Question

In: Finance

Here is the information that William has accumulated so far: The Capital Budgeting Projects He must...

Here is the information that William has accumulated so far:

The Capital Budgeting Projects

He must choose one of the four capital budgeting projects listed below:  

Table 1

t

A

B

C

D

0

      (19,000,000)

      (20,000,000)

      (18,900,000)

       (19,500,000)

1

         5,200,000

         5,700,000

         6,080,000

          6,600,000

2

         8,300,000

         8,000,000

         6,080,000

          8,100,000

3

         6,100,000

         6,300,000

         6,080,000

          6,100,000

4

         6,100,000

         4,400,000

         6,080,000

          6,100,000

Risk

High

Average

Low

Average

Table 1 shows the expected after-tax operating cash flows for each project. All projects are expected to have a 4 year life. The projects differ in size (the cost of the initial investment), and their cash flow patterns are different. They also differ in risk as indicated in the above table.

The capital budget is $22 million and the projects are mutually exclusive.

Capital Structures

Grand Island Hotel has the following capital structure, which is considered to be optimal:

Debt  

45%

Preferred Equity

5%

Common Equity

50%

100%

   

Cost of Capital

William knows that in order to evaluate the projects he will have to determine the cost of capital for each of them. He has been given the following data, which he believes will be relevant to his task.

(1)The firm’s tax rate is 38%.

(2) Grand Island Hotel has issued a 9% semi-annual coupon bond with 15 years term to maturity. The current trading price is $960.

(3) The firm has issued some preferred stock which pays an annual 8.5% dividend of $100 par value, and the current market price is $98.

(4) The firm’s stock is currently selling for $88 per share. Its last dividend (D0) was $4.5, and dividends are expected to grow at a constant rate of 7.5%. The current risk free return offered by Treasury security is 2.5%, and the market portfolio’s return is 8%. Grand Island Hotel has a beta of 2.1. For the bond-yield-plus-risk-premium approach, the firm uses a risk premium of 3.9%.

(5) The firm adjusts its project WACC for risk by adding 1.8% to the overall WACC for high-risk projects and subtracting 2% for low-risk projects.

William knows that Grand Island Hotel executives have favored IRR in the past for making their capital budgeting decisions. His professor at Seattle U. said NPV was better than IRR. His textbook says that MIRR is also better than IRR. He is the new kid on the block and must be prepared to defend his recommendations.

First, however, William must finish the analysis and write his report. To help begin, he has formulated the following questions:

  1. What is the firm’s cost of debt?
  1. What is the cost of preferred stock for Grand Island Hotel?
  1. Cost of common equity

(1) What is the estimated cost of common equity using the CAPM approach?

(2) What is the estimated cost of common equity using the DCF approach?

(3) What is the estimated cost of common equity using the bond-yield-plus-risk-premium approach?

(4) What is the final estimate for rs?

  1. What is Grand Island Hotel’s overall WACC?
  1. Do you think the firm should use the single overall WACC as the hurdle rate for each of its projects? Explain.
  1. What is the WACC for each project? Place your numerical solutions in Table 2.
  1. Calculate all relevant capital budgeting measures for each project, and place your numerical solutions in Table 2.

Table 2

A

B

C

D

WACC

NPV

IRR

MIRR

Solutions

Expert Solution

a] Before tax cost of debt = YTM
YTM using an online calculator = 9.51%
[Inputs: Current price = $960; coupon 9%; Years to
maturity 15, payment interval = 2]
After tax cost of debt = 9.51%*(1-38%) = 5.90%
b] Cost of preferred stock = 8.5/98 = 8.67%
c] Constant dividend growth model:
Cost of equity = 4.5*1.075/88+0.075 = 13.00%
CAPM:
Cost of equity = 2.5%+2.1*(8%-2.5%) = 14.05%
Bond yield plus risk premium:
Cost of equity = 9.51%+3.9% = 13.41%
Final estimate for rs = (13%+14.05%+13.41%)/3 = 13.49%
d] Overall WACC = 5.90%*45%+8.67%*5%+13.49%*50% = 9.83%
e] No, the overall WACC should not be used as the
discount rate for all the projects as the projects
have different risks. Adjustments in the WACC for
projects with lower/higher risk than the average
projects.
f] WACC of each project is:
A = 9.83%+1.8% = 11.63%
B = 9.83%+0 = 9.83%
C = 9.83%-2.00% = 7.83%
D = 9.83%+0% = 9.83%
g] PROJECT A:
Year Cash flows PVIF at 11.63% PV at 11.63% PVIF at 13% PV at 13% PVIF at 14% PV at 14% FVIF at 11.63% FV at 11.63%
0 $ -1,90,00,000 1.00000 $-1,90,00,000 1 $ -1,90,00,000 1 $ -1,90,00,000
1 $       52,00,000 0.89582 $      46,58,246 0.88496 $      46,01,770 0.87719 $      45,61,404 1.39105 $    72,33,461
2 $       83,00,000 0.80249 $      66,60,644 0.78315 $      65,00,117 0.76947 $      63,86,580 1.24613 $1,03,42,843
3 $       61,00,000 0.71888 $      43,85,176 0.69305 $      42,27,606 0.67497 $      41,17,326 1.11630 $    68,09,430
4 $       61,00,000 0.64399 $      39,28,313 0.61332 $      37,41,244 0.59208 $      36,11,690 1.00000 $    61,00,000
$        6,32,380 $            70,738 $       -3,23,000 $3,04,85,734
NPV = $         6,32,380
IRR = 13%+1%*70738/(70738+323000) = 13.18%
MIRR = (30485734/19000000)^(1/4)-1 = 12.55%
PROJECT B:
Year Cash flows PVIF at 9.83% PV at 9.83% PVIF at 8% PV at 8% PVIF at 9% PV at 9% FVIF at 9.83% FV at 9.83%
0 $ -2,00,00,000 1.00000 $-2,00,00,000 1 $ -2,00,00,000 1 $ -2,00,00,000
1 $       57,00,000 0.91050 $      51,89,839 0.92593 $      52,77,778 0.91743 $      52,29,358 1.32484 $    75,51,580
2 $       80,00,000 0.82901 $      66,32,053 0.85734 $      68,58,711 0.84168 $      67,33,440 1.20626 $    96,50,103
3 $       63,00,000 0.75481 $      47,55,296 0.79383 $      50,01,143 0.77218 $      48,64,756 1.09830 $    69,19,290
4 $       44,00,000 0.68725 $      30,23,909 0.73503 $      32,34,131 0.70843 $      31,17,071 1.00000 $    44,00,000
$      -3,98,902 $         3,71,763 $           -55,375 $2,85,20,973
NPV = $       -3,98,902
IRR = 8%+1%*371763/(371763+55375) = 8.87%
MIRR = (28520973/20000000)^(1/4)-1 = 9.28%
PROJECT C:
Year Cash flows PVIF at 7.83% PV at 7.83% PVIF at 10% PV at 10% PVIF at 11% PV at 11% FVIF at 7.83% FV at 7.83%
0 $ -1,89,00,000 1.00000 $-1,89,00,000 1 $ -1,89,00,000 1 $ -1,89,00,000
1 $       60,80,000 0.92739 $      56,38,505 0.90909 $      55,27,273 0.90090 $      54,77,477 1.25377 $    76,22,938
2 $       60,80,000 0.86004 $      52,29,069 0.82645 $      50,24,793 0.81162 $      49,34,664 1.16273 $    70,69,404
3 $       60,80,000 0.79759 $      48,49,364 0.75131 $      45,67,994 0.73119 $      44,45,644 1.07830 $    65,56,064
4 $       60,80,000 0.73968 $      44,97,231 0.68301 $      41,52,722 0.65873 $      40,05,084 1.00000 $    60,80,000
$      13,14,168 $         3,72,782 $           -37,130 $2,73,28,406
NPV = $       13,14,168
IRR = 10%+1%*372782/(372782+37130) = 10.91%
MIRR = (27328406/18900000)^(1/4)-1 = 9.66%
PROJECT D:
Year Cash flows PVIF at 9.83% PV at 9.83% PVIF at 15% PV at 15% PVIF at 14% PV at 14% FVIF at 9.83% FV at 9.83%
0 $ -1,95,00,000 1.00000 $-1,95,00,000 1 $ -1,95,00,000 1 $ -1,95,00,000
1 $       66,00,000 0.91050 $      60,09,287 0.86957 $      57,39,130 0.87719 $      57,89,474 1.32484 $    87,43,934
2 $       81,00,000 0.82901 $      67,14,954 0.75614 $      61,24,764 0.76947 $      62,32,687 1.20626 $    97,70,729
3 $       61,00,000 0.75481 $      46,04,335 0.65752 $      40,10,849 0.67497 $      41,17,326 1.09830 $    66,99,630
4 $       61,00,000 0.68725 $      41,92,238 0.57175 $      34,87,695 0.59208 $      36,11,690 1.00000 $    61,00,000
$      20,20,814 $       -1,37,562 $         2,51,177 $3,13,14,294
NPV = $       20,20,814
IRR = 14%+1%*251177/(251177+137562) = 14.65%
MIRR = (31314294/19500000)^(1/4)-1 = 12.57%
CHOICE:
The results are tabulated below:
Project NPV IRR MIRR Discount Rate Accept/Reject
A $         6,32,380 13.18% 12.55% 11.63% Accept
B $       -3,98,902 8.87% 9.28% 9.83% Reject
C $       13,14,168 10.91% 9.66% 7.83% Accept
D $       20,20,814 14.65% 12.57% 9.83% Accept
Of the 4 mutually exclusive projects, Project B is to be rejected as it has negative NPV and IRR/MIRR are less than required
rate of return.
Of the remaining 3 projects, Project D with higher NPV, IRR and MIRR is to be selected.

Related Solutions

The Capital Budgeting Projects She must choose one of the four capital budgeting projects listed below:  ...
The Capital Budgeting Projects She must choose one of the four capital budgeting projects listed below:   Table 1 t A B C D 0         (19,500,000)         (21,000,000)         (16,500,000)         (18,000,000) 1            7,500,000            6,500,000            5,200,000            7,500,000 2            7,500,000            7,200,000            5,200,000            5,800,000 3            5,000,000            8,000,000            6,300,000            4,400,000 4            3,500,000            3,000,000            5,900,000            4,500,000 Risk Average Average High Low Table 1 shows the expected after-tax operating...
XYZ Inc., has $100 to spend on capital budgeting projects. Which combination of projects should the...
XYZ Inc., has $100 to spend on capital budgeting projects. Which combination of projects should the company undertake? Note that the goal is choose the combination of projects that maximizes the firm’s value. Project cost NPV IRR A $30 $9 20% B $60 $15 13% C $45 $20 12% D $35 $13 17% E $25 $12 16% a. C, A b. C, E c. C, E, A d. B, C, D
Describe the 8 types of capital budgeting projects.
Describe the 8 types of capital budgeting projects.
13. What is capital budgeting? Why capital budgeting decisions are so important to business? 14. What...
13. What is capital budgeting? Why capital budgeting decisions are so important to business? 14. What are the five steps of capital budgeting? 15. Role of financial analysis 16. Cash flow estimation 17. What is breakeven analysis in capital budgeting? 18. Uneven cash flows stream and how to approach these problems 19. Describe payback period, NPV and IRR? 20. What is MIRR?
Here is my C++ program so far. Is there anyway I can make it display an...
Here is my C++ program so far. Is there anyway I can make it display an error if the user enters a float? Thanks #include <iostream> using namespace std; // Creating a constant for the number of integers in the array const int size = 10; int main() { // Assigning literals to the varibles int a[size]; int sum=0; float avg; // For loop that will reiterate until all 10 integers are entered by the user for(int i=0; i<size; i++)...
Monty Inc. is comparing several alternative capital budgeting projects as shown below:                      Projects    &nbsp
Monty Inc. is comparing several alternative capital budgeting projects as shown below:                      Projects                            A             B             C       Initial investment $82000    $122000    $162000    Present value of net cash flows 92000    112000    202000   Using the profitability index, the projects rank as C, A, B. A, C, B. C, B, A. A, B, C.
Monty Inc. is comparing several alternative capital budgeting projects as shown below:                      Projects    &nbsp
Monty Inc. is comparing several alternative capital budgeting projects as shown below:                      Projects                            A             B             C       Initial investment $82000    $122000    $162000    Present value of net cash flows 92000    112000    202000   Using the profitability index, the projects rank as C, A, B. A, C, B. C, B, A. A, B, C.
In capital budgeting: a. ​ If a firm accepts projects without regard for risk, then the...
In capital budgeting: a. ​ If a firm accepts projects without regard for risk, then the company can change its overall risk profile firm as perceived by investors. b. ​ Projects are thought to be incremental to the normal business of the firm. c. ​All of the above. d. ​ Risk is important and should be included in the analysis but often isn’t.
What are the advantages and disadvantages of zero-base budgeting? Why is the capital budgeting process so...
What are the advantages and disadvantages of zero-base budgeting? Why is the capital budgeting process so important to a company’s success?
What is capital rationing? How capital budgeting projects are chosen when capital rationing exist? Explain.
What is capital rationing? How capital budgeting projects are chosen when capital rationing exist? Explain.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT