Question

In: Accounting

Boxer Corporation has consistently used the percentage-of-completion method of recognizing income. In 2018, Boxer started work...

Boxer Corporation has consistently used the percentage-of-completion method of recognizing income. In 2018, Boxer started work on a $45,000,000 construction contract that was completed in 2019. The following information was taken from Boxer's accounting records in 2018.

Progress billings $15,400,000

Costs incurred 14,700,000

Collections 9,600,000

Estimated costs to complete 21,400,000

What amount of gross profit should Boxer have recognized in 2018 on this project?

Solutions

Expert Solution

PARTICULARS AMOUNT(in $)
costs incurred till 2018 14,700,000
estimated costs to complete 21,400,000
total cost of construction 36,100,000
(less) contract price 45,000,000
gain/(loss) 89,000,000

an expected loss on the construction contract should be recognised as an expense immediately.

contract revenue is recognised only to the extent of costs incurred that are expected to be recovered.as the outcome of the contract cannot be estimated reliably,no profit is recognised

as per AS 7 CONSTRUCTION CONTRACT when the outcome of the construction contract can be estimated reliably, contract revenue and contract costs associated with the construction contract shoul be recognised as income or expense respectively by reference to the stage of completion of the contract activity at the reporting date

accordingly,

contract work in progress= 14,700,000/36,100,000*100

40.72%

proportion of total contract value to be recognised as turnover = 40.72% of $45,000,000

= $18,324,000


Related Solutions

Which of the following methods of recognizing income is most recommended? a. Billings method b. Percentage-of-Completion...
Which of the following methods of recognizing income is most recommended? a. Billings method b. Percentage-of-Completion method
Horner Construction Co. uses the percentage-of-completion method. In 2018, Horner began work on a contract for...
Horner Construction Co. uses the percentage-of-completion method. In 2018, Horner began work on a contract for $22,000,000; it was completed in 2019. The following cost data pertain to this contract for the year-ended 2018... Cost incurred during the year: $7,800,000... Estimated costs to complete: $5,200,000. The following cost data pertain to this contract for the year-ended 2019... Cost incurred during the year: $5,600,000... Estimated costs to complete: n/a. If the completed-contract method of accounting was used, the amount of gross...
Question 2 25 Marks The percentage of completion method (based on costs) is used to calculate...
Question 2 25 Marks The percentage of completion method (based on costs) is used to calculate profit on contracts, but only once contracts are 30% or completed or more. REQUIRED: 2.1 Discuss the difference between the Work Certified Method and the Percentage of C0mpletion method. (6) 2.2 Calculate the profit/loss that can be brought into account for the financial period under review for each of the contracts in the records of Ovitoto Concrete Investment Cc. (19 . the table to...
Cullumber Construction Company uses the percentage-of-completion method of accounting. In 2020, Cullumber began work under a...
Cullumber Construction Company uses the percentage-of-completion method of accounting. In 2020, Cullumber began work under a non-cancellable contract #E2-D2, which provided for a contract price of $2,178,000. Other details follow: 2020 2021 Costs incurred during the year $706,640 $1,422,000 Estimated costs to complete, as at December 31 899,360 0 Billings during the year (non-refundable) 420,000 1,713,600 Collections during the year 352,000 1,481,000 How much revenue should be recognized in 2020 and in 2021? 2020 2021 Revenue to be recognized $enter...
In the construction industry, the percentage of completion (POC) method is the most common accounting method....
In the construction industry, the percentage of completion (POC) method is the most common accounting method. Explain what business environments create favorable conditions for a company to use this POC method.
Nash Construction Company uses the percentage-of-completion method of accounting. In 2017, Nash began work under contract...
Nash Construction Company uses the percentage-of-completion method of accounting. In 2017, Nash began work under contract #E2-D2, which provided for a contract price of $2,234,000. Other details follow: 2017 2018 Costs incurred during the year $615,980 $1,420,000 Estimated costs to complete, as of December 31 1,005,020 –0– Billings to date 413,000 2,234,000 Collections during the year 351,000 1,530,000 Prepare a complete set of journal entries for 2017 (using the percentage-of-completion method). (Credit account titles are automatically indented when amount is...
Madoff Construction Company uses the percentage of completion method (cost to cost method) for their long...
Madoff Construction Company uses the percentage of completion method (cost to cost method) for their long term construction contracts..... They were working on a contract for which they would receive $900,000 at completion.... In 2024, they reported a gross profit of 58,440..... 2025 was a disastrous year for the company. As of the end of the year, they had incurred costs of $800,000 (which includes costs for both 2024 and 2025) , and think it is going to cost 120,266...
Make Turner’s 2021 journal entries using the percentage-of-completion method.
Turner, Inc. began work on a $7,000,000 contract in 2021 to construct an office building. During 2021, Turner, Inc. incurred costs of $1,700,000, billed its customers for $1,200,000, and collected $960,000. At December 31, 2021, the estimated future costs to complete the project total $3,300,000. Make Turner’s 2021 journal entries using the percentage-of-completion method.  
PERCENTAGE OF COMPLETION METHOD AttiK Construction Company currently has a long-term construction project. The project has...
PERCENTAGE OF COMPLETION METHOD AttiK Construction Company currently has a long-term construction project. The project has a contract price of $130,000,000 with total estimated costs of $100,000,000. AttiK appropriately uses the percentage of completion method. After 2 years of construction, the following costs have been accumulated: Actual cost incurred, Year 1 $30,000,000 Total estimated costs remaining after Year 1 70,000,000 Actual cost incurred, Year 2 50,000,000 Total estimated cost remaining after Year 2 20,000,000 Determine the gross profit for each...
Ex. 18-134—Percentage-of-completion method. Penner Builders contracted to build a high-rise for €35,000,000. Construction began in 2018...
Ex. 18-134—Percentage-of-completion method. Penner Builders contracted to build a high-rise for €35,000,000. Construction began in 2018 and is expected to be completed in 2020. Data for 2018 and 2019 are:    2018 2019 costs incurred to date    4.5M 13M Estimated cost to complete 18M. 12M Penner uses the percentage-of-completion method. Instructions A: How much gross profit should be reported for 2018? Show your computation. B: How much gross profit should be reported for 2019? C: Make the journal Entry...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT