Question

In: Accounting

Brady Construction Company contracted to build an apartment complex for a price of $6,900,000. Construction began...

Brady Construction Company contracted to build an apartment complex for a price of $6,900,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars.

Estimated Costs to Complete

Costs Incurred During Year

(As of the End of the Year)

Situation

2018

2019

2020

2018

2019

2020

1 1,690 2,700 1,470 4,170 1,470
2 1,690 1,470 3,160 4,170 3,160
3 1,690 2,700 3,120 4,170 3,020
4 690 3,190 1,380 4,830 970
5 690 3,190 2,630 4,830 3,020
6 690 3,190 3,700 6,455 3,410


Required:
Complete the following table. (Do not round intermediate calculations. Enter answers in dollars. Round your final answers to the nearest whole dollar. Negative amounts should be indicated by a minus sign.)

Gross Profit (loss) Recogonized

Revenue Recogonized over time/Revenue Recogonized upon completed for situation 1-6 years 2018, 2019, 2020

Solutions

Expert Solution

Solution:

Gross Profit when Revenue recgonized over time:

Computation of % of Gross Profit - Brady Construction Company (Situation 1)
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) % of completion (D) (B/C) Contract Price
(E)
Total Revenue to be recoganized (F) (E * D) Revenue for current period (G) Gross Profit (H) (G - A)
2018 $1,690,000 $1,690,000 $5,860,000 28.84% $6,900,000 $1,989,932 $1,989,932 $299,932
2019 $2,700,000 $4,390,000 $5,860,000 74.91% $6,900,000 $5,169,113 $3,179,181 $479,181
2020 $1,470,000 $5,860,000 $5,860,000 100.00% $6,900,000 $6,900,000 $1,730,887 $260,887
Computation of Gross Profit - Brady Construction Company (Situation 2)
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) % of completion (D) (B/C) Contract Price
(E)
Total Revenue to be recoganized (F) (E * D) Revenue for current period (G) Gross Profit (H) (G - A)
2018 $1,690,000 $1,690,000 $5,860,000 28.84% $6,900,000 $1,989,932 $1,989,932 $299,932
2019 $1,470,000 $3,160,000 $6,320,000 50.00% $6,900,000 $3,450,000 $1,460,068 -$9,932
2020 $3,160,000 $6,320,000 $6,320,000 100.00% $6,900,000 $6,900,000 $3,450,000 $290,000
Computation of Gross Profit - Brady Construction Company (Situation 3)
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) % of completion (D) (B/C) Contract Price
(E)
Total Revenue to be recoganized (F) (E * D) Revenue for current period (G) Gross Profit (H)
2018 $1,690,000 $1,690,000 $5,860,000 28.84% $6,900,000 $1,989,932 $1,989,932 $299,932 $1,989,932 - $1,690,000
2019 $2,700,000 $4,390,000 $7,410,000 59.24% $6,900,000 $4,087,854 $2,097,923 -$809,932 $6,900,000 - $7,410,000 - $299,932
2020 $3,120,000 $7,510,000 $7,510,000 100.00% $6,900,000 $6,900,000 $2,812,146 -$100,000 $6,900,000 - $7,510,000 - $299,932 + $809,932
Computation of Gross Profit - Brady Construction Company (Situation 4)
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) % of completion (D) (B/C) Contract Price
(E)
Total Revenue to be recoganized (F) (E * D) Revenue for current period (G) Gross Profit (H) (G - A)
2018 $690,000 $690,000 $5,520,000 12.50% $6,900,000 $862,500 $862,500 $172,500
2019 $3,190,000 $3,880,000 $4,850,000 80.00% $6,900,000 $5,520,000 $4,657,500 $1,467,500
2020 $1,380,000 $5,260,000 $5,260,000 100.00% $6,900,000 $6,900,000 $1,380,000 $0
Computation of Gross Profit - Brady Construction Company (Situation 5)
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) % of completion (D) (B/C) Contract Price
(E)
Total Revenue to be recoganized (F) (E * D) Revenue for current period (G) Gross Profit (H) (G - A)
2018 $690,000 $690,000 $5,520,000 12.50% $6,900,000 $862,500 $862,500 $172,500
2019 $3,190,000 $3,880,000 $6,900,000 56.23% $6,900,000 $3,880,000 $3,017,500 -$172,500
2020 $2,630,000 $6,510,000 $6,510,000 100.00% $6,900,000 $6,900,000 $3,020,000 $390,000
Computation of Gross Profit - Brady Construction Company (Situation 6)
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) % of completion (D) (B/C) Contract Price
(E)
Total Revenue to be recoganized (F) (E * D) Revenue for current period (G) Gross Profit (H)
2018 $690,000 $690,000 $7,145,000 9.66% $6,900,000 $666,340 $666,340 -$245,000 $6,900,000 - $7,145,000
2019 $3,190,000 $3,880,000 $7,290,000 53.22% $6,900,000 $3,672,428 $3,006,088 -$145,000 $6,900,000 - $7,290,000 + $245,000
2020 $3,700,000 $7,580,000 $7,580,000 100.00% $6,900,000 $6,900,000 $3,227,572 -$290,000 $6,900,000 - $7,580,000 + $245,000 + $145,000

Gross Profit when revenue regonized upon completion:

