A new wastewater treatment plant was built to treat the
wastewater flow 800,000 gpd. The capital cost to build the
wastewater treatment plant was $6,000,000. The annual operation and
maintenance costs of operating the plant is $700,000/year. Estimate
the cost of treating 1000 gallons of wastewater ($/1000 gallon).
Assume the design life as 20 years and interest rate of 4%.