Question

In: Accounting

Malty is a national company whose office facilities were ravaged by fire on July 15, 2017....

Malty is a national company whose office facilities were ravaged by fire on July 15, 2017. The following information was retrieved from the remaining (singed) accounting documents. Malty's uses normal job-order costing and its fiscal year-end is September 30.

Sept 30, 2016 July 15, 2017
Supplies inventory (direct and indirect materials) $ 130,000 $  113,000   
Work in process inventory     196,000          ?
Finished goods inventory       37,000      42,000
Cost of goods sold     632,000          ?
Accounts payable for supplies purchased     26,000       17,000
Manufacturing overhead incurred       31,500       27,200
Manufacturing overhead applied     34,200          ?
Other information (Oct 1/16 to July 15/17):
Cash payments to suppliers       92,000
Payroll (including $10,300 indirect)       96,600
Indirect materials used         7,800
Over-applied overhead            700

Answer the following questions:

(a) What is the value of supplies purchased in the 9 1/2 month period ended July 15, 2017?

What is the value of direct materials used in the 9 1/2 month period ended July 15, 2017?

(b) What is the value of direct labour incurred in the 9 1/2 month period ended July 15, 2017?

(c) What is the manufacturing overhead applied in the 9 1/2 month period ended July 15, 2017?

(d) By how much was the manufacturing overhead over- or under-applied for the year ended Sept 30, 2016? and indicate Over-applied or Under-applied

Please show detailed steps. Thank you.

Solutions

Expert Solution

(a) Value of supplies purchased in the 9 1/2 month period ended July 15, 2017
Accounts payable Ledger a/c ( for supplies purchased)
30-Sep-16 Beginning balance 26000
New purchases(Plug-in figure) 83000
Cash payments to suppliers 92000
15-Jul-17 Ending balance 17000
109000 109000
So, Answer : a = 83000
Value of direct materials used in the 9 1/2 month period ended July 15, 2017
Supplies inventory ledger a/c (direct and indirect materials)
30-Sep-16 Beginning balance 130000
New purchases 83000
Materials used(Plug-in figure) 100000
15-Jul-17 Ending balance 113000
213000 213000
Materials used(as above) 100000
Given: Indirect materials used 7800
So, direct materials used(100000-7800)= 92200
(b) Value of direct labour incurred in the 9 1/2 month period ended July 15, 2017
Payroll (including $10,300 indirect)       96,600
So, direct labor(96600-10300)= 86300
(c) Mfg . overhead applied in the 9 1/2 month period ended July 15, 2017
Manufacturing overhead incurred 27200
Add: Over-applied overhead 700
Mfg. Oh applied (27200+700) 27900
(d) Mfg. overhead over- or under-applied for the year ended Sept 30, 2016
Manufacturing overhead incurred 31500
Manufacturing overhead applied 34200
MFG. OH applied > Mfg. Oh incurred
So, over-applied by
(34200-31500)=
2700
Finished goods inventory
30-Sep-16 Beginning balance(given) 37000
Trf. From WIP 420500
COGS (Plug-in fig.) 415500
15-Jul-17 Ending balance(given) 42000
457500 457500
WIP Inventory
30-Sep-16 Beginning balance(given) 196000
Direct& indirect materials used(92200+7800) 100000
Direct& indirect labor(86300+10300) 96600
Mfg. Oh applied(27200+700) 27900
15-Jul-17 Trf. To fin.gds.Inventory 420500
420500 420500
NOTE: As additional details are missing, WIP fully transferred to Fin.gds.Inventory

Related Solutions

On April 1, 2017 FIRE retired its note payable and on July 1, 2017 the company...
On April 1, 2017 FIRE retired its note payable and on July 1, 2017 the company issued a bond. Bond information Face value $90000 Coupon rate 6.0% Term 9 years Net proceeds $98,000 Interest will be paid semi-annually on December 31 and June 30. At the investor's option, each $2,000 bond is convertible into 50 common shares of the company. Your investigation into similar bond issues showed that had the company issued the debt without the conversion option, the market...
Jessica’s office building is destroyed by fire on November 15, 2016. The adjusted basis of the...
Jessica’s office building is destroyed by fire on November 15, 2016. The adjusted basis of the building is $360,000. She receives insurance proceeds of $505,000 on December 12, 2016. (If there is no gain or loss, select "No gain/loss".) Calculate her realized and recognized gain or loss for the replacement property if she acquires an office building in December 2016 for $505,000. Calculate her realized and recognized gain or loss for the replacement property if she acquires an office building...
On July 1, 2017, Skysong Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Skysong Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,910,000. On July 1, Skysong estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
On July 1, 2017, Headland Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Headland Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,890,000. On July 1, Headland estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
On July 1, 2017, Sheridan Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Sheridan Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,880,000. On July 1, Sheridan estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel...
On July 1, 2017, Torvill Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Torvill estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017, 2018, and 2019. At 12/31/17 At 12/31/18 At 12/31/19...
On April 15, 2021, fire damaged the office and warehouse of Marigold Corporation. The only accounting...
On April 15, 2021, fire damaged the office and warehouse of Marigold Corporation. The only accounting record saved was the general ledger, from which the balance sheet data below was prepared. MARIGOLD CORPORATION MARCH 31, 2021 Cash $19,160 Accounts receivable 42,070 Inventory, December 31, 2020 72,620 Land 35,640 Buildings 111,680 Accumulated depreciation $41,997 Equipment 3,878 Accounts payable 21,638 Other accrued expenses 21,320 Common stock 103,700 Retained earnings 49,110 Sales revenue 121,800 Purchases 49,110 Miscellaneous expense 25,407 $359,565 $359,565 The following...
On April 15, 2021, fire damaged the office and warehouse of Whispering Corporation. The only accounting...
On April 15, 2021, fire damaged the office and warehouse of Whispering Corporation. The only accounting record saved was the general ledger, from which the balance sheet data below was prepared. WHISPERING CORPORATION MARCH 31, 2021 Cash $21,860 Accounts receivable 43,040 Inventory, December 31, 2020 77,390 Land 31,880 Buildings 118,120 Accumulated depreciation $37,414 Equipment 3,738 Accounts payable 22,698 Other accrued expenses 35,483 Common stock 90,800 Retained earnings 56,770 Sales revenue 134,410 Purchases 56,770 Miscellaneous expense 24,777 $377,575 $377,575 The following...
On April 15, 2021, fire damaged the office and warehouse of Whispering Corporation. The only accounting...
On April 15, 2021, fire damaged the office and warehouse of Whispering Corporation. The only accounting record saved was the general ledger, from which the balance sheet data below was prepared. WHISPERING CORPORATION MARCH 31, 2021 Cash $21,860 Accounts receivable 43,040 Inventory, December 31, 2020 77,390 Land 31,880 Buildings 118,120 Accumulated depreciation $37,414 Equipment 3,738 Accounts payable 22,698 Other accrued expenses 35,483 Common stock 90,800 Retained earnings 56,770 Sales revenue 134,410 Purchases 56,770 Miscellaneous expense 24,777 $377,575 $377,575 The following...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT