Question

In: Finance

REQUIRED Use the information provided below to calculate the following: 5.1.1 Payback Period of Project A...

REQUIRED Use the information provided below to calculate the following: 5.1.1 Payback Period of Project A (answer expressed in years and months) 5.1.2 Net Present Value (NPV) of both projects (amounts rounded off to the nearest Rand). INFORMATION Slater Limited is looking at the possibility of investing in one of two new projects, Project A or Project B. Project A would cost R600 000, and its net cash flows are estimated to be R200 000 per year, except for the third year. The project would last for five years but would need a major overhaul costing R160 000 (not considered in the figures above) at the end of the third year. No scrap value is anticipated for this project. Project B is expected to cost R600 000 and have a useful life of six years. Annual net cash flows from this project are forecasted to be R176 000 per year. The project is expected to have a scrap value of R60 000 (not included in the figures above). The company’s cost of capital is 12%. 5.2 REQUIRED Calculate the following from the information provided below: 5.2.1 Internal Rate of Return of Project Y (answer expressed to two decimal places). 5.2.2 Return on average investment of Project X (answer expressed to two decimal places). INFORMATION Two projects are being evaluated for possible acquisition by Mobray Corporation. Forecasts relating to the two projects are as follows: Project X Project Y Initial investment R1 000 000 R1 000 000 Expected useful life 5 years 5 years Depreciation per year R200 000 R200 000 Estimated salvage value 0 0 Net cash flows: R R Year 1 300 000 220 000 Year 2 300 000 280 000 Year 3 300 000 400 000 Year 4 300 000 420 000 Year 5 300 000 200 000 The cost of capital is 15%.

Solutions

Expert Solution

Refer the images attached for answers to all the parts.


Related Solutions

Calculate the Payback Period and Discounted Payback Period for the following project: 1. An initial investment...
Calculate the Payback Period and Discounted Payback Period for the following project: 1. An initial investment of $20,000 with expected after-tax operating cash flows of $125,000 per year for each of the next 3 years. However, in preparation for its termination at the end of year 3, an additional investment of $350,000 must be made at the end of Year 2. Please show all work in excel.
REQUIRED Use the information provided below to answer each of the following questions independently: 1.1 Calculate...
REQUIRED Use the information provided below to answer each of the following questions independently: 1.1 Calculate the break-even value using the marginal income ratio. 1.2 The sales manager proposes a R2 per unit reduction in selling price with the expectation that this would increase sales by 2 000 units. Is this a good idea? Motivate your answer. 1.3 Determine the selling price per unit if a net profit of R486 000 is desired. INFORMATION The following forecasts for January 2021...
Study the information bellow and answer the following questions Required 1.Calculate the payback period of nick...
Study the information bellow and answer the following questions Required 1.Calculate the payback period of nick and nak equipment (answer must be expressed in years,months and days) 2.Calculate the accounting Rate of return ( on average investment )of Nak equipment (answers expressed to two decimal places) 3.Calculate the net Present value of Nik equipment.(round off amounts to the nearest rand) 4.Calculate the Internal rate of return of Nak equipment (answer expressed to two decimal places) Information Simba limited is investigation...
1.1 REQUIRED Use the information provided below to calculate the cost to Umhlali Stores (as a...
1.1 REQUIRED Use the information provided below to calculate the cost to Umhlali Stores (as a percentage) of not accepting the discount. (Assume a 365-day year.) (5) INFORMATION Jehcon Manufacturers’ credit terms to Umhlali Stores are 60 days but the manufacturer is prepared to allow a 2.5% rebate if Umhlali Stores pays the account within 10 days. 1.2 Use the information given below to calculate the: 1.2.1 EOQ (4) 1.2.2 Reorder point (4) INFORMATION Gem Enterprises intends purchasing 7 200...
1.2 REQUIRED: Use the information provided below to calculate the following: 1.2.1 Idle time variance (3)...
1.2 REQUIRED: Use the information provided below to calculate the following: 1.2.1 Idle time variance (3) 1.2.2 Labour mix variance (7) 1.2.3 Labour yield variance (3) Indicate whether each variance is favourable or unfavourable. INFORMATION : Standard labour costs for Electro Manufacturers to manufacture 2 000 units: 400 hours at R70 per hour 200 hours at R35 per hour Actual labour costs incurred to produce 1 900 units: 290 hours at R R65 per hour 170 hours at R32 per...
1.2 REQUIRED: Use the information provided below to calculate the following: 1.2.1 Idle time variance (3)...
1.2 REQUIRED: Use the information provided below to calculate the following: 1.2.1 Idle time variance (3) 1.2.2 Labour mix variance (7) 1.2.3 Labour yield variance (3) Indicate whether each variance is favourable or unfavourable. INFORMATION: Standard labour costs for Electro Manufacturers to manufacture 2 000 units: 400 hours at R70 per hour 200 hours at R35 per hour Actual labour costs incurred to produce 1 900 units: 290 hours at R R65 per hour 170 hours at R32 per hour...
1.2 REQUIRED: Use the information provided below to calculate the following: 1.2.1 Idle time variance (3)...
1.2 REQUIRED: Use the information provided below to calculate the following: 1.2.1 Idle time variance (3) 1.2.2 Labour mix variance (7) 1.2.3 Labour yield variance (3) Indicate whether each variance is favourable or unfavourable. INFORMATION: Standard labour costs for Electro Manufacturers to manufacture 2 000 units: 400 hours at R70 per hour 200 hours at R35 per hour Actual labour costs incurred to produce 1 900 units: 290 hours at R R65 per hour 170 hours at R32 per hour...
3.1 REQUIRED Use the information provided below to calculate the profit to Mersat Stores if: 3.1.1...
3.1 REQUIRED Use the information provided below to calculate the profit to Mersat Stores if: 3.1.1 All the sales are for cash. (1 mark) 3.1.2 Seventy percent (70%) of the sales are on credit and the balance is for cash. All accounts are paid in 30 days. 3.1.3 All the sales are on credit and the credit terms are 4/10 net 30 days. Suppose this discount applies to 75% of the credit sales. INFORMATION Mersat Stores expects to sell 10...
Given the following cash flows for a capital project, calculate its payback period and discounted payback...
Given the following cash flows for a capital project, calculate its payback period and discounted payback period. The required rate of return is 8 percent. Year 0 1 2 3 4 5 Cash Flows $-37500 $11250 $11250 $15000 $6000 $6000 The discounted payback period is 0.16 year longer than the payback period. 0.80 year longer than the payback period. 1.27 years longer than the payback period. 1.85 years longer than the payback period.
Given the following cash flows for a capital project, calculate its payback period and discounted payback...
Given the following cash flows for a capital project, calculate its payback period and discounted payback period. The required rate of return is 8 percent. Year 0 1 2 3 4 5 Cash Flows $-56900 $13650 $18050 $25200 $10000 $5000 The discounted payback period is
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT