Question

In: Chemistry

A new wastewater treatment plant was built to treat the wastewater flow 800,000 gpd. The capital...

A new wastewater treatment plant was built to treat the wastewater flow 800,000 gpd. The capital cost to build the wastewater treatment plant was $6,000,000. The annual operation and maintenance costs of operating the plant is $700,000/year. Estimate the cost of treating 1000 gallons of wastewater ($/1000 gallon). Assume the design life as 20 years and interest rate of 4%.

Solutions

Expert Solution

Wastewater treatment plant capacity= 800000 gpd

Design life= 20 years

Interest rate = 4%

Capital cost = $6000000

Annual maintenance = $700000/years

  • Total cost of plant for 20 years =

(Capital cost + interest cost for 20 years) + (Maintenance cost for 20 years + compound interest cost for over 20 years)

  • Capital cost= $ 6,000,000
  • Interest cost for 20 years = ($ 6000000 * 0.04) * 20 = $ 48, 00, 000
  • Maintenance cost for 20 years + compound interest cost for over 20 years =

A = B/C {(1+C) n – 1}

Where, A = Maintenance cost for 20 years + compound interest cost for over 20 years

            B= Yearly maintenance cost = $ 7, 00,000

            C = Interest rate = 4% = 0.04

            n= Number of years = 20

Therefore, A = (7, 00,000/0.04) {(1+ 0.04)20 – 1}

        = (7, 00,000/0.04) * 1.19

        = $ 2, 08, 25,000

Total cost of plant for 20 years = ($ 6,000,000 + $ 48, 00, 000) + ($ 2, 08, 25, 000)

                                              = $ 31, 36, 50, 000

  • Total amount of water processed over 20 years = (Daily capacity of plant) * 365 * 20

     = 8, 00, 000 * 365 * 20

     = 58 40 000 000 gallon

  • Cost per gallon = (Total cost of plant for 20 years) / (Total amount of water processed over 20 years)

      = ($31, 36, 50, 000) / (58, 40, 000, 000 gallon)

      = $ 0.00542 /gallon

Cost per 1000 gallon = $ 0.00542 * 1000 = $5.42 / gallon

  


Related Solutions

The wastewater treatment plant will also treat wastewater originating from the industrial activity of textile mills...
The wastewater treatment plant will also treat wastewater originating from the industrial activity of textile mills in the future. proposed and describe appropriate unit processes that can be added to the plant.
The total flow at a wastewater treatment plant is 682 m3/day. The purpose of the plant...
The total flow at a wastewater treatment plant is 682 m3/day. The purpose of the plant is to remove compound Z from the wastewater by treating it in reactors, using a newly developed microbial process. Assume the microbial treatment can be modeled as a first order reaction with a rate coefficient of 0.36/h. Suppose the flow is split evenly and treated in two parallel reactors– one complete mix and one plug flow -- each with a volume of 88 x...
A wastewater treatment plant has a rupture in one of their flow tubes, thereby leading to...
A wastewater treatment plant has a rupture in one of their flow tubes, thereby leading to the discharge of waste material into a local lake system. The rupture goes unnoticed for a long enough time that the concentration of the waste in the lake reaches a steady state. Assume that the lake can be modeled as a continuously stirred tank reactor, with inflow, outflow, and complete mixing, and that the lake flows so that the volume remains constant at 107...
The Wilson Wastewater Treatment Plant currently provides primary treatment for a flow rate of 2500 m3/day....
The Wilson Wastewater Treatment Plant currently provides primary treatment for a flow rate of 2500 m3/day. The effluent from the primary tank has a soluble BOD5= 240 mg/L. You need to design an activated sludge treatment to update the plant. The secondary effluent standards to meet are 25.0 mg/L BOD5 total (suspended and soluble BOD) and 30 mg/L suspended solids. Use the following assumptions: Target soluble BOD5 in the effluent of the secondary treatment is 2.5 mg/L. Growth constants can...
A wastewater treatment plant that treats wastewater to secondary treatment standards uses a primary sedimentation process...
A wastewater treatment plant that treats wastewater to secondary treatment standards uses a primary sedimentation process followed by an activated sludge process composed of aeration tanks and a secondary clarifiers. This problem focuses on the activated sludge process. The activated sludge process receives a flow of 15 million gallons per day (MGD). The primary sedimentation process effluent has a BOD5 concentration of 180 mgBOD5/L (this concentration is often referred as S). Before flowing into the activated sludge process, the primary...
Design rapid sand filters for a water treatment plant to treat a flow rate of 25...
Design rapid sand filters for a water treatment plant to treat a flow rate of 25 mgd. Use 1.5 for a peak factor. Consider the location of overflow troughs, freeboard, and pressure head of water. Assume that the length of the filters is 2 times the width and that the filtration rate is 3 gpm/ft2. Assume anthracite over sand with 1 ft gravel under media, top of water level during filtration is below troughs, and a 3 ft head drop...
A municipal wastewater treatment plant discharges 20,000 m3/d of treated wastewater to a stream. The wastewater...
A municipal wastewater treatment plant discharges 20,000 m3/d of treated wastewater to a stream. The wastewater has a BOD5 of 30 mg/L with a k1 of 0.23 d-1. The temperature of the wastewater is 20 oC, and the dissolved oxygen is 2.0 mg/L. The stream just above the point of wastewater discharge flows at 0.65 m3/s, has a BOD5 of 5.0 mg/L, and is 90% saturated with oxygen. The temperature of the stream is also 20 oC. After mixing, the...
Your task is to build a wastewater treatment plant to handle all of the domestic wastewater...
Your task is to build a wastewater treatment plant to handle all of the domestic wastewater produced by a housing estate. Using population equivalent, PE = 65000, design, describe and calculate briefly the sizes of all the unit processes in the treatment plant that are going to be built. You may assume the value that is not given.
A municipal wastewater treatment plant is designed for COD removal and nitrification. The wastewater characteristics and...
A municipal wastewater treatment plant is designed for COD removal and nitrification. The wastewater characteristics and kinetic coefficients are described in the table below. The aeration tank DO concentration is 2.0 mg/L and MLSS concentration is 2500 mg/L. The temperature is 15C. Assume that the concentration of influent NH4-N that is nitrified accounts for 80% of influent TKN. Calculate the following parameters as a function of SRT (i.e., derive mathematical expressions of the following parameters as a function of SRT,...
Your task is to build a wastewater treatment plant to handle all of the domestic wastewater...
Your task is to build a wastewater treatment plant to handle all of the domestic wastewater produced by a housing estate. Using population equivalent, PE = 65000, design, describe and calculate briefly the sizes of all the unit processes in the treatment plant that are going to be built. You may assume the value that is not given.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT