Question

In: Finance

Below is the data for the spreadsheet for a project selection model: Project              NPV (return)       cash...

Below is the data for the spreadsheet for a project selection model:

Project              NPV (return)       cash investment personnel requirements

1              75,000                 30,000                          10

2              50,000                 45,000                          5

3              25,000                 75,000                          10

4              85,000                 30,000                          4

5              50,000                 45,000                          8

6              25,000                 75,000                          7

7              95,000                 45,000                          6

8              25,000                 60,000                          1

9              75,000                 30,000                          2

10            65,000                 45,000                          2

You have $250,000 to invest and 36 people. Maximize NPV by approving/rejecting projects.

Multiple Choice #8: How many projects of the ten are approved?

A) 6

B) 4

C) 10
D) 5

Multiple Choice #9: If I told you that you cannot accept both projects #3 and project #4, would your current optimal solution change?

A) Yes; since we current accept both projects, we know the optimal answer would have to be different with an additional constraint.

B) No; since we are not accepting project #3 anyway, our current solution would still be optimal.

C) No; since we are not accepting project #4 anyway, our current solution would still be optimal.

D) No; since we are not accepting either project, our current solution would still be optimal.

E) There is no way we can tell unless we redefine the problem and rerun Solver.

Multiple Choice #10: Has project #3 been approved (in our optimal solution)?

A) Yes; this is one of the projects that has been approved.

B) No; there is enough spare (aka slack aka extra) cash, but not enough spare personnel.

C) No; there is enough spare personnel, but not enough spare cash to invest.
D) No; there is neither enough spare cash nor spare personnel.

Multiple Choice #11: Has project #8 been approved (in our optimal solution)?

A) Yes; this is one of the projects that has been approved.

B) No; there is enough spare (aka slack aka extra) cash, but not enough spare personnel.

C) No; there is enough spare personnel, but not enough spare cash to invest.
D) No; there is neither enough spare cash nor spare personnel.

Multiple Choice #12: What is the total amount of cash used for all accepted projects?

A) $ 480,000

B) $ 250,000

C) $ 360,000
D) $ 225,000

Multiple Choice #13: What is the total amount of personnel used for all accepted projects?

A) 36

B) 32

C) 40
D) 55

Multiple Choice #14: What is the total return obtained from all accepted projects?

A) $ 495,000

B) $ 330,000

C) $ 445,000

D) $ 570,000

Solutions

Expert Solution

Answers are:

(8): Option “a” – 6

(9): Option “b” - No; since we are not accepting project #3 anyway, our current solution would still be optimal.

(10): Option “d” - No; there is neither enough spare cash nor spare personnel.

(11): Option “c” - No; there is enough spare personnel, but not enough spare cash to invest.

(12): Option “d” – 225,000

(13): option “b” – 32

(14): option “c” – 445,000

Explanation:

In this case we will introduce binary variables for each project. Let the binary variables be a for project 1, b for project 2….. j for project 10.

Thus objective function = sum product of (binary variables, NPV) and has to be maximized.

Constraints:

(i): sum product of (binary variables, investment) <= 250,000

(ii) sum product of (binary variables, personnel requirements) <=36.

(iii): All variables (i.e. a to j) are binary

Solving in excel using the solver function we get the following solution:

Project   Binary variable NPV Investment Personnel NPV * binary variable binary variable * investment binary variable * personnel
                        1                                1            75,000              30,000                    10            75,000           30,000                 10
                        2                               -              50,000              45,000                      5                     -                       -                    -  
                        3                               -              25,000              75,000                    10                     -                       -                    -  
                        4                                1            85,000              30,000                      4            85,000           30,000                    4
                        5                                1            50,000              45,000                      8            50,000           45,000                    8
                        6                               -              25,000              75,000                      7                     -                       -                    -  
                        7                                1            95,000              45,000                      6            95,000           45,000                    6
                        8                               -              25,000              60,000                      1                     -                       -                    -  
                        9                                1            75,000              30,000                      2            75,000           30,000                    2
                     10                                1            65,000              45,000                      2            65,000           45,000                    2
Total          445,000         225,000                 32
Objective function                   445,000
Constraints
           225,000 <=          250,000
                     32 <=                    36

Related Solutions

(a) Develop proforma Project Income Statement Using Excel Spreadsheet (b) Compute Net Project Cash flows, NPV,...
(a) Develop proforma Project Income Statement Using Excel Spreadsheet (b) Compute Net Project Cash flows, NPV, IRR and PayBack Period (c) Develop Problem-Solving and Critical Thinking Skills 1) Life Period of the Equipment = 4 years 8) Sales for first year (1) $   200,000 2) New equipment cost $ (200,000) 9) Sales increase per year 5% 3) Equipment ship & install cost $     (35,000) 10) Operating cost: $ (120,000) 4) Related start up cost $       (5,000)     (60 Percent of...
Calculate the NPV for a 3-year project with the following cash flows and a required return...
Calculate the NPV for a 3-year project with the following cash flows and a required return of 15%: CF0 = -$800,000 ATCF1 = $160,000 ATCF2 = $160,000 ATCF3 = $160,000 ATER = $600,000 Calculate the IRR for a 2-year project with the following cash flows and a required return of 12%: CFO = -$375,000 ATCF1 = $27,500 ATCF2 = -$134,800 ATER = $596,000 ATER = After-Tax Equity Reversion ATCF = After-Tac Cash Flow Please show me how you answer the...
Based on the data presented in the Spreadsheet below (Cash Budget tab), calculate the cash receipts...
Based on the data presented in the Spreadsheet below (Cash Budget tab), calculate the cash receipts for the first quarter of this year. Complete your calculations by filling in the highlighted cells. Discuss your observations about the way cash is collected if the company needs $150,000 per month for expenses. Cookie Business The budgeted credit sales are as follows: December last year $          250,000 January $          125,000 February $          300,000 March $             90,000 Collection: Month of the sale 80% Month...
With the data below, calculate NPV for the following Project Project life is 5 year Sales...
With the data below, calculate NPV for the following Project Project life is 5 year Sales forecasting for yr1 is $485,000 follow by sales Growth rate of 15.650%, 13.85%, 12.50% & 10.90% COGS as % of annual sales is 63.15 cap invest $275,000 to be depreciated over 6year Salvage value $81,000 Beg NWC $8900 NWC as % of Sales 1.05% WACC 10.23% Tax rate 35.40% The Firm could rent out the property for $1950/yr if they decide to not go...
NPV profile of a project. Given the following cash flow of Project​ L-2, draw the NPV...
NPV profile of a project. Given the following cash flow of Project​ L-2, draw the NPV profile. Hint​: Be sure to use a discount rate of zero for one intercept ​(y​-axis) and solve for the IRR for the other intercept ​(x​-axis). Year 0   -$250,000 Year 1   $49,000 Year 2   $80,000 Year 3   $114,000 Year 4   $139,000 What is the NPV of Project​ L-2 where zero is the discount​ rate? What is the IRR of Project​ L-2? Which of the graphs...
Calculate the NPV for Project A and accept or reject the project with the cash flows...
Calculate the NPV for Project A and accept or reject the project with the cash flows shown below if the appropriate cost of capital is 7% Project A Time 0 1 2 3 4 5 Cash Flow -990 350 480 500 630 120 2) Calculate the NPV for project L and recommend whether the company should accept or reject the project. Cost of Capital is 6% Project L Time 0 1 2 3 4 5 Cash Flow -         8,600          ...
What is the role that the required rate of return plays in the NPV model? In...
What is the role that the required rate of return plays in the NPV model? In the IRR model? Consider some real-life example situations where NPV and IRR should be applied and why rate of return is so important.
A. What is the NPV of the following cash flows if the required rate of return...
A. What is the NPV of the following cash flows if the required rate of return is 0.05? Year 0 1 2 3 4 CF -13868 2129 2503 694 3244    Enter the answer with 2 decimals (e.g. 1000.23). B. Winnebagel Corp. currently sells 39298 motor homes per year at $59840 each, and 17359 luxury motor coaches per year at $116566 each. The company wants to introduce a new portable camper to fill out its product line; it hopes to...
Given the cash-flows in the table, what is the NPV of project A?
1. Project A Year Cash Flow 0 -$107 1 $69 2 $80 3 $120 WACC = 6.19% Given the cash-flows in the table, what is the NPV of project A?   State your answer to the nearest penny. Give just the number with no dollar sign (e.g., 3.26) If the NPV is negative include the - sign (e.g. -4.28) 2. Using the information in the table, what is the IRR for Project A? Cash Flow Year Project A 0 ($175) 1...
While NPV and IRR are measures of return of a project/investment. Payback is a measure of...
While NPV and IRR are measures of return of a project/investment. Payback is a measure of risk. Explain what payback tells about a project/investment and how is it calculated.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT