Question

In: Accounting

Question 2 25 Marks The percentage of completion method (based on costs) is used to calculate...

Question 2 25 Marks

The percentage of completion method (based on costs) is used to calculate profit on contracts, but only once contracts are 30% or completed or more.

REQUIRED:

2.1 Discuss the difference between the Work Certified Method and the Percentage of C0mpletion method. (6)

2.2 Calculate the profit/loss that can be brought into account for the financial period under review for each of the contracts in the records of Ovitoto Concrete Investment Cc. (19 . the table to use is below

Ovitoto Concrete Investment Cc presented you with the following information for the contracts awarded in Sept 2017; Contract

Okahandja Road

Midgard Road

Contract Price

1 499 500

1 950 550

Work certified

1 249 500

1 550 550

Cost of work certified

1 199 500

1 400 550

Cost of uncertified work

999 500

1 210 550

Cash received

1 149 500

1 400 550

Total expected cost (including costs incurred)

1 299 500

1 850 550

Solutions

Expert Solution

2.1.. Both are different types of value based methods of to measure the stage of completion of construction contracts -to assign values upto that stage -so as to recognise revenues,costs & profits.
As normally, the construction units measure the stage of completion of a contract, at the end of their reporting period using one of the following methods:
Cost to Cost Basis(% of completion method)
(Cost to date/(Cost to date + Future Cost)) *100
Physical Proportion or Work Certified Method:
(Work Certified to date/ Total Contract Price)* 100
Survey Method:
As per the assessment survey completed by qualified professionals
2.2   Work-certfied method:
Total Contract Price 1499500 1950550
Value of Work certified to-date 1249500 1550550
% of completion as per work certified method-(Work certified/Total contract price) 83.33% 79.49%
So, revenue to be recognised= Value of work certified 1249500 1550550
Less: Cost of work certified 1199500 1400550
So,profit to be recognised 50000 150000

Related Solutions

Question # 2 — Percentage-of-completion method. Arshdeep Builders contracted to build a high-rise for $35,000,000. Construction...
Question # 2 — Percentage-of-completion method. Arshdeep Builders contracted to build a high-rise for $35,000,000. Construction began in 2018 and is expected to be completed in 2020. Data for 2018 and 2019 are: Costs incurred to date Estimated costs to complete Arshdeep uses the percentage-of-completion method. Instructions 2018 $4,500,000 18,000,000 2019 $13,000,000 12,000,000 (a) How much gross profit should be reported for 2018? Show your computation. (b) How much gross profit should be reported for 2019? (c) Make the journal...
In the construction industry, the percentage of completion (POC) method is the most common accounting method....
In the construction industry, the percentage of completion (POC) method is the most common accounting method. Explain what business environments create favorable conditions for a company to use this POC method.
Long‐term contract based on percentage of completion method Jim’s Construction Co. has a $6,800,000 contract which...
Long‐term contract based on percentage of completion method Jim’s Construction Co. has a $6,800,000 contract which began on January 1, 2015 to build a new football stadium with an expected completion date of October 31, 2017. The following table provides information gathered during the construction period. Jim uses the percentage completion method to account for this contract.                                                                                                                                  2015 2016 2017 Construction costs incurred during the year 2,040,000 2,932,500 1,657,500 Estimated costs to complete 3,060,000 1,657,500 0 Billings during the...
Boxer Corporation has consistently used the percentage-of-completion method of recognizing income. In 2018, Boxer started work...
Boxer Corporation has consistently used the percentage-of-completion method of recognizing income. In 2018, Boxer started work on a $45,000,000 construction contract that was completed in 2019. The following information was taken from Boxer's accounting records in 2018. Progress billings $15,400,000 Costs incurred 14,700,000 Collections 9,600,000 Estimated costs to complete 21,400,000 What amount of gross profit should Boxer have recognized in 2018 on this project?
Madoff Construction Company uses the percentage of completion method (cost to cost method) for their long...
Madoff Construction Company uses the percentage of completion method (cost to cost method) for their long term construction contracts..... They were working on a contract for which they would receive $900,000 at completion.... In 2024, they reported a gross profit of 58,440..... 2025 was a disastrous year for the company. As of the end of the year, they had incurred costs of $800,000 (which includes costs for both 2024 and 2025) , and think it is going to cost 120,266...
Make Turner’s 2021 journal entries using the percentage-of-completion method.
Turner, Inc. began work on a $7,000,000 contract in 2021 to construct an office building. During 2021, Turner, Inc. incurred costs of $1,700,000, billed its customers for $1,200,000, and collected $960,000. At December 31, 2021, the estimated future costs to complete the project total $3,300,000. Make Turner’s 2021 journal entries using the percentage-of-completion method.  
QUESTION 2 (25 Marks) Marvel Industries is a South African based manufacturer of “Solasheet”, an award-winning...
QUESTION 2 Marvel Industries is a South African based manufacturer of “Solasheet”, an award-winning skylight. The company is currently investigating two investment projects. The information is given below: Project Chuck Involves extending the company’s production facility at Westville, Kwa-Zulu Natal. The plant will cost R12 million and is expected to create an additional annual profit of R2.26 million for the 8 years life of the project. The following expenses were included in the annual profit:  Depreciation was calculated on...
Question 2 (25 marks) The following statements relate to general principles or terms used inthe audit...
Question 2 The following statements relate to general principles or terms used inthe audit of financial statements. Identify at least two errors from eachof the following statements (a) to (e), and then explain why these are errors and suggest corrections. a )The objective of an audit of financial statements is to enable auditorsto give a true and correct view in all respects in accordance with an identified financial reporting framework. b )Fraud refers to an unintentional act by one or...
When we formed the construction contract, do we need the margin percentage for the percentage-of-completion method?...
When we formed the construction contract, do we need the margin percentage for the percentage-of-completion method? I am trying to calculate the revenue. I have information about the estimated cost, cost incurred per year, the finalized cost, project years, and margin. However, I am not sure it is necessary. It said that the worker wants to add a margin of % on its cost estimate. Can anyone help me to use an example to explain to me?
Green Earth Corp. is a construction company that uses the percentage of completion method. They won...
Green Earth Corp. is a construction company that uses the percentage of completion method. They won a contract to build an apartment building in 2019 for $60,000,000. Please record the journal entries relating to each of the events below. Also assume that the company has a December 31 year-end and records adjusting entries only at year-end. a) Actual costs incurred to the end of 2019 were $36,000,000 and all was paid with cash. b) Billings made to the client amounted...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT