4                  5 Cash flow:                     -$20,000    $6000    $6000      $6000    $6000          $6000 Cost of Capital: 8.2% D. Year:                              0               ...
) The cash flows for four projects are shown below, along with the cost of capital...
) The cash flows for four projects are shown below, along with the cost of capital for these projects. If these projects are mutually exclusive, which one should be taken? 28) A) Year: 0 1 2 3 4 5 Cash flow: -$20,000 $6000 $6000 $6000 $6000 $6000 Cost of Capital: 8.2% B) Year: 0 1 2 3 4 5 Cash flow: -$15,000 $4000 $4000 $4000 $4000 $4000 Cost of Capital: 7.0% C) Year: 0 1 2 3 4 5 Cash...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher MIRR rather than the one with the higher NPV, how much value will be forgone? Note that under some conditions choosing projects on the basis of the MIRR will cause $0.00 value to be lost. WACC: 10.75% 0 1 2 3 4 CFS -$1,100...
Kosovski Company is considering Projects S and L, whose cash flows are shown below. These projects...
Kosovski Company is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and are not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under some conditions choosing projects on the basis of the IRR will cause $0.00 value to be lost. WACC: 7.75 CFs Y0: $-1050 Y1 $675 $650 CFl Y0 $-1050 Y1 $360 Y2 360 Y3$360...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT