In: Economics
You are financial analyst for the XYZ company. The director has asked you to analyze two proposed capital investments, Project A and Project B. Each project has a cost of RM 10, 000, and the cost of capital for each project is 12 percent. The project s’ cash flows are as follows:
Year |
Expected Net Cash Flows |
|
Project A |
Project B |
|
0 |
(10,000) |
(10,000) |
1 |
6500 |
3500 |
2 |
3000 |
3500 |
3 |
3000 |
3500 |
4 |
1000 |
3500 |
NPV Project A = 966.0
NPV Project B = 630.7
Project A should be accepted
Explanation:-
Using formula
PV = FV / (1 + r)n
PV is present value, FV is future cash flow, r is rate of interest for period and n is the number of periods.
Rate = 12% = 0.12
i Compute NPV for the cash flows for the 4 years period
NPV Project A Computation
PVA0 =-10000
PVA1 = 6500 / (1 + 0.12)1 = 6500 / 1.12 = 5803.6 (rounded)
PVA2 = 3000 / (1 + 0.12)2 = 3000 / 1.122 = 3000 / 1.254 = 2391.6 (rounded)
PVA3 = 3000 / (1 + 0.12)3 = 3000 / 1.123 = 3000 / 1.405 = 2135.3 (rounded)
PVA4 = 1000 / (1 + 0.12)4 = 1000 / 1.124 = 1000 / 1.574 = 635.5 (rounded)
NPVProjectA = PVA0 + PVA1 + PVA2 + PVA3 + PVA4
= -10000 + 5803.6 + 2391.6 + 2135.3 + 635.5
= 966.0
NPV Project B Computation
PVB0 =-10000
PVB1 = 3500 / (1 + 0.12)1 = 3500 / 1.12 = 3125
PVB2 = 3500 / (1 + 0.12)2 = 3500 / 1.122 = 3500 / 1.254 = 2790.2 (rounded)
PVB3 = 3500 / (1 + 0.12)3 = 3500 / 1.123 = 3500 / 1.405 = 2491.2 (rounded)
PVB4 = 3500 / (1 + 0.12)4 = 3500 / 1.124 = 3500 / 1.574 = 2224.3 (rounded)
NPVProjectB = PVB0 + PVB1 + PVB2 + PVB3 + PVB4
= -10000 + 3125 + 2790.2 + 2491.2 + 2224.3
= 630.7
NPV Project A = 966.0
NPV Project B = 630.7
ii Determine project to be accepted
NPVProjectA > NPVProjectB
Project A should be accepted