Computation of Gross Profit - Revenue on completion - Brady Construction Company (Situation 1)
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) Contract Price
(D)
Gross Profit
2018 $1,690,000 $1,690,000 $5,860,000 $6,900,000 $0
2019 $2,700,000 $4,390,000 $5,860,000 $6,900,000 $0
2020 $1,470,000 $5,860,000 $5,860,000 $6,900,000 $1,040,000
Computation of Gross Profit - Revenue on completion - Brady Construction Company (Situation 2)
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) Contract Price
(D)
Gross Profit
2018 $1,690,000 $1,690,000 $5,860,000 $6,900,000 $0
2019 $1,470,000 $3,160,000 $6,320,000 $6,900,000 $0
2020 $3,160,000 $6,320,000 $6,320,000 $6,900,000 $580,000
Computation of Gross Profit - Revenue on completion - Brady Construction Company (Situation 3)
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) Contract Price
(D)
Gross Profit
2018 $1,690,000 $1,690,000 $5,860,000 $6,900,000 $0
2019 $2,700,000 $4,390,000 $7,410,000 $6,900,000 -$510,000
2020 $3,120,000 $7,510,000 $7,510,000 $6,900,000 -$100,000
Computation of Gross Profit - Revenue on completion - Brady Construction Company (Situation 4)
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) Contract Price
(D)
Gross Profit
2018 $690,000 $690,000 $5,520,000 $6,900,000 $0
2019 $3,190,000 $3,880,000 $4,850,000 $6,900,000 $0
2020 $1,380,000 $5,260,000 $5,260,000 $6,900,000 $1,640,000
Computation of Gross Profit - Revenue on completion - Brady Construction Company (Situation 5)
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) Contract Price
(D)
Gross Profit
2018 $690,000 $690,000 $5,520,000 $6,900,000 $0
2019 $3,190,000 $3,880,000 $6,900,000 $6,900,000 $0
2020 $2,630,000 $6,510,000 $6,510,000 $6,900,000 $390,000
Computation of Gross Profit - Revenue on completion - Brady Construction Company (Situation 6)
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) Contract Price
(D)
Gross Profit
2018 $690,000 $690,000 $7,145,000 $6,900,000 -$245,000
2019 $3,190,000 $3,880,000 $7,290,000 $6,900,000 -$145,000
2020 $3,700,000 $7,580,000 $7,580,000 $6,900,000 -$290,000

Related Solutions

Brady Construction Company contracted to build an apartment complex for a price of $5,800,000. Construction began...
Brady Construction Company contracted to build an apartment complex for a price of $5,800,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred During Year (As of the End of the Year) Situation 2021 2022 2023 2021 2022 2023 1 1,580 2,370 1,140 3,510 1,140 — 2 1,580...
Brady Construction Company contracted to build an apartment complex for a price of $5,200,000. Construction began...
Brady Construction Company contracted to build an apartment complex for a price of $5,200,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred During Year (As of the End of the Year) Situation 2018 2019 2020 2018 2019 2020 1 1,520 2,190 960 3,150 960 — 2 1,520...
Brady Construction Company contracted to build an apartment complex for a price of $6,000,000. Construction began...
Brady Construction Company contracted to build an apartment complex for a price of $6,000,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred During Year (As of the End of the Year) Situation 2018 2019 2020 2018 2019 2020 1 1,600 2,430 1,200 3,630 1,200 — 2 1,600...
Brady Construction Company contracted to build an apartment complex for a price of $5,200,000. Construction began...
Brady Construction Company contracted to build an apartment complex for a price of $5,200,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred During Year (As of the End of the Year) Situation 2021 2022 2023 2021 2022 2023 1 1,520 2,190 960 3,150 960 — 2 1,520...
Brady Construction Company contracted to build an apartment complex for a price of $5,200,000. Construction began...
Brady Construction Company contracted to build an apartment complex for a price of $5,200,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred During Year (As of the End of the Year) Situation 2021 2022 2023 2021 2022 2023 1 1,520 2,190 960 3,150 960 — 2 1,520...
Brady Construction Company contracted to build an apartment complex for a price of $6,800,000. Construction began...
Brady Construction Company contracted to build an apartment complex for a price of $6,800,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred During Year (As of the End of the Year) Situation 2018 2019 2020 2018 2019 2020 1 1,680 2,670 1,440 4,110 1,440 — 2 1,680...
Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began...
Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred During Year (As of the End of the Year) Situation 2018 2019 2020 2018 2019 2020 1 1,630 2,520 1,290 3,810 1,290 — 2 1,630...
Brady Construction Company contracted to build an apartment complex for a price of $6,400,000. Construction began...
Brady Construction Company contracted to build an apartment complex for a price of $6,400,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred During Year (As of the End of the Year) Situation 2018 2019 2020 2018 2019 2020 1 1,640 2,550 1,320 3,870 1,320 — 2 1,640...
Brady Construction Company contracted to build an apartment complex for a price of $6,400,000. Construction began...
Brady Construction Company contracted to build an apartment complex for a price of $6,400,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred During Year (As of the End of the Year) Situation 2018 2019 2020 2018 2019 2020 1 1,640 2,550 1,320 3,870 1,320 — 2 1,640...
Brady Construction Company contracted to build an apartment complex for a price of $5,700,000. Construction began...
Brady Construction Company contracted to build an apartment complex for a price of $5,700,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred During Year (As of the End of the Year) Situation 2018 2019 2020 2018 2019 2020 1 1,570 2,340 1,110 3,450 1,110 — 2 1,570...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT