Question

In: Finance

Exercise 6.6: Details for 6 project proposals as are shown below. Find payback period, NPW, EUAC,...

Exercise 6.6: Details for 6 project proposals as are shown below. Find payback period,
NPW, EUAC, and NFW?
Machine A Machine B Machine C Machine D Machine E Machine F
Initial cost ($240,000) ($360,000) ($420,000) ($560,000) ($660,000) ($850,000)
Life of machine 3 4 5 6 7 9
MARR 9% 10% 11% 12% 13% 14%
Benefits in first year $75,000 $92,000 $109,000 $126,000 $143,000 $131,000
Salvage cost (% of initial cost) 15% 14% 13% 15% 14% 13%
Increase in benefits each year 5% 6% 7% 8% 9% 5%

Solutions

Expert Solution

Machine A
Year 0 1 2 3
Initial cost -240000
Salvage(240000*15%) 36000
Benefits 75000 78750 82688
Total Cash flows -240000 75000 78750 118688
Cumulative cash flows -240000 -165000 -86250 32438
Payback period= 2+(86250/118688)=
2.73 Years
PV F at 9%(1/1.09^Yr.n) 1 0.91743 0.84168 0.77218
PV at 9% -240000 68807 66282 91649
NPV -13262
EUAC=
NPV/(PV Factor)
-13262/((1-1.09^-3)/0.09)=
-5239
NFW
Total Cash flows -240000 75000 78750 118688
FW F at 9%(1*1.09^Yr.n) 1.295029 1.1881 1.09 1
FW at 9% -310807 89108 85838 118688
FW at 9% -17174
Machine B
Year 0 1 2 3 4
Initial cost -360000
Salvage(360000*14%) 50400
Benefits 92000 97520 103371 109573
Total Cash flows -360000 92000 97520 103371 159973
Cumulative cash flows -360000 -268000 -170480 -67109 92865
Payback period= 3+(67109/159973)=
3.42 Years
PV F at 10%(1/1.10^Yr.n) 1 0.90909 0.82645 0.75131 0.683013
PV at 9% -360000 -243636 -140893 -50420 63428
NPV -731521
EUAC=
NPV/(PV Factor)
-731521/((1-1.10^-4)/0.10)=
-230773.5178
NFW
Total Cash flows -360000 92000 97520 103371 159973
FW F at 10%(1*1.10^Yr.n) 1.4641 1.331 1.21 1.1 1
FW at 10% -527076 122452 117999 113708 159973
FW at 10% -12943
Machine C
Year 0 1 2 3 4 5
Initial cost -420000
Salvage(420000*13%) 54600
Benefits 109000 116630 124794 133530 142877
Total Cash flows -420000 109000 116630 124794 133530 197477
Cumulative cash flows -420000 -311000 -194370 -69576 63954 261431
Payback period= 3+(69576/133530)=
3.52 Years
PV F at 11%(1/1.11^Yr.n) 1 0.90090 0.81162 0.73119 0.65873 0.59345
PV at 9% -420000 98198 94660 91248 87960 117193
NPV 69259
EUAC=
NPV/(PV Factor)
-69529/((1-1.11^-5)/0.11)=
-18812.48305
NFW
Total Cash flows -420000 109000 116630 124794 133530 197477
FW F at 11%(1*1.11^Yr.n) 1.685058 1.51807 1.367631 1.2321 1.11 1
FW at 11% -707724 165470 159507 153759 148218 197477
FW at 11% 116706
Machine D
Year 0 1 2 3 4 5 6
Initial cost -560000
Salvage(560000*15%) 84000
Benefits 126000 136080 146966 158724 171422 185135
Total Cash flows -560000 126000 136080 146966 158724 171422 269135
Cumulative cash flows -560000 -434000 -297920 -150954 7770 179192 448327
Payback period= 3+(150954/158724)=
3.95 Years
PV F at 12%(1/1.12^Yr.n) 1 0.89286 0.79719 0.71178 0.63552 0.56743 0.50663
PV at 9% -560000 112500 108482 104608 100872 97269 136352
NPV 100083
EUAC=
NPV/(PV Factor)
100083/((1-1.12^-6)/0.12)=
24343
NFW
Total Cash flows -560000 126000 136080 146966 158724 171422 269135
FW F at 12%(1*1.12^Yr.n) 1.97382 1.76234 1.57352 1.40493 1.2544 1.12 1
FW at 12% -1105341 222055 214125 206477 199103 191992 269135
FW at 12% 197547

Related Solutions

Find payback period
Find payback period Year Project Cash Flow ($) 0 -15,000,000 1 5,500,000 2 4,250,000 3 3,333,333 4 2,050,000 5 1,250,000 6 1,250,000
The NPV and payback period Suppose you are evaluating a project with the cash inflows shown...
The NPV and payback period Suppose you are evaluating a project with the cash inflows shown in the following table. Your boss has asked you to calculate the project’s net present value (NPV). You don’t know the project’s initial cost, but you do know the project’s regular, or conventional, payback period is 2.50 years. The project's annual cash flows are: Year Cash Flow Year 1 $400,000 Year 2 600,000 Year 3 500,000 Year 4 475,000 If the project’s desired rate...
Find the Discounted Payback period for the following project. The discount rate is 10% Project X...
Find the Discounted Payback period for the following project. The discount rate is 10% Project X Initial Outlay $17,249 Year 1 $5,113 Year 2 $5,108 Year 3 $5,772 Year 4 $8,459 Round the answer to two decimal places.
Find the discounted payback period for the following project. The discount rate is 10% Project X...
Find the discounted payback period for the following project. The discount rate is 10% Project X Initial Outlay $8,845 Year 1 $3,480 Year 2 $3,765 Year 3 $5,094 Year 4 $6,366 Round the answer to two decimal places.
Find the discounted payback period. YEAR PROJECT A PROJECT B PROJECT C PROJECT D 0 (10,000)...
Find the discounted payback period. YEAR PROJECT A PROJECT B PROJECT C PROJECT D 0 (10,000) (15,000) (20,000) (30,000) 1 5,000 5,000 10,000 0 2 5000 5,000 10,000 0 3 20,000 5,000 4,000 100,000 4 1,000 10,000 2,000 120,000 5 - 5,000 - 60,000 answer : A(3 years) B(4years) C(4 years) D(3 years) Pls show me the working on how to get the discounted payback period. Pls do not show the working in excel, pls do it manually and attached...
Calculate the Payback Period and Discounted Payback Period for the following project: 1. An initial investment...
Calculate the Payback Period and Discounted Payback Period for the following project: 1. An initial investment of $20,000 with expected after-tax operating cash flows of $125,000 per year for each of the next 3 years. However, in preparation for its termination at the end of year 3, an additional investment of $350,000 must be made at the end of Year 2. Please show all work in excel.
Find the discounted payback period for the following project. THe discount rate is 7%. Initial Outlay...
Find the discounted payback period for the following project. THe discount rate is 7%. Initial Outlay - $8,273 Year 1 - $3.774 Year 2 - $3,300 Year 3 - $5,328 Year 4 - $7,303 Round the answer to two decimal places. Show your work.
REQUIRED Use the information provided below to calculate the following: 5.1.1 Payback Period of Project A...
REQUIRED Use the information provided below to calculate the following: 5.1.1 Payback Period of Project A (answer expressed in years and months) 5.1.2 Net Present Value (NPV) of both projects (amounts rounded off to the nearest Rand). INFORMATION Slater Limited is looking at the possibility of investing in one of two new projects, Project A or Project B. Project A would cost R600 000, and its net cash flows are estimated to be R200 000 per year, except for the...
Payback Period An organization’s initial outlay for a proposed project is $650,000. Use the table below...
Payback Period An organization’s initial outlay for a proposed project is $650,000. Use the table below to calculate the payback period for this project. Free Cash Flows Year Amount Year Amount 1 $95,000.00 6 $620,000.00 2 $46,000.00 7 $100,000.00 3 $167,000.00 8 $100,000.00 4 $185,000.00 9 $100,000.00 5 $90,000.00 10 $100,000.00 The organization’s objectives indicate a corporate payback period of 7 years or less. Would the company be able to meet the cost of the project according to its stated...
The table below lists the projects that your company is considering to invest: Project   Payback Period...
The table below lists the projects that your company is considering to invest: Project   Payback Period (Years)   NPV (USD)   IRR (%) A   4.7   53000   15.44 B   2.1   17000   17.76 C   4.7   18000   16.75 D   4.4   14000   17.05 E   2.8   14000   17.15 The required return is 14.6 percent. Which project should be accepted if they are mutually exclusive?        E        D        C        B        A
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT