Question

In: Accounting

Monty Inc. is comparing several alternative capital budgeting projects as shown below:                      Projects    &nbsp

Monty Inc. is comparing several alternative capital budgeting projects as shown below:

                     Projects                     
      A             B             C      
Initial investment $82000    $122000    $162000   
Present value of net cash flows 92000    112000    202000  

Using the profitability index, the projects rank as

C, A, B.

A, C, B.

C, B, A.

A, B, C.

Solutions

Expert Solution

Answer: C, A, B

Explanation

1. Computation of the project profitability index for each investment proposal.
A B C
Present value of net cash flows       92,000.00           112,000.00     202,000.00
Initial Investment       82,000.00           122,000.00     162,000.00
Project Profitability Index 112.20% 91.80% 124.69%
(Net Present Value / Initial Investment)
2. Ranking the proposals in terms of preference:
A B C
Rank 2 3 1
Explanation
Proposal C has the highest project profitability index , hence it ranks first.

Related Solutions

Monty Inc. is comparing several alternative capital budgeting projects as shown below:                      Projects    &nbsp
Monty Inc. is comparing several alternative capital budgeting projects as shown below:                      Projects                            A             B             C       Initial investment $82000    $122000    $162000    Present value of net cash flows 92000    112000    202000   Using the profitability index, the projects rank as C, A, B. A, C, B. C, B, A. A, B, C.
The Capital Budgeting Projects She must choose one of the four capital budgeting projects listed below:  ...
The Capital Budgeting Projects She must choose one of the four capital budgeting projects listed below:   Table 1 t A B C D 0         (19,500,000)         (21,000,000)         (16,500,000)         (18,000,000) 1            7,500,000            6,500,000            5,200,000            7,500,000 2            7,500,000            7,200,000            5,200,000            5,800,000 3            5,000,000            8,000,000            6,300,000            4,400,000 4            3,500,000            3,000,000            5,900,000            4,500,000 Risk Average Average High Low Table 1 shows the expected after-tax operating...
True or false Capital budgeting is considering alternative projects in choosing the most profitable
True or false Capital budgeting is considering alternative projects in choosing the most profitable
Petram company is considering two alternative capital budgeting projects. Project A is an investment of $300,000...
Petram company is considering two alternative capital budgeting projects. Project A is an investment of $300,000 to renovate office facilities. Project B is an investment of $600,000 to expand diagnostic capabilities. Relevant cash flow data for the two projects over their expected two-year lives are as follows: Year 1 Year 2    Pr.     Cash Flow    Pr.        Cash Flow Project A 0.18 $     0 0.08 $    0 0.64 100,000 0.84 100,000 0.18 200,000 0.08 200,000 Project...
Discuss the four alternative methods for evaluating capital budgeting projects? Explain the advantages and disadvantages of...
Discuss the four alternative methods for evaluating capital budgeting projects? Explain the advantages and disadvantages of each method?
what are alternative capital projects?
what are alternative capital projects?
evaluate alternative capital projects
evaluate alternative capital projects
XYZ Inc., has $100 to spend on capital budgeting projects. Which combination of projects should the...
XYZ Inc., has $100 to spend on capital budgeting projects. Which combination of projects should the company undertake? Note that the goal is choose the combination of projects that maximizes the firm’s value. Project cost NPV IRR A $30 $9 20% B $60 $15 13% C $45 $20 12% D $35 $13 17% E $25 $12 16% a. C, A b. C, E c. C, E, A d. B, C, D
The cash flows for four projects are shown below, along with the cost of capital for...
The cash flows for four projects are shown below, along with the cost of capital for these projects. If these projects are mutually exclusive, which one should be taken? A. Year:                         0                1            2              3            4                  5 Cash flow:                     -$12,000    $4000    $4000      $4000    $4000          $4000 Cost of Capital: 5.0% B. Year:                              0                1            2              3            4                  5 Cash flow:                     -$15,000    $4000    $4000      $4000    $4000          $4000 Cost of Capital: 7.0% C. Year:                              0                1            2              3            4                  5 Cash flow:                     -$20,000    $6000    $6000      $6000    $6000          $6000 Cost of Capital: 8.2% D. Year:                              0               ...
) The cash flows for four projects are shown below, along with the cost of capital...
) The cash flows for four projects are shown below, along with the cost of capital for these projects. If these projects are mutually exclusive, which one should be taken? 28) A) Year: 0 1 2 3 4 5 Cash flow: -$20,000 $6000 $6000 $6000 $6000 $6000 Cost of Capital: 8.2% B) Year: 0 1 2 3 4 5 Cash flow: -$15,000 $4000 $4000 $4000 $4000 $4000 Cost of Capital: 7.0% C) Year: 0 1 2 3 4 5 Cash...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT