In: Accounting
Question 2 25 Marks
The percentage of completion method (based on costs) is used to calculate profit on contracts, but only once contracts are 30% or completed or more.
REQUIRED:
2.1 Discuss the difference between the Work Certified Method and the Percentage of C0mpletion method. (6)
2.2 Calculate the profit/loss that can be brought into account for the financial period under review for each of the contracts in the records of Ovitoto Concrete Investment Cc. (19 . the table to use is below
Ovitoto Concrete Investment Cc presented you with the following information for the contracts awarded in Sept 2017; Contract |
|||
Okahandja Road |
Midgard Road |
||
Contract Price |
1 499 500 |
1 950 550 |
|
Work certified |
1 249 500 |
1 550 550 |
|
Cost of work certified |
1 199 500 |
1 400 550 |
|
Cost of uncertified work |
999 500 |
1 210 550 |
|
Cash received |
1 149 500 |
1 400 550 |
|
Total expected cost (including costs incurred) |
1 299 500 |
1 850 550 |
2.1.. Both are different types of value based methods of to measure the stage of completion of construction contracts -to assign values upto that stage -so as to recognise revenues,costs & profits. |
As normally, the construction units measure the stage of completion of a contract, at the end of their reporting period using one of the following methods: |
Cost to Cost Basis(% of completion method) |
(Cost to date/(Cost to date + Future Cost)) *100 |
Physical Proportion or Work Certified Method: |
(Work Certified to date/ Total Contract Price)* 100 |
Survey Method: |
As per the assessment survey completed by qualified professionals |
2.2 Work-certfied method: | ||
Total Contract Price | 1499500 | 1950550 |
Value of Work certified to-date | 1249500 | 1550550 |
% of completion as per work certified method-(Work certified/Total contract price) | 83.33% | 79.49% |
So, revenue to be recognised= Value of work certified | 1249500 | 1550550 |
Less: Cost of work certified | 1199500 | 1400550 |
So,profit to be recognised | 50000 | 150000 |