In: Accounting
Activity-Based Product Costing
Roberts Company produces two weed eaters: basic and advanced. The company has four activities: machining, engineering, receiving, and inspection. Information on these activities and their drivers is given below.
Basic | Advanced | Total | ||||
Units produced | 100,000 | 300,000 | — | |||
Prime costs | $8,000,000 | $30,000,000 | $38,000,000 | |||
Machine hours | 100,000 | 500,000 | 600,000 | |||
Engineering hours | 400 | 3,600 | 4,000 | |||
Receiving orders | 400 | 1,200 | 1,600 | |||
Inspection hours | 800 | 1,600 | 2,400 | |||
Overhead costs: | ||||||
Machining | $6,000,000 | |||||
Engineering | 2,000,000 | |||||
Receiving | 560,000 | |||||
Inspecting products | 360,000 |
Required:
1. Calculate the four activity rates.
Machining rate | $ per machine hour |
Engineering rate | $ per hour |
Receiving rate | $ per order |
Inspecting rate | $ per hour |
2. Calculate the unit costs using activity rates. Round your answers to the nearest cent.
Unit cost | |
Basic | $ per unit |
Advanced | $ per unit |
Calculate the overhead cost per unit. Round your answers to the nearest cent.
Overhead Cost | |
Basic | $ per unit |
Advanced | $ per unit |
3. If consumption ratios instead of activity rates were used to assign costs instead of activity rates, show the cost assignment for the inspection activity.
Part 1
Machining rate = $6,000,000/600,000(100000+500000) = $10per machine hour
Engineering rate: $2,000,000/4,000(400+3600) = $500 per hour
Receiving rate: $560,000/1,600(400+1200) = $350 per order
Inspecting rate: $360,000/2,400(800+1600)= $150 per hour
Part 2
Basic | advanced | |
Prime costs : | 8000000 | 30000000 |
Overhead costs : | ||
Machining | ||
10*100000 | 1000000 | |
10*500000 | 5000000 | |
Engineering | ||
500*400 | 200000 | |
500*3600 | 1800000 | |
Receiving | ||
350*400 | 140000 | |
350*1200 | 420000 | |
Inspecting products | ||
150*800 | 120000 | |
150*1600 | 240000 | |
Total manufacturing costs | 9460000 | 37460000 |
Units of production | 100000 | 300000 |
Unit cost | 94.60 | 124.87 |
Prime cost per unit:
Basic = $8,000,000 ÷ 100,000 = $80.00
Advanced = $30,000,000 ÷ 300,000 = $100.00
Overhead cost per unit:
Basic: $94.60 − $80.00 = $14.60
Advance : $124.87 − $100.00 = 24.87
Part 3
Using the consumption ratios instead of activity rates this will yield exactly the same overhead assignments because the activity rates is an actual activity usage as same as the expected usage.