Question

In: Finance

An all-equity firm is considering the following projects: Project Beta IRR W .80 9.3% X .90...

An all-equity firm is considering the following projects:

Project

Beta

IRR

W

.80

9.3%

X

.90

10.6

Y

1.10

11.4

Z

1.35

14.1

The T-bill rate is 4 percent, and the expected return on the market is 11 percent.

  1. Which projects have a higher expected return than the firm’s 11 percent cost of capital?

  2. Which projects should be accepted?

  3. Which projects will be incorrectly accepted or rejected if the firm’s overall cost of capital were used as a hurdle rate?

Solutions

Expert Solution

Answer :

The formula for expected return is as follows:

Expected return = Risk-free rate + Beta * ( Market return - Risk-free rate )

The risk-free rate is 4% and market return is 11%. Calculate the expected return for each project as follows:

Project Beta IRR Expected Return
W 0.80 9.30% 9.60%
X 0.90 10.60% 10.30%
Y 1.10 11.40% 11.70%
Z 1.35 14.10% 13.45%

Expected return for the above table is calculated below as follows:

W = 4% + 0.80 * ( 11% - 4% ) = 4% + 5.6% = 9.60%

X = 4% + 0.90 * ( 11% - 4% ) = 4% + 6.30% = 10.30%

Y = 4% + 1.10 * ( 11% - 4% ) = 4% + 7.70% = 11.70%

Z = 4% + 1.35 * ( 11% - 4% ) = 4% + 9.45% = 13.45%

1) Projects having expected return higher than the cost of capital of 11% are Project Y with 11.70% expected return and Project Z with 13.45% expected return.

2) Project which has expected return higher than the IRR should be accepted. Project W with 9.60% expected return and Project Y with 11.70% expected return should be accepted.

3) In case, the firm's overall cost of capital was used as a hurdle rate, then Project W would be accepted incorrectly as it has expected return of 9.60% which is lower than 11% cost of capital. And Project X would be accepted incorrectly as it has expected