Question

In: Finance

You are a financial analyst for the Hittle Company. The director of capital budgeting has asked...

You are a financial analyst for the Hittle Company. The director of capital budgeting
has asked you to analyze two proposed capital investments, Projects X and Y. Each
project has a cost of $10,000, and the cost of capital for each is 12%. The projects’
expected net cash flows are as follows:
Expected Net Cash Flows
Year Project X Project Y
0 ?$10,000 ?$10,000
1 6,500 3,500
2 3,000 3,500
3 3,000 3,500
4 1,000 3,500
a. Calculate each project’s payback period, net present value (NPV), internal rate
of return (IRR), modified internal rate of return (MIRR), and profitability
index (PI).
b. Which project or projects should be accepted if they are independent?
c. Which project should be accepted if they are mutually exclusive?
d. How might a change in the cost of capital produce a conflict between the NPV
and IRR rankings of these two projects? Would this conflict exist if r were 5%?
(Hint: Plot the NPV profiles.)
e. Why does the conflict exist

Solutions

Expert Solution

A B C D E F G H I J
2
3 a)
4 Payback Period, NPV, IRR and MIRR Calculation for Project X:
5
6 Cash Flow for Project X is as follows:
7 Year 0 1 2 3 4
8 Cash Flow ($10,000) $6,500 $3,000 $3,000 $1,000
9
10 Calculation of Payback period:
11 Payback period is the period when investment amount is recovered.
12 Year 0 1 2 3 4
13 Free Cash Flow ($10,000) $6,500 $3,000 $3,000 $1,000
14 Cumulative cash flow ($10,000) ($3,500) ($500) $2,500 $3,500
15
16 Payback period is when cumulative free cash flow becomes zero.
17 It can be seen from above that cumulative cash flow becomes zero between year 2 and year 3.
18
19 To estimate the exact payback period cumulative free cash flow can be proprated over the years as follows:
20 Payback period 2.17 =F12+(0-F14)/(G14-F14)
21
22 Hence Payback period is 2.17 Years
23
24
25
26 Given the following cash flow and WACC, NPV for the project can be calculated as follows:
27 Year 0 1 2 3 4
28 Incremental Cash Flow ($10,000) $6,500 $3,000 $3,000 $1,000
29 MARR (i) 12%
30 (P/F,i,n) for each year 0.89 0.80 0.71 0.64
31 Present Value of cash flows = FCF*(P/F,i,n) $5,803.57 $2,391.58 $2,135.34 $635.52
32 Present value if future cash flows $10,966.01 =SUM(E31:H31)
33
34 NPV for Project =Present value fo future cash flows - Initial investment
35 $966.01 =D32+D28
36
37 Hence NPV for Project $966.01
38
39 Calculation of IRR:
40 IRR is the rate at which NPV of the project will be zero.
41 Given the following cash flow IRR can be calculated as below:
42
43 Year 0 1 2 3 4
44 Incremental Cash Flow ($10,000) $6,500 $3,000 $3,000 $1,000
45
46 NPV=-10000+6500/(1+IRR)^1 +3000/(1+IRR)^2+3000/(1+IRR)^3+1000/(1+IRR)^4
47 0=-10000+6500/(1+IRR)^1 +3000/(1+IRR)^2+3000/(1+IRR)^3+1000/(1+IRR)^4
48 IRR can be found using hit and trial method for above equation.
49
50 IRR can also be found using IRR function in excel as follows:
51 Year 0 1 2 3 4
52 Incremental Cash Flow ($10,000) $6,500 $3,000 $3,000 $1,000
53 IRR 18.03% =IRR(D52:H52)
54
55 Inremental IRR of the project 18.03%
56
57 Calculation of MIRR:
58 MIRR is the rate at which PV of cash outflows is equal to the PV of FV of cash inflows.
59 Project term 4 years
60 Incremental cash flows:
61 Year 0 1 2 3 4
62 Incremental Cash Flow ($10,000) $6,500 $3,000 $3,000 $1,000
63
64 PV of cash outflow $10,000
65
66 Calculation of Future Value of cash inflows
67 Year 0 1 2 3 4
68 Incremental Cash Flow $6,500 $3,000 $3,000 $1,000
69 WACC 12%
70 Future Value of cash inflows $9,132 $3,763 $3,360 $1,000
71 Total FV of cash inflows $17,255
72
73 Let r be the MIRR then,
74 PV of cash outflow*(1+r)4=FV of cash inflow
75 10000*(1+r)4=17255
76
77 Solving the above equation:
78 r = 14.61%
79
80 Hence MIRR is 14.61%
81
82 Calculation of Profitability Index:
83
84 Profitability index is given by following formula:
85 Profitability index = Present value of future cash flows / Initial Investment
86 or
87 Profitability index = (NPV+Initial Investment) / Initial Investment
88
89 Using the following data:
90 NPV $966.01
91 Initial Investment $10,000
92
93 Profitability index = (NPV+Initial Investment) / Initial Investment
94 1.10 =(D90+D91)/D91
95
96 Hence profitability index of project X is 1.10
97
98 Payback Period, NPV, IRR and MIRR Calculation for Project Y
99
100 Cash Flow for Project Y is as follows:
101 Year 0 1 2 3 4
102 Cash Flow ($10,000) $3,500 $3,500 $3,500 $3,500
103
104 Calculation of Payback period:
105 Payback period is the period when investment amount is recovered.
106 Year 0 1 2 3 4
107 Free Cash Flow ($10,000) $3,500 $3,500 $3,500 $3,500
108 Cumulative cash flow ($10,000) ($6,500) ($3,000) $500 $4,000
109
110 Payback period is when cumulative free cash flow becomes zero.
111 It can be seen from above that cumulative cash flow becomes zero between year 2 and year 3.
112
113 To estimate the exact payback period cumulative free cash flow can be proprated over the years as follows:
114 Payback period 2.86 =F106+(0-F108)/(G108-F108)
115
116 Hence Payback period is 2.86 Years
117
118 Given the following cash flow and WACC, NPV for the project can be calculated as follows:
119 Year 0 1 2 3 4
120 Incremental Cash Flow ($10,000) $3,500 $3,500 $3,500 $3,500
121 MARR (i) 12%
122 (P/F,i,n) for each year 0.89 0.80 0.71 0.64
123 Present Value of cash flows = FCF*(P/F,i,n) $3,125.00 $2,790.18 $2,491.23 $2,224.31
124 Present value if future cash flows $10,630.72 =SUM(E123:H123)
125
126 NPV for Project =Present value fo future cash flows - Initial investment
127 $630.72 =D124+D120
128
129 Hence NPV for Project $630.72
130
131 Calculation of IRR:
132 IRR is the rate at which NPV of the project will be zero.
133 Given the following cash flow IRR can be calculated as below:
134
135 Year 0 1 2 3 4
136 Incremental Cash Flow ($10,000) $3,500 $3,500 $3,500 $3,500
137
138 NPV=-10000+3500/(1+IRR)^1 +3500/(1+IRR)^2+3500/(1+IRR)^3+3500/(1+IRR)^4
139 0=-10000+3500/(1+IRR)^1 +3500/(1+IRR)^2+3500/(1+IRR)^3+3500/(1+IRR)^4
140 IRR can be found using hit and trial method for above equation.
141
142 IRR can also be found using IRR function in excel as follows:
143 Year 0 1 2 3 4
144 Incremental Cash Flow ($10,000) $3,500 $3,500 $3,500 $3,500
145 IRR 14.96% =IRR(D144:H144)
146
147 Inremental IRR of the project 14.96%
148
149 Calculation of MIRR:
150 MIRR is the rate at which PV of cash outflows is equal to the PV of FV of cash inflows.
151 Project term 4 years
152 Incremental cash flows:
153 Year 0 1 2 3 4
154 Incremental Cash Flow ($10,000) $3,500 $3,500 $3,500 $3,500
155
156 PV of cash outflow $10,000
157
158 Calculation of Future Value of cash inflows
159 Year 0 1 2 3 4
160 Incremental Cash Flow $3,500 $3,500 $3,500 $3,500
161 WACC 12%
162 Future Value of cash inflows $4,917 $4,390 $3,920 $3,500
163 Total FV of cash inflows $16,728 =SUM(E162:H162)
164
165 Let r be the MIRR then,
166 PV of cash outflow*(1+r)4=FV of cash inflow
167 10000*(1+r)4=16728
168
169 Solving the above equation:
170 r = 13.73% =((D163/D156)^(1/D151))-1
171
172 Hence MIRR of Project Y is 13.73%
173
174
175 Calculation of Profitability Index:
176
177 Profitability index is given by following formula:
178 Profitability index = Present value of future cash flows / Initial Investment
179 or
180 Profitability index = (NPV+Initial Investment) / Initial Investment
181
182 Using the following data:
183 NPV $630.72
184 Initial Investment $10,000
185
186 Profitability index = (NPV+Initial Investment) / Initial Investment
187 1.06 =(D183+D184)/D184
188
189 Hence profitability index of project Y is 1.06
190
191 b)
192
193 Since NPV of project X and Y both are positive and independent therefore both projects can be accepted.
194
195 c)
196
197 Since both project are mutually exlusive, therefore only one project can be selected.
198 As profitability index shows the profitability of the project and it is higher for project X,
199 therefore project X should be selected.
200

Related Solutions

You are a financial analyst for the Waffle Company. The director of capital budgeting has asked...
You are a financial analyst for the Waffle Company. The director of capital budgeting has asked you to analyze two proposed capital investments, Projects A and B. Each project has a cost of $50,000, and the cost of capital for each is 10%. The projects’ expected net cash flows are as follows: Expected Net Cash Flows Year Project A Project B 0 ($50,000) ($50,000) 1 25,000 15,000 2 20,000 15,000 3 10,000 15,000 4 5,000 15,000 5 5,000 15,000 e....
Q- 2 You are a financial analyst for the Hittle Company. The director of capital budgeting...
Q- 2 You are a financial analyst for the Hittle Company. The director of capital budgeting has asked you to analyze two proposed capital investments, Projects X and Y. Each project has a cost of $10,000, and the cost of capital for each is 12%. The projects’ expected net cash flows are as follows: Year Project X Project Y 0 −$ 10,000 −$10,000 1 $ 6,500 $ 35,00 2 $ 3000 $ 35,00 3 $ 3000 $ 35,00 4 $...
You are a financial analyst working for Salalah Mills LLC The Director of Capital Budgeting has...
You are a financial analyst working for Salalah Mills LLC The Director of Capital Budgeting has asked you to analyze an Investment Proposal. The investment will need an initial cash outflow if OMR 60000 and has a life of 5 years. Following information is given Cash flow ( OMR) year 1 16000 year 2 16000 year 3 22000 year 4 22000 year 5 31000 a) Calculate the Net present value for using the discounting money cash flows if the rate...
You are financial analyst for the XYZ company. The director has asked you to analyze two...
You are financial analyst for the XYZ company. The director has asked you to analyze two proposed capital investments, Project A and Project B. Each project has a cost of RM 10, 000, and the cost of capital for each project is 12 percent. The project s’ cash flows are as follows: Year Expected Net Cash Flows Project A Project B 0 (10,000) (10,000) 1 6500 3500 2 3000 3500 3 3000 3500 4 1000 3500 Calculate each project’s NPV....
You are the financial analyst for the Glad It’s Finally Over Company. The director of capital...
You are the financial analyst for the Glad It’s Finally Over Company. The director of capital budgeting has asked you to analyze a proposed capital investment. The project has a cost of $30,000 and the cost of capital is 10%. The project’s expected net cash flows are as follows: Year                Expected Net Cash Flow 0                               ($30,000) 1 12,500 2 10,000 3 10,000 4 8,000 A) What is the project’s payback period? B) What is the project’s discounted payback period? C)...
(Khaleef is appointed as a financial analyst for the NASHORA Bhd. The director has asked him...
(Khaleef is appointed as a financial analyst for the NASHORA Bhd. The director has asked him to analyse two proposed capital investments, Project NAS dan Project HORA. Each project has a cost of RM2,000,000. NASHORA Bhd will used a mix of capital structure (40% of debt and 60% of equity) to finance their project’s cost. NASHORA will issuing a-10years bond with 10% coupon rate and selling price at RM750. Tax rate = 30%. Meanwhile, a 4%-risk free rate, risk premium...
You are a senior financial analyst with IBM in their capital budgeting division. IBM is considering...
You are a senior financial analyst with IBM in their capital budgeting division. IBM is considering expanding in Australia due to its positive business atmosphere and cultural similarities to the U.S. The new facility would require an initial investment in fixed assets of $5 billion Australian and an additional capital investment of 3% would be required each year in years 1–4. All capital investments would be depreciated straight-line over the five years that the facility operates. First-year revenues from the...
The Financial Director of your company has recently asked you to attend a conference where a...
The Financial Director of your company has recently asked you to attend a conference where a paper on Balanced Scorecards entitled ‘Linking Management Accounting with Strategy’ was presented. At the next Board meeting of the company you have been asked to: (a) Discuss what the four perspectives of a Balanced Scorecard are, and how they are translated into performance measures and targets. (b) Critically appraise the success of the application of Balanced Scorecards in business organisations and whether they are...
Exercise Example - Capital Budgeting Project Analysis - Chapter 5 As director of capital budgeting, you...
Exercise Example - Capital Budgeting Project Analysis - Chapter 5 As director of capital budgeting, you are reviewing three potential investment projects with the following cost and cash flow projections.   Cash Flow Project A Project B Project C Investment Cost ($500,000) ($375,000) ($475,000) Year One Cash Flow $200,000 $175,000 $250,000 Year Two Cash Flow $180,000 $50,000 $200,000 Year Three Cash Flow $100,000 $50,000 $75,000 Year Four Cash Flow $80,000 $50,000 $30,000 Year Five Cash Flow $140,000 $300,000 $30,000 Calculate the...
19. A financial analyst in Bookman’s Book Company just analyzed a capital budgeting project and realized...
19. A financial analyst in Bookman’s Book Company just analyzed a capital budgeting project and realized that the IRR of 12% on the project was identical to the company’s discount rate of 12%. Which of the following is true regarding the net present value of the project? A. The NPV of the project is positive B. The NPV of the project is zero C. The NPV of the project is negative D. More information is needed to answer the question...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT