Question

In: Accounting

Question 1. Cashion International (Sensitivity Analysis) Cashion International are considering a project that is susceptible to...

Question 1. Cashion International (Sensitivity Analysis)
Cashion International are considering a project that is susceptible to risk. An initial investment of £90,000 will be followed by three years each with the following most likely cash flows The initial investment consists of £70,000 in machines, which have a zero scrap value at the end of the three year life of the project and £20,000 in additional working capital which is recoverable at the end. The discount rate is 10%.


Sales (100,000 units) £200,000
Labour costs £100,000
Material costs £40,000
Other costs £10,000 £150,000
Net cash flow    £ 50,000


Required:
For the four variables of
i. Sales price
ii. Labour costs
iii. Material costs
iv. Discount rate
a) Rank the above in terms of their sensitivity to the project outcome and calculate the percentage deviation before breakeven NPV is reached
b) Discuss how the management of Cashion would use this information.

Solutions

Expert Solution

Part a:

Ranking on the basis of sensitivity is provided below.

Sensitivity rank:

Rank

Sales price

I

Labour cost

II

Material costs

III

Discount rate

IV

Workings:

Present value factors @ 10%

0.909090909

0.82644628

Particulars

Amount (£)

Amount (£)

Present value of total cash inflow

   1,24,342.60

Add: Present value of working capital to be recovered

      15,026.30

Present value of cash flows

   1,39,368.90

Less: Initial investment

      90,000.00

Net present value

     49,368.90

Sensitivity levels

Sales price

Current sales price (200000/100000)

2

If sales price is decreased by 10%

New sales price

1.8

NPV will be

Net annual cash flow

30000

Particulars

Amount (£)

Amount (£)

Present value of total cash inflow

      74,605.56

Add: Present value of working capital to be recovered

      15,026.30

Present value of cash flows

      89,631.86

Less: Initial investment

      90,000.00

Net present value

         -368.14

Change in sales price

10%

Sensitivity (%)

-100.745701

Sensitivity of sales price is

         -100.75

Labour cost

Current labour cost

100000

Increase of 10%

New labour cost

110000

Net annual cash flow

40000

Present value factors @ 10%

0.909090909

0.82644628

Particulars

Amount (£)

Amount (£)

Present value of total cash inflow

      99,474.08

Add: Present value of working capital to be recovered

      15,026.30

Present value of cash flows

   1,14,500.38

Less: Initial investment

      90,000.00

Net present value

     24,500.38

Change in labour cost

10%

Change in NPV

           -50.37

Material cost

Increase of 10% in material cost

Current material cost

40000

New material costs

44000

Net annual cash flow

46000

Present value factors @ 10%

0.909090909

0.82644628

Particulars

Amount (£)

Amount (£)

Present value of total cash inflow

   1,14,395.19

Add: Present value of working capital to be recovered

      15,026.30

Present value of cash flows

   1,29,421.49

Less: Initial investment

      90,000.00

Net present value

     39,421.49

Change in labour cost

10%

Change in NPV

           -20.15

Part b:

Management of Cashion would use this information to make important decisions such as pricing the products, salaries and wages policies of the employees and workers, purchasing raw materials and taking loan for investment or issuing capital for investment in new projects.


Related Solutions

1. Perform sensitivity analysis on the following project by first finding the NPV for the base...
1. Perform sensitivity analysis on the following project by first finding the NPV for the base case, then for a 10% decline in quantity sold and a 10% increase in quantity sold.       Investment = $270,000 Straight line depreciation                                      over 3 years       quantity sold per year = 20,000       Price per unit = $20       Operating Cost = $10 per unit (all variable)       Tax rate 25%   cost of capital 10%       Project will have a 3-year life...
Sensitivity Analysis Consider the project where the initial cost is $200,000, and the project has a...
Sensitivity Analysis Consider the project where the initial cost is $200,000, and the project has a 5-year life. There is no salvage. Depreciation is straight-line (Depreciation = 200,000/5 = 40,000) Unit Sales = 6000, Price per unit = $80 (Sales = 6,000 x 80) Variable cost per unit = $60 (Variable Costs = 6,000 x 60) The required return is 12%, and the tax rate is 21%  What are the cash flow each year, NPV and IRR in each...
Explain the meaning of the term ‘sensitivity analysis’ in the context of project appraisal, and discuss...
Explain the meaning of the term ‘sensitivity analysis’ in the context of project appraisal, and discuss how it is carried out for both standard project variables and also the discount rate. kindly note that i need a full answer and correct with full details
You are performing a sensitivity analysis on an investment project and looking at the EXPECTED case...
You are performing a sensitivity analysis on an investment project and looking at the EXPECTED case of outcome. At t = 0, you invest $5 million in a 10-year project and expect to receive a revenue (sales) of $10 million each year. Variable cost is 75% of revenue (sales) and the cost of capital is 8% p.a. Using the straight-line depreciation method, determine the depreciation per year. A. $ 500,000 B. $ 750,000 C. $ 1,000,000 D. $ 1,500,000 E....
1) Describe "Sensitivity Analysis" within the Linear Programming context. Why is sensitivity analysis important? 2) Discuss...
1) Describe "Sensitivity Analysis" within the Linear Programming context. Why is sensitivity analysis important? 2) Discuss the impact of the changes in the following to your optimal solution: objective function coefficient resources or right-hand-side values. I need at least 200 words
Choose ONE: Capital budgeting typically requires some type of sensitivity analysis. In the case of international...
Choose ONE: Capital budgeting typically requires some type of sensitivity analysis. In the case of international capital budgeting from the project perspective, analysts consider political risk, foreign exchange risk and foreign exchange risk. Identify and discuss the important aspects of these two types of risk considerations. What is real option analysis? How does it differ from the discounted cash flow approach to project evaluation? Why do some decision-makers prefer the real option approach over the DCF approach? Make sure you...
Problem 9-1 Sensitivity Analysis and Break-Even Point We are evaluating a project that costs $520,000, has...
Problem 9-1 Sensitivity Analysis and Break-Even Point We are evaluating a project that costs $520,000, has a five-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 64,000 units per year. Price per unit is $46, variable cost per unit is $26, and fixed costs are $832,000 per year. The tax rate is 35 percent, and we require a return of 20 percent on this project....
What is the primary difference between a sensitivity and a scenario analysis? A) in a sensitivity...
What is the primary difference between a sensitivity and a scenario analysis? A) in a sensitivity analysis, you allow one assumption to differ from the expect level at a time. In a scenario analysis, you allow at least two assumptions to differ from the expected level at the same time. B)In a sensitivity analysis, you allow one assumption to differ from the expected level at a time. In a scenario analysis, you solve for the value of one assumption that...
A. Sensitivity Analysis and Break-Even Point We are evaluating a project that costs $780,000, has an...
A. Sensitivity Analysis and Break-Even Point We are evaluating a project that costs $780,000, has an eight-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 92,000 units per year. Price per unit is $37, variable cost per unit is $23, and fixed costs are $875,000 per year. The tax rate is 35 percent, and we require a return of 15 percent on this project. B....
Discuss ways that breakeven and sensitivity analysis might be used together in evaluating a project. Which...
Discuss ways that breakeven and sensitivity analysis might be used together in evaluating a project. Which one would you use first and why? (There is no right or wrong answer here; I'm interested in your thoughts on how to apply these analytical methods.)
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT