Question

In: Finance

Calculate the Payback Period and Discounted Payback Period for the following project: 1. An initial investment...

Calculate the Payback Period and Discounted Payback Period for the following project:

1. An initial investment of $20,000 with expected after-tax operating cash flows of $125,000 per year for each of the next 3 years. However, in preparation for its termination at the end of year 3, an additional investment of $350,000 must be made at the end of Year 2.

Please show all work in excel.

Solutions

Expert Solution

Initial investment =$ 20,000

Investment 2nd year end = $ 3,50,000

Total investment = $ 3,70,000

Cash inflows after tax = 1,25,000+1,25,000+1,25,000

Total =$ 3,75,000

Cumulative cash inflows in year 2= 1,25,000+1,25,000

= 2,50,000

Required cash flow to cover-up initial investment:

= 3,70,000-2,50,000

= $1,20,000

1,25,000 = 12 months

1,20,000 = ? months

Months required = 11.52 months

Therefore payback period = 2 years 11.52 months.

Discounted payback period:

In question required return not given, so time value of money not calculated without required return.

Take eg: required return = 10%

Cash inflows

= 1,25,000*0.909+1,25,000*0.826+1,25,000*0.751

= 1,13,625+1,03,250+93,875

= $ 3,10,750.

Initial investment = 20,000

2nd year end investment = 3,50,000*0.826 = 2,89,100

Total investment = $ 3,09,100.

Cumulative cash inflow in year 2 = 1,13,625+1,03,250

= 2,16,875.

Required cash inflow to cover-up initial investment:

= 3,09,100-2,16,875 = $ 92,225

93,875 = 12 months

92,225 = ? Months required

Therefore =92,225*12/93,875 =11.79 months approximately.

Discounted payback period is 2 years 11.79 months.


Related Solutions

Given the following cash flows for a capital project, calculate its payback period and discounted payback...
Given the following cash flows for a capital project, calculate its payback period and discounted payback period. The required rate of return is 8 percent. Year 0 1 2 3 4 5 Cash Flows $-37500 $11250 $11250 $15000 $6000 $6000 The discounted payback period is 0.16 year longer than the payback period. 0.80 year longer than the payback period. 1.27 years longer than the payback period. 1.85 years longer than the payback period.
What is the discounted payback period for the investment project that has the following cash flows,...
What is the discounted payback period for the investment project that has the following cash flows, if the discount rate is 14 percent? (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16)) Year Cash Flows 0 -13779 1 4470 2 5005 3 5877 4 6626
Find the discounted payback period for the following project. THe discount rate is 7%. Initial Outlay...
Find the discounted payback period for the following project. THe discount rate is 7%. Initial Outlay - $8,273 Year 1 - $3.774 Year 2 - $3,300 Year 3 - $5,328 Year 4 - $7,303 Round the answer to two decimal places. Show your work.
Problem #4 Calculate NPV, Payback, Discounted Payback, IRR and Modified IRR for the following project Initial...
Problem #4 Calculate NPV, Payback, Discounted Payback, IRR and Modified IRR for the following project Initial Investment: -100,000 Annual project cash flow 22,000 for 6 years Cost of capital is 6%
Calculate the discounted payback period for the following cash flows. Investment = $300,000 Salvage Value =...
Calculate the discounted payback period for the following cash flows. Investment = $300,000 Salvage Value = 0 Service Life = 4 Years MARR = 5% n Cash Flow Cost of Capital Balance 0 -300,000 1 100,000 2 150,000 3 125,000 4 100,000
a) Calculate the dynamic payback period for the project A b) Calculate the return on investment...
a) Calculate the dynamic payback period for the project A b) Calculate the return on investment of the project A c) Determine the appropriate selling price which will ensure the NPV of project A and B are the same d) Determine if the NPV of the project A is more sensitive to interest rate than the selling price. Use appropriate diagrams and appropriate parameter Parameter Project A Project B Project lifetime years 20 20 Real interest rate 10% 10% Investment...
What is the discounted payback period of the following investment if the required return is 10%?...
What is the discounted payback period of the following investment if the required return is 10%? Year Cash Flows 0 = -$90 1 = $30 2 = $35 3 = $30 4 = $25 5 = $20
Find the Discounted Payback period for the following project. The discount rate is 10% Project X...
Find the Discounted Payback period for the following project. The discount rate is 10% Project X Initial Outlay $17,249 Year 1 $5,113 Year 2 $5,108 Year 3 $5,772 Year 4 $8,459 Round the answer to two decimal places.
Find the discounted payback period for the following project. The discount rate is 10% Project X...
Find the discounted payback period for the following project. The discount rate is 10% Project X Initial Outlay $8,845 Year 1 $3,480 Year 2 $3,765 Year 3 $5,094 Year 4 $6,366 Round the answer to two decimal places.
Distinguish between the payback period and the discounted payback period?
Distinguish between the payback period and the discounted payback period?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT