Question

In: Finance

Shell City considers 2 projects using the cost of capital of 12%. Project Sponge: cost $10,000,...

Shell City considers 2 projects using the cost of capital of 12%. Project Sponge: cost $10,000, cash flows of $4,300; $5,200, and $4,700 in 3 years respectively. Project Whale: cost $14,000, cash flows of $5,600; $4,100; $6,500; and $5,300 in 4 years respectively. What is the equivalent ANPV of Project Sponge?

$811.26

$1,330.06

$450.68

$553.77

What is the equivalent ANPV of Project Whale?

$821.44

$610.52

$745.16

$418.90

Solutions

Expert Solution

Calculating the NPV of Project Sponge and Project whale:-

Year Cash Flows of Project Sponge ($) Cash Flows of Project Whale ($) Cash IN-Flows ($) PV Factor @12.00% Present Value of Project Sponge($) Present Value of Project Whale ($)
0                    (10,000.00)                       (14,000.00)                             -   1.0000                    (10,000.00)                          (14,000.00)
1                         4,300.00                           5,600.00                             -   0.8929                         3,839.29                               5,000.00
2                         5,200.00                           4,100.00                      20.00 0.7972                         4,145.41                               3,268.49
3                         4,700.00                           6,500.00                      30.00 0.7118                         3,345.37                               4,626.57
4                                      -                             5,300.00 0.6355                                      -                                 3,368.25
NPV                         1,330.06                               2,263.31

a). Equivalent ANPV of Project Sponge = NPV of Project Sponge/PVIFA(12%, 3 years)

= 1330.06/2.4018

= $ 553.77

hence, Option D

Note- PVIFA(12%, 3 years) = [1/(1+0.12)^1] + [1/(1+0.12)^2] + [1/(1+0.12)^3]

= 0.8929 + 0.7972 + 0.7118

= 2.4018

b).  Equivalent ANPV of Project Whale = NPV of Project Whale/PVIFA(12%, 4 years)

= 2263.31/3.0373

= $ 745.17

Hence, Option C.

Note- PVIFA(12%, 3 years) = [1/(1+0.12)^1] + [1/(1+0.12)^2] + [1/(1+0.12)^3] + [1/(1+0.12)^4]

= 0.8929 + 0.7972 + 0.7118 + 0.6355

= 3.0373

If you need any clarification, you can ask in comments.     

If you like my answer, then please up-vote as it will be motivating


Related Solutions

A firm is considering the following projects. Its opportunity cost of capital is 12%. Project 0...
A firm is considering the following projects. Its opportunity cost of capital is 12%. Project 0 1 2 3 4 A -8,500 +1,875 +1,875 +4,750 0 B -4,500 0 +4,500 +3,750 +4,750 C -8,500 +1,875 +1,875 +4,750 +8,500 1) What is the payback period on each project? 2) What is the discounted payback period on each project?
Diamond City is considering two mutually exclusive investment projects. The cost of capital for these projects...
Diamond City is considering two mutually exclusive investment projects. The cost of capital for these projects is r. The projects’ expected net cash flows are as follows: Year Project A Project B 0 -42,000 -42,000 1 24,000 16,000 2 20,000 18,000 3 16,000 22,000 4 12,000 26,000 a. If r = 10%, which project should be selected under the NPV method? b. If r = 20%, which project should be selected under the NPV method? c. Calculate each project’s PI...
Diamond City is considering two mutually exclusive investment projects. The cost of capital for these projects...
Diamond City is considering two mutually exclusive investment projects. The cost of capital for these projects is r. The projects’ expected net cash flows are as follows: Year Project A Project B 0 -42,000 -42,000 1 24,000 16,000 2 20,000 18,000 3 16,000 22,000 4 12,000 26,000 a. Calculate each project’s payback (PB) period if r = 10% (up to 2 decimal places). Which project should be accepted? b. Calculate each project’s discounted payback (DPB) period if r = 10%...
Consider the following projects and assume an opportunity cost of capital of 12%.
Consider the following projects and assume an opportunity cost of capital of 12%. a. Calculate the Net Present Value (NPV) of each project. Which is to be preferred and why?(8 marks)b. If there is a capital constraint in place which limits spending to £10,000, which project or projects should be selected? Support your answer with calculations.
a project has a cost of 10000$ and the cost of capital is 12% what is...
a project has a cost of 10000$ and the cost of capital is 12% what is the net present value given that the cash flow from the project of next four years is 3500$ each year
Consider the following two projects. The cost of capital for both projects is 15%. Project Year...
Consider the following two projects. The cost of capital for both projects is 15%. Project Year 0 1 2 3 4 5 Alpha -55,000 15,000 14,000 22,000 30,000 35,000 Gamma -80,000 40,000 30,000 25,000 25,000 20,000 Calculate the IRR for each project and determine which one is better. Calculate the NPV for each project and determine which one is better. Based on profitability index method, which project is better? Overall, which project should be accepted assuming they are mutually exclusive?...
6.3: For the projects shown, what is the capital recovery cost? Project P Project Q Project...
6.3: For the projects shown, what is the capital recovery cost? Project P Project Q Project R Project S Project T Project U Initial Cost ($120,000) ($230,000) ($350,000) ($450,000) ($530,000) ($690,000) Salvage value (% of IC) 20% 15% -12% 16% -11% 32% Project life 3 4 5 6 7 9 Rate of interest (MARR) 12% 11% 14% 15% 13% 10%
Consider the following three projects; assume 14 percent cost of capital. Period Project A    Project...
Consider the following three projects; assume 14 percent cost of capital. Period Project A    Project B                   Project C                   T=0                                               ($3,000)                     ($5,000)                     ($2,000)                   T=1                                               $1,000                       $1,500                            $900                   T=2                                               $1,200                      $1,500                            $900                   T=3                                               $1,500                      $2,500                            $700                   T=4                                               $1,500                       $2,500                            $700                          When you have only $5,000 to support the above projects, which project (or projects) should be chosen under the Profitability Index?
A firm with a cost of capital of 10% considers the following capital investment: Cash Flows:...
A firm with a cost of capital of 10% considers the following capital investment: Cash Flows: Year 0 -4 million Year 1 26.5 Million Year 2 -24.2 Million (A) According to the IRR given by your financial calculator, should the firm accept this project? (B) Up to how many IRRs could this project have? (C) According to the MIRR, should the firm accept this project? (D) Should the firm accept this project? Justify your answer using the NPV. (Please show...
Capital Budgeting Methods Project S has a cost of $10,000 and is expected to produce benefits...
Capital Budgeting Methods Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,500 per year for 5 years. Project L costs $25,000 and is expected to produce cash flows of $8,000 per year for 5 years. Calculate the two projects' NPVs, assuming a cost of capital of 14%. Do not round intermediate calculations. Round your answers to the nearest cent. Project S: $   Project L: $   Which project would be selected, assuming they...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT