In: Finance
You are a financial analyst for the Waffle Company. The director of capital budgeting has asked you to analyze two proposed capital investments, Projects A and B. Each project has a cost of $50,000, and the cost of capital for each is 10%. The projects’ expected net cash flows are as follows: Expected Net Cash Flows Year
Project A Project B
0 ($50,000) ($50,000)
1 25,000 15,000
2 20,000 15,000
3 10,000 15,000
4 5,000 15,000
5 5,000 15,000
e. How might a change in the cost of capital produce a conflict
between the NPV and IRR rankings of these two projects? Would this
conflict exist if r were 6%? (Hint: Plot the NPV profiles.)
Net Present Value(NPV) is the difference between the present value of cash inflows and the present value of cash outflows. It is used in evaluating capital budgeting decisions. Projects with NPV greater than 0 are investable.
We are given,
Initial cost of both projects = $50,000
Cost of capiatl = 10%
We can calculate NPV for both projects using excel,
Cashflows | Discounted cash flows | ||||
Yr | A | B | Discount factor @ 10% | A | B |
0 | -50000 | -50000 | 1.000 | -50000.0 | -50000.0 |
1 | 25000 | 15000 | 0.909 | 22727.3 | 13636.4 |
2 | 20000 | 15000 | 0.826 | 16528.9 | 12396.7 |
3 | 10000 | 15000 | 0.751 | 7513.1 | 11269.7 |
4 | 5000 | 15000 | 0.683 | 3415.1 | 10245.2 |
5 | 5000 | 15000 | 0.621 | 3104.6 | 9313.8 |
NPV | 3289.0 | 6861.8 | |||
IRR | 13.57% | 15.24% |
NPV of project A = $3,289
NPV of project B = $6,6861.8
IRR of both projects is greater than the cost of capital(10%). With a 10% discount rate, NPV of Projejct B > NPV of Project A, hence we will select Project B.
Discount rate | NPV A | NPV B |
0% | 15000 | 25000 |
1% | 13627 | 22801 |
2% | 12304 | 20702 |
3% | 11031 | 18696 |
4% | 9803 | 16777 |
5% | 8620 | 14942 |
6% | 7478 | 13185 |
7% | 6376 | 11503 |
8% | 5311 | 9891 |
9% | 4283 | 8345 |
10% | 3289 | 6862 |
11% | 2328 | 5438 |
12% | 1398 | 4072 |
13% | 498 | 2758 |
14% | -374 | 1496 |
15% | -1218 | 282 |
16% | -2036 | -886 |
17% | -2830 | -2010 |
18% | -3599 | -3092 |
19% | -4346 | -4135 |
20% | -5070 | -5141 |
As we can see from the NPV profile of Project A & B, Project B's NPV is greater than Project A's NPV at all level of discount rate. It is below Project A NPV at a discount rate of 20%.
At a 6% discount rate, NPV of B > NPV of A.
If you have any doubts please let me know in the comments. Please give a positive rating if the answer is helpful to you. Thanks.