Question

In: Finance

You are analyzing two projects with the cash flows shown below. Year:                        0       &nb

You are analyzing two projects with the cash flows shown below.

Year:                        0                     1                  2                 3               4                    5           

Project 1:     -$6,000       $1,000      $1,000    $1,500    $2,000    $4,000     

Project 2:     -$6,000       $2,500      $2,000    $1,500    $1,000    $1,500

Construct an NPV chart with discount rates from 1% - 25%.   On your NPV chart, please identify and label the following points:

a) The IRR of project 1 (calculate the value and label the value on the chart)

b) The IRR of project 2 (calculate the value and label the value on the chart)

c) The discount rate at which the NPV of the two projects is equal (i.e., the incremental IRR). (calculate the value and label the value on the chart)

d) What is the simple payback period for each project?

e) If you can only do one of the two projects, which project will you do if your firm’s cost of capital is 6%? Why?

f) If you had no capital constraints (i.e., if you had unlimited funds), which projects would you do if your firm’s cost of capital was 12%?

g) If you could only do one project, which project would you do if your firm’s cost of capital was 12%? Why?

h) Which projects would you do if your firm’s cost of capital was 16%? Why?

Solutions

Expert Solution

IRR :
IRR is the Rate at which PV of Cash Inflows are equal to PV of Cash Outflows or Rate of growth is expected from project/ Investment. At IRR, NPV of Project/ Investment will be Zero. It assumes that intermediary Cfs are reinvested at IRR only.

IRR = Rate at which least +ve NPV + [ NPV at that Rate / Change in NPV due to 1% inc in disc rate ] * 1%

If IRR > Cost of Capital - Project can be accepted
IRR = Cost of Capital - Indifferebce Point - Project will be accepted / Rejected
IRR < Cost of Capital - Project will be erejected

NPV :
NPV is the difference between Present value of Cash Inflows and Present value of cash outflows.

NPV = PV of Cash Inflows - PV of Cash Outflows
If NPV > 0 , Project can be accepted
NPV = 0 , Indifference point. Project can be accepted/ Rejected.
NPV < 0 , Project will be rejected.

Part A:

Year CF PVF @13 % Disc CF PVF @14 % Disc CF
0 $         (6,000.00)          1.0000 $         -6,000.00         1.0000 $         -6,000.00
1 $          1,000.00          0.8850 $             884.96         0.8772 $             877.19
2 $          1,000.00          0.7831 $             783.15         0.7695 $             769.47
3 $          1,500.00          0.6931 $          1,039.58         0.6750 $          1,012.46
4 $          2,000.00          0.6133 $          1,226.64         0.5921 $          1,184.16
5 $          4,000.00          0.5428 $          2,171.04         0.5194 $          2,077.47
NPV $             105.35 $              -79.25

IRR = Rate at which least +ve NPV + [ NPV at that rate / Change in NPV due to Inc of 1% in Int Rate ] * 1%
= 13 % + [ 105.35 / ( 105.35 - ( -79.25) ) ] * 1 %
= 13 % + [ 105.35 / ( 184.6) ] * 1 %
= 13 % + [ 0.57 ] * 1 %
= 13 % + 0.57 %
= 13.57 %

Part B:

Year CF PVF @14 % Disc CF PVF @15 % Disc CF
0 $         (6,000.00)          1.0000 $         -6,000.00         1.0000 $         -6,000.00
1 $          2,500.00          0.8772 $          2,192.98         0.8696 $          2,173.91
2 $          2,000.00          0.7695 $          1,538.94         0.7561 $          1,512.29
3 $          1,500.00          0.6750 $          1,012.46         0.6575 $             986.27
4 $          1,000.00          0.5921 $             592.08         0.5718 $             571.75
5 $          1,500.00          0.5194 $             779.05         0.4972 $             745.77
NPV $             115.51 $              -10.01

IRR = Rate at which least +ve NPV + [ NPV at that rate / Change in NPV due to Inc of 1% in Int Rate ] * 1%
= 14 % + [ 115.51 / ( 115.51 - ( -10.01) ) ] * 1 %
= 14 % + [ 115.51 / ( 125.52) ] * 1 %
= 14 % + [ 0.92 ] * 1 %
= 14 % + 0.92 %
= 14.92 %
Part C:

Year CF of Project 1 CF of Project 2 Diff CF PVF @10 % Disc CF PVF @11 % Disc CF
0 $ -60,000.00 $ -60,000.00 $                 -            1.0000 $                 -            1.0000 $                 -  
1 $      1,000.00 $      2,500.00 $   -1,500.00          0.9091 $   -1,363.64          0.9009 $   -1,351.35
2 $      1,000.00 $      2,000.00 $   -1,000.00          0.8264 $      -826.45          0.8116 $      -811.62
3 $      1,500.00 $      1,500.00 $                 -            0.7513 $                 -            0.7312 $                 -  
4 $      2,000.00 $      1,000.00 $    1,000.00          0.6830 $        683.01          0.6587 $        658.73
5 $      4,000.00 $      1,500.00 $    2,500.00          0.6209 $    1,552.30          0.5935 $    1,483.63
NPV $          45.23 $        -20.61

Cross over Rate = Rate at which least +ve NPV + [ NPV at That rate / Change in NPV due to 1% inc in disc Rate ] * 1%

= 10 % + [ $ 45.23 / $ 65.85 ] * 1%
= 10 % + [ 0.69 ] * 1%
= 10 % + [ 0.69 % ]
= 10.69 %

Till Cross over Rate (10.69 % ) we can consider the Project with Higher NPV at cost of capital i.e Project 1
After Cross over Rate (10.69 % ) we can consider the Project with Lower NPV at cost of capital i.e Project 2

Part D:

Payback period:

Payback period is the period in which initial investment is recovered.

PBP = Year in which least +ve Closing Balance + [ Closing balance at that year / Cash flow in Next Year ]
If Actual PBP > Expected PBP - Project will be rejected
Actual PBP </= Expected PBP - Project will be accepted

Project 1:

Year Opening Balance Cash Flow Closing Balance
               1 $            6,000.00 $         1,000.00 $          5,000.00
               2 $            5,000.00 $         1,000.00 $          4,000.00
               3 $            4,000.00 $         1,500.00 $          2,500.00
               4 $            2,500.00 $         2,000.00 $             500.00
               5 $               500.00 $         4,000.00 $        -3,500.00

PBP = Year in which least +ve Closing Balance + [ Closing balance at that year / Cash flow in Next Year ]
= 4 Years + [ $ 500 / $ 4000 ]
= 4 Years + 0.13 Years
= 4.13 Years

Payback Period is 4.13 Years

Project 2:

Year Opening Balance Cash Flow Closing Balance
               1 $            6,000.00 $         2,500.00 $          3,500.00
               2 $            3,500.00 $         2,000.00 $          1,500.00
               3 $            1,500.00 $         1,500.00 $                      -  
               4 $                        -   $         1,000.00 $        -1,000.00
               5 $           -1,000.00 $         1,500.00 $        -2,500.00

PBP = Year in which least +ve Closing Balance + [ Closing balance at that year / Cash flow in Next Year ]
= 3 Years + [ $ 0 / $ 1000 ]
= 3 Years + 0 Years
= 3 Years Payback Period is 3 Years

As these questions are lengthy, Website is supporting part of them. Sorry for inconvinience.


Related Solutions

The cash flows for two projects, A and B, are shown in the table, below. Notice...
The cash flows for two projects, A and B, are shown in the table, below. Notice that Project A has a life of 5 years and Project B has a 3 year life. Calculate the NPV of each project and calculate which should be adopted using the replacement chain approach. Assume that the cost of capital is 10%. Project CFs Project CFs Time A B 0 -100 -150 1 20 75 2 25 60 3 30 50 4 30 5...
The cash flows for the two projects are as follows? ($ million): Project Year 0 Year...
The cash flows for the two projects are as follows? ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A - $ 100 $26 $28 $42 $52 B -$ 100    $52 $42 $28    $18 a. What is the IRR of each? project? b. What is the NPV of each project at your cost of? capital? c. At what cost of capital are you indifferent between the two? projects? d. What should you? do?
1.A company is analyzing two mutually exclusive projects, E and F, whose cash flows are shown...
1.A company is analyzing two mutually exclusive projects, E and F, whose cash flows are shown below: Years 0 1 2 3 4 Cash Flow E -$1,100 $900 $350 $50 $10 Cash Flow F -$1,100 $0 $300 $400 $850 The company's cost of capital is 12 percent, and it can get an unlimited amount of capital at that cost. What is the regular IRR (not MIRR) of the better project? (Hint: Note that the better project may or may not...
You are analyzing a project with the following cash flows: Year 0:      -240,000 Year 1:      +...
You are analyzing a project with the following cash flows: Year 0:      -240,000 Year 1:      + 10,000 Year 2:      + 55,000 Year 3:      +100,000 Year 4:      +380,000 What is the NPV for this project, using a 15% discount rate? Multiple Choice The Project has an NPV of $69,281 The Project has an NPV of $58,445 The Project has an NPV of $70,617 The Project has an NPV of $93,301 What is the IRR for this project? Multiple Choice The Project...
The following are the cash flows of two projects: Year Project A Project B 0 ?$...
The following are the cash flows of two projects: Year Project A Project B 0 ?$ 380 ?$ 380 1 210 280 2 210 280 3 210 280 4 210 If the opportunity cost of capital is 11%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.)
The following are the cash flows of two projects: Year Project A Project B 0 ?$...
The following are the cash flows of two projects: Year Project A Project B 0 ?$ 280 ?$ 280 1 160 180 2 160 180 3 160 180 4 160 If the opportunity cost of capital is 10%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.) Project A Profitability Index Project B
The following are the cash flows of two projects: Year Project A Project B 0 −$...
The following are the cash flows of two projects: Year Project A Project B 0 −$ 290 −$ 290 1 170 190 2 170 190 3 170 190 4 170 If the opportunity cost of capital is 11%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.)
The following are the cash flows of two projects: Year Project A Project B 0 $...
The following are the cash flows of two projects: Year Project A Project B 0 $ (330) $ (330) 1 160 230 2 160 230 3 160 230 4 160 If the opportunity cost of capital is 12%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.) Project Profitability Index: A B
The following are the cash flows of two projects: Year Project A Project B 0 ?$...
The following are the cash flows of two projects: Year Project A Project B 0 ?$ 220 ?$ 220 1 100 120 2 100 120 3 100 120 4 100 If the opportunity cost of capital is 10%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.)
The following are the cash flows of two projects: Year Project A Project B 0 $...
The following are the cash flows of two projects: Year Project A Project B 0 $ (260 ) $ (260 ) 1 140 160 2 140 160 3 140 160 4 140 a. Calculate the NPV for both projects if the opportunity cost of capital is 16%. (Do not round intermediate calculations. Round your answers to 2 decimal places.) Project A Project B b. Suppose that you can choose only one of these projects. Which would you choose? Project A...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT