A city plans to upgrade its storm water management infrastructure by installing new pipes. The installation costs 2.1 million dollars and the annual maintenance cost is $28,000. Every 10 years, the system needs to be fully examined which requires a fixed management and material cost of $ 20,000 and a variable labor cost at the rate of $25/hr. 8 full time (working 8 hours per day) workers will be employed for 40 days for this task. If the infrastructure has a life time of 120 years and the city's interest rate is 8%

What is the capitalized worth of the project (in millions)? Please note that the value could be negative.

Solutions

Expert Solution

Answer: Calculation of capitalised worth:
Present value
Particulars Amount Calculation Amount
Installation costs    2,100,000.00 -      2,100,000.00
Annual maintenance cost          28,000.00 28,000 / 0.08         350,000.00
Fixed management cost every 10 years          20,000.00 20,000 * A/F(8%,10)
20,000 * 0.06903              1,380.60
Variable labour cost every 10 years            8,000.00 8,000 * A/F(8%,10)
8,000 * 0.06903                  552.24
Capitalised worth equals (2,451,932.84)
Please rate my answer well. Thanks in advance.

Related Solutions

Explain Storm water Management
Explain Storm water Management
using Permutations (nPr) solve: 1. The city plans to upgrade its Personal Identification Number (PIN) for...
using Permutations (nPr) solve: 1. The city plans to upgrade its Personal Identification Number (PIN) for each of its employees. The PIN will consist of 7 characters defined, in three independent categories, as follows: • The first two characters are uppercase letters, no letter to be repeated. • The next three characters are digits, no digit to be repeated. • the last two characters are letters (uppercase or lowercase), but no letter is to be repeated. For example, aA is...
the city engineer asks you to compare the cost of installing water pipe with city employees...
the city engineer asks you to compare the cost of installing water pipe with city employees ( alternative A) versus contracting it out ( Alternative B). They need to lay 4000 lineal feet of pipe per month for 48 months. Use i=9% per year Alternative A: Buy equipment =$2,000,000 paid now Resale of equipment at EMO 48 = 10% of purchase price Equipment O & M, labor, Materials = $10/lineal foot for the first 12 months, increasing by $0.10/month for...
In the design of a city water supply system, three reservoirs are connected by three pipes...
In the design of a city water supply system, three reservoirs are connected by three pipes which meet at the junction. Reservoir A needs to supply 0.0938 m3/s to lower reservoirs B (Elevation 150 m) and C (Elevation 140 m). Pipe 1 is 900 m long and 300 mm in diameter, pipe 2 is a 200 mm diameter pipe 387 m long, and pipe 3 is 200 mm in diameter and 700 m long. The roughness coefficient for all pipes...
The city of Stillwater is planning to install a new settling tank as an upgrade to...
The city of Stillwater is planning to install a new settling tank as an upgrade to their existing water treat plant. You run a batch settling test using a 2.0 m column and coagulated water from their existing tank and collect the following data (Table 1). Using this data, design a settling tank to remove 65% of the influent suspended solids. Assume a design flow of 0.5 m3/s. Use scale up factors of 0.65 for overflow rate and 1.75 for...
A city is considering a reservoir water as its new drinking water source. As a result,...
A city is considering a reservoir water as its new drinking water source. As a result, the city council wants to know how good the reservoir water is to serve this potential purpose. Assume you are the chief engineer of the city utilities; please provide a list of water quality parameters need to be tested and the corresponding testing methods.
A municipal water authority is considering the installation of a new water system. Two options are...
A municipal water authority is considering the installation of a new water system. Two options are being considered. The first option is a steel pipeline with an installation cost of $225 million. Annual maintenance and pumping costs begin at $15 million and increase by $1.0 million per year. The second option is a gravity fed concrete canal with an installation cost of $400 million. Annual maintenance costs begin at $0.5 million and increase by $0.4 million per year. The water...
The Cebu City plans to increase the capacity of her existing water transmission lines. Two plans...
The Cebu City plans to increase the capacity of her existing water transmission lines. Two plans are under consideration. Plan A requires the construction of a parallel pipeline, the flow being maintained by gravity. The initial cost is P151,582,222 and the life is 40 years, with an annual operating cost of P6,350,911 for the 1st 20 years and P14,898,843 for the next 20 years. Plan B requires the construction of a booster pumping station costing P100M with the life of...
Your organization plans to upgrade its operating system to the newest version. The IT department identifies...
Your organization plans to upgrade its operating system to the newest version. The IT department identifies several legacy applications that will require significant modifications to run under the new OS. You suggest instead that they should consider supporting both the old and the new operating system by using one of the following three options: a. virtualization b. exokernels c. microkernels Briefly explain how each option could provide the needed support.
The City of Bourbonnais plans to construct a water purificationfacility that requires $1,000,000 investment in...
The City of Bourbonnais plans to construct a water purification facility that requires $1,000,000 investment in the beginning and $20,000 O&M costs per year. The city will expect additional revenue of $70,000 per year from residents.Assuming the city’s MARR is 10% compounded yearly and the facility is handed over after 20 years to a utility company that would pay $120,000 for the facility, compute the net present worth of the project and determine if the project is economically worthy? ....