Question

In: Finance

Problem 9-1 Sensitivity Analysis and Break-Even Point We are evaluating a project that costs $520,000, has...

Problem 9-1 Sensitivity Analysis and Break-Even Point

We are evaluating a project that costs $520,000, has a five-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 64,000 units per year. Price per unit is $46, variable cost per unit is $26, and fixed costs are $832,000 per year. The tax rate is 35 percent, and we require a return of 20 percent on this project.

a. Calculate the accounting break-even point. (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.)

Break-even point           units

b-1 Calculate the base-case cash flow and NPV. (Do not round intermediate calculations and round your NPV answer to 2 decimal places, e.g., 32.16.)

Cash flow $
NPV $


b-2
What is the sensitivity of NPV to changes in the sales figure? (Do not round intermediate calculations and round your answer to 3 decimal places, e.g., 32.161.)

?NPV/?Q          $

b-3 Calculate the change in NPV if sales were to drop by 500 units. (Enter your answer as a positive number. Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)

NPV would (Click to select)increasedecrease by $

c. What is the sensitivity of OCF to changes in the variable cost figure? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.)

?OCF/?VC          $

Solutions

Expert Solution

We need to calculate the Depreciation before we can go on to solving any of the other parts

Part A: Breakeven sales units can be calculated using the following formula:

At breakeven number of units there is 0 profit

So if the company sells 46800 units, it will not earn any profit nor make any loss.

Part B-1: Cash flow in base case NPV would be calculated as follows

(Sales Units*SP -Variable cos per unit*Sales units-Fixed cost- depreciation)*(1-tax rate)+Depreciation

(64000*46-26*64000-832000- 104000)*(1-0.35)+104000

Cash flow = 327600

Part B-2: Cash flow if sales price per unit falls by $1 would be calculated as follows

(Sales Units*SP -Variable cos per unit*Sales units-Fixed cost- depreciation)*(1-tax rate)+Depreciation

(64000*45-26*64000-832000- 104000)*(1-0.35)+104000

Cash flow = 286000

Change in Sales was 64000*(46-45) = $64000

Following is the calculation of sensitivity of NPV to Sales:

This means that for every $1 reduction in sales value, the NPV ruduces by $1.94 and vice versa

Part B-3: Cash flow if number of units fall by 500 would be calculated as follows

(Sales Units*SP -Variable cos per unit*Sales units-Fixed cost- depreciation)*(1-tax rate)+Depreciation

(63500*46-26*63500-832000- 104000)*(1-0.35)+104000

Cash flow = 321100

This means that due to a fall in number of units by 500, the NPV decreases by 19438.98

Part C: Cash flow if variable per unit falls by $1 would be calculated as follows

(Sales Units*SP -Variable cos per unit*Sales units-Fixed cost- depreciation)*(1-tax rate)+Depreciation

(64000*46-25*64000-832000- 104000)*(1-0.35)+104000

Cash flow = 362375

Change in Variable cost was 64000*(26-25) = $64000

Following is the calculation of sensitivity of NPV to VC:

This means that for every $1 reduction in VC, the NPV increases by $1.62 and vice versa


Related Solutions

A. Sensitivity Analysis and Break-Even Point We are evaluating a project that costs $780,000, has an...
A. Sensitivity Analysis and Break-Even Point We are evaluating a project that costs $780,000, has an eight-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 92,000 units per year. Price per unit is $37, variable cost per unit is $23, and fixed costs are $875,000 per year. The tax rate is 35 percent, and we require a return of 15 percent on this project. B....
Sensitivity Analysis and break-even point We are evaluating a project that costs $780,000, has an eight-year...
Sensitivity Analysis and break-even point We are evaluating a project that costs $780,000, has an eight-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 92,000 units per year. price per unit is $37, variable cost per unit is $23, and fixed costs are $875,000 per year. The tax rate is 35 percent, and we require a return of 15 percent on this project. A calculate...
Problem 11-5 Sensitivity Analysis and Break-Even [LO1, 3] We are evaluating a project that costs $630,700,...
Problem 11-5 Sensitivity Analysis and Break-Even [LO1, 3] We are evaluating a project that costs $630,700, has a seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 90,000 units per year. Price per unit is $46, variable cost per unit is $33, and fixed costs are $720,000 per year. The tax rate is 25 percent, and we require a return of 10 percent on this...
Problem 11-5 Sensitivity Analysis and Break-Even [LO1, 3] We are evaluating a project that costs $583,800,...
Problem 11-5 Sensitivity Analysis and Break-Even [LO1, 3] We are evaluating a project that costs $583,800, has a six-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 90,000 units per year. Price per unit is $41, variable cost per unit is $27, and fixed costs are $695,000 per year. The tax rate is 25 percent, and we require a return of 9 percent on this...
We are evaluating a project that costs $520,000, has a life of 6 years, and has...
We are evaluating a project that costs $520,000, has a life of 6 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 73,000 units per year. Price per unit is $45, variable cost per unit is $30, and fixed costs are $840,000 per year. The tax rate is 21 percent and we require a return of 15 percent on this project. a. Calculate the accounting break-even...
We are evaluating a project that costs $520,000, has a life of 6 years, and has...
We are evaluating a project that costs $520,000, has a life of 6 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 73,000 units per year. Price per unit is $45, variable cost per unit is $30, and fixed costs are $840,000 per year. The tax rate is 21 percent and we require a return of 15 percent on this project. Suppose the projections given for...
We are evaluating a project that costs $520,000, has a life of 6 years, and has...
We are evaluating a project that costs $520,000, has a life of 6 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 73,000 units per year. Price per unit is $45, variable cost per unit is $30, and fixed costs are $840,000 per year. The tax rate is 21 percent and we require a return of 15 percent on this project. Suppose the projections given for...
what are the drawbacks of sensitivity analysis, scenario analysis and break-even analysis? are they reliable in...
what are the drawbacks of sensitivity analysis, scenario analysis and break-even analysis? are they reliable in open market conditons?
What are sensitivity analysis, scenario analysis, break-even analysis, and simulation? Why are these analyses important, and...
What are sensitivity analysis, scenario analysis, break-even analysis, and simulation? Why are these analyses important, and how should they be used? please provide APA references !
(Break-even analysis) Project Accounting ​Break-Even Point​ (in units) Price per Unit Variable Cost per Unit Fixed...
(Break-even analysis) Project Accounting ​Break-Even Point​ (in units) Price per Unit Variable Cost per Unit Fixed Costs Depreciation A 6, 230 ​$52 ​$102,000 ​$26,000 B    760 ​$1,000 ​$499,000 ​$103,000 C 1,970 ​$25 ​$13 ​$5,000 D 1,970 ​$25 ​$7 ​$17,000 a.  Calculate the missing information for each of the above projects. b.  Note that Projects C and D share the same accounting​ break-even. If sales are above the​ break-even point, which project would you​ prefer? Explain why. c.  Calculate the cash​...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT