Question

In: Economics

the city engineer asks you to compare the cost of installing water pipe with city employees...

the city engineer asks you to compare the cost of installing water pipe with city employees ( alternative A) versus contracting it out ( Alternative B). They need to lay 4000 lineal feet of pipe per month for 48 months. Use i=9% per year

Alternative A:

Buy equipment =$2,000,000 paid now

Resale of equipment at EMO 48 = 10% of purchase price

Equipment O & M, labor, Materials = $10/lineal foot for the first 12 months, increasing by $0.10/month for each

subsequent month

Alternative B

Contract the work for $25/lineal foot with no increases over the 48-month period.

find the Net Present Cost for each alternative and compare.

only EXCEL answer

Solutions

Expert Solution

Data Provided in the question:

Two alternative plans are provided for installing water pipes with the following details:

Alternative A:

  1. Equipment cost=$2,000,000; Resale value after 48 months=10% of purchase price.
  2. Equipment O & M, labour, Materials = $10/lineal foot for the first 12 months, increasing by $0.10/month for each subsequent month.

Alternative B:

  1. Contract fee=$25/lineal foot with no increases over the 48-month period.

Additional details:

  1. 4000 lineal feet of pipe per month is laid for 48 months
  2. Interest rate=9% p.a.

Solution:

To find Net Present cost, total cash outflow of the project is calculated and total cash inflow discounted by the interest rate is subtracted from it.

Total Cash outflow is the sum of Equipment, Labour & Materials and Contract fee.

Contract fee is total lineal feet of pipe laid multiplied with $25 per feet.

4000 feet per month X 48 months =192000 feet

Labour & Materials are calculated as under:

Residual Value of Materials is calculated by discounting the resale value of materials by the interest rate over the given time period,

Residual value= Resale Value/ (1+rate of interest)^No. of years

By substituting values we get,

Residual value= 10% of Purchase price/ (1+0.09)^4 years

Residual value= $ 200,000/ 1.41158

Residual value=$ 141,685.04

By the above comparison, we find that the Net Present cost of Contracting the work is more that executing the work with city employees.


Related Solutions

A water tower supplies water to a city through a pipe with 1 ft diameter. The...
A water tower supplies water to a city through a pipe with 1 ft diameter. The pipe is 0.5 miles long and is made of commercial steel pipe. Over the years, the supply line lost head and engineers are considering the replacement of 94 percent of the pipe length with a larger diameter pipe (same type). The peak water demand is 3.53 ft3/sec. How much pressure head could be gained by this strategy?
A suspension of calcium carbonate particles in water flows through a pipe. An engineer was asked...
A suspension of calcium carbonate particles in water flows through a pipe. An engineer was asked to determine both the flow rate and the composition of this slurry. The engineer proceeded to collect the stream in a graduated cylinder for a time given in the table below. The engineer weighed the cylinder, evaporate the collected water, and reweighed the cylinder. The following results are obtained based on two occasion Item Sample 1 Sample 2 Time to collect 1 min 1...
You are studying the laminar flow of water in a pipe at 20˚C. The pipe is...
You are studying the laminar flow of water in a pipe at 20˚C. The pipe is 2 cm in diameter, and the pressure gradient driving the flow is 0.8 Pa/m. Find the x-sectional average velocity (Poiseuille’s Law) and the maximum velocity achieved at the centerline of the pipe (use the equation for Umax presented in the alternative derivation of Poiseuille’s Law). How many times greater is the maximum velocity compared to the average velocity? Is this ū/umax ratio constant or...
A city plans to upgrade its storm water management infrastructure by installing new pipes. The installation...
A city plans to upgrade its storm water management infrastructure by installing new pipes. The installation costs 2.1 million dollars and the annual maintenance cost is $28,000. Every 10 years, the system needs to be fully examined which requires a fixed management and material cost of $ 20,000 and a variable labor cost at the rate of $25/hr. 8 full time (working 8 hours per day) workers will be employed for 40 days for this task. If the infrastructure has...
Suppose you are the independent CPA for small city. The city manager asks you for guidance...
Suppose you are the independent CPA for small city. The city manager asks you for guidance to determine the geminally accepted accounting principles requirements for the city-owned housing projects to be accounted for in the enterprise fund. what would be your response to the city manager?
You are the city engineer of a large city. Name and describe any one system of...
You are the city engineer of a large city. Name and describe any one system of systems (SOS) that falls under your control. List one concern that is likely to be associated with your SOS’s physical structure, operation, or physical condition. How would you assess the overall technical performance of (a) any one component system of the SOS and (b) the entire SOS? For the SOS, list and discuss any three costs or “disutilities” associated with the system.
Suppose the chief engineer asks you to do a replacement analysis on an existing piece of...
Suppose the chief engineer asks you to do a replacement analysis on an existing piece of equipment. (The defender) Because technology changes so rapidly, she does not want you to evaluate the equipment beyond 4 years since the equipment will be obsolete. The company uses a MARR of 8 percent. The existing equipment was purchased 5-years ago for $175,000 but can be sold today (t = 0) for $30,000. The future salvage values of the equipment are expected to decrease...
You are the Engineer In Charge for a large paving project in New York City. There...
You are the Engineer In Charge for a large paving project in New York City. There is some additional paving work being added to the mainline expressway job involving approximately 25,000 metric tons of asphalt. The additional work involves paving nine (9) ramps along the mainline expressway. Due to the Maintenance and Protection of Traffic requirements, the ramps will each be paved on their own night. The total estimated quantity is 400 Metric Tons of Superpave Top Asphalt and 500...
2. React to the following situation: One of the employees you supervise asks you to have...
2. React to the following situation: One of the employees you supervise asks you to have Friday off because some relatives arrive from the United States and he wants to share with them. You as your supervisor tried to give you the day off and it was not possible due to need for service. When informing the employee, he was upset and indicated that he would talk to the hospital administrator and when he left his office, he threw the...
Suppose you are a civil engineer, specializing in traffic volume control for the City of Grand...
Suppose you are a civil engineer, specializing in traffic volume control for the City of Grand Rapids. Your department has been receiving a multitude of complaints about traffic wait times for a certain intersection in the heart of downtown. To see if these claims are valid, you want to monitor the true average wait time at that intersection. Over the course of a few months, you record the average number of minutes a car waits at the intersection between 4:00...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT