In: Accounting
Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below.
Basic | Advanced | Total | ||||
Units produced | 110,000 | 330,000 | — | |||
Prime costs | $8,800,000 | $34,980,000 | $43,780,000 | |||
Machine hours | 110,000 | 550,000 | 660,000 | |||
Engineering hours | 500 | 4,500 | 5,000 | |||
Receiving orders | 400 | 1,200 | 1,600 | |||
Inspection hours | 700 | 1,400 | 2,100 | |||
Overhead costs: | ||||||
Machining | $9,240,000 | |||||
Engineering | 2,300,000 | |||||
Receiving | 480,000 | |||||
Inspecting products | 399,000 |
Required:
1. Calculate the four activity rates.
Machining rate | $ per machine hour |
Engineering rate | $ per hour |
Receiving rate | $ per order |
Inspecting rate | $ per hour |
2. Calculate the unit costs using activity rates. Round your answers to the nearest cent.
Unit cost | |
Basic | $ per unit |
Advanced | $ per unit |
Calculate the overhead cost per unit. Round your answers to the nearest cent.
Overhead Cost | |
Basic | $ per unit |
Advanced | $ per unit |
3. If consumption ratios instead of activity rates were used to assign costs instead of activity rates, show the cost assignment for the inspection activity.
Cost assignment | |
Basic | $ |
Advanced | $ |
Thank you for your patience. Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks! |
Roberts Company | ||||
Answer 1 | A | B | C=A/B | |
Activity cost pool | Activity Measure | Total cost | Activity usage | ABC rates |
Machining | Machine Hours | 9,240,000.00 | 660,000.00 | 14.00 |
Engineering | Engineering Hours | 2,300,000.00 | 5,000.00 | 460.00 |
Receiving | Receiving Orders | 480,000.00 | 1,600.00 | 300.00 |
Inspecting Products | Inspection Hours | 399,000.00 | 2,100.00 | 190.00 |
Total Cost | 12,419,000.00 | |||
Answer 2 | ||||
Basic | See C | D | E=C*D | |
Activity cost pool | Activity Measure | ABC Rates | Activity used | Cost assigned |
Machining | Machine Hours | 14.00 | 110,000.00 | 1,540,000.00 |
Engineering | Engineering Hours | 460.00 | 500.00 | 230,000.00 |
Receiving | Receiving Orders | 300.00 | 400.00 | 120,000.00 |
Inspecting Products | Inspection Hours | 190.00 | 700.00 | 133,000.00 |
Total Cost assigned | 2,023,000.00 | |||
Advanced | See C | F | G=C*F | |
Activity cost pool | Activity Measure | ABC Rates | Activity used | Cost assigned |
Machining | Machine Hours | 14.00 | 550,000.00 | 7,700,000.00 |
Engineering | Engineering Hours | 460.00 | 4,500.00 | 2,070,000.00 |
Receiving | Receiving Orders | 300.00 | 1,200.00 | 360,000.00 |
Inspecting Products | Inspection Hours | 190.00 | 1,400.00 | 266,000.00 |
Total Cost assigned | 10,396,000.00 |
Product cost per unit | Basic | Advanced | Note |
Prime costs | 880,000.00 | 34,980,000.00 | |
Overhead | 2,023,000.00 | 10,396,000.00 | H= See E, G |
Total product cost | 2,903,000.00 | 45,376,000.00 | I |
Number of units | 110,000.00 | 310,000.00 | J |
Product cost per unit | 26.39 | 146.37 | K=I/J |
Answer 2 | Basic | Advanced | |
Overhead assigned | 2,023,000.00 | 10,396,000.00 | See H |
Number of units | 110,000.00 | 330,000.00 | See I |
Overhead cost per unit | 18.39 | 31.50 | L=H/I |
Answer 3 | Basic | Advanced | Total | Note |
Prime costs | 880,000.00 | 34,980,000.00 | 35,860,000.00 | M |
Inspecting Products | 399,000.00 | N | ||
Company wide OH Rate | 1.11% | O=N/M | ||
Cost assignment for Inspecting Products | 9,791.41 | 389,208.59 | 399,000.00 | P=M*O |