In: Finance
MNO (Japanese firm) is considering investing in a four year project that costs 22 million yen. MNO expects to receive 7 million yen and 20,000 pesos each year the project is in operation. The expected yen/peso exchange rate for each of the next four years is ¥5.5/peso in year one, ¥5.25/peso in year two, ¥6/peso in year three and ¥4.5/peso in year four. Find the net present value of the project (in yen) if the appropriate discount rate is 15%. Round intermediate steps to four decimals and your final answer to two decimals. Do not use currency symbols when entering your response.
I need the answer ASAP
A | B | C | D | E | F | G | H | I | J | K |
2 | ||||||||||
3 | First cash flow needs to be converted into Yen and then the NPV of the cash flow needs to be calculated: | |||||||||
4 | Year | 0 | 1 | 2 | 3 | 4 | ||||
5 | Initial investment | -¥7,000,000 | ||||||||
6 | Cash Inflow (Peso) | 20,000 | 20,000 | 20,000 | 20,000 | |||||
7 | Exchange rate (Yen per peso) | 5.5 | 5.25 | 6 | 4.5 | |||||
8 | Cash Inflow (Yen) | ¥110,000 | ¥105,000 | ¥120,000 | ¥90,000 | =H6*H7 | ||||
9 | Free Cash Flow | -¥7,000,000 | ¥110,000 | ¥105,000 | ¥120,000 | ¥90,000 | ||||
10 | ||||||||||
11 | Calculation of NPV: | |||||||||
12 | ||||||||||
13 | NPV of the project is present value of future cash flows discounted at required rate of return less the initial investment. | |||||||||
14 | Given the following cash flow and WACC, NPV for the project can be calculated as follows: | |||||||||
15 | Year | 0 | 1 | 2 | 3 | 4 | ||||
16 | Free Cash Flow (FCF) | -¥7,000,000 | ¥110,000 | ¥105,000 | ¥120,000 | ¥90,000 | ||||
17 | Discount rate (i) | 15% | ||||||||
18 | (P/F,i,n) for each year | 0.87 | 0.76 | 0.66 | 0.57 | =1/((1+$D17)^H15) | ||||
19 | Present Value of cash flows = FCF*(P/F,i,n) | ¥95,652 | ¥79,395 | ¥78,902 | ¥51,458 | =H16*H18 | ||||
20 | Present value if future cash flows | ¥305,407 | =SUM(E19:H19) | |||||||
21 | ||||||||||
22 | NPV for Project | =Present value fo future cash flows - Initial investment | ||||||||
23 | -¥6,694,593 | =D54+D50 | ||||||||
24 | ||||||||||
25 | Hence NPV of the project is | -¥6,694,593 | ||||||||
26 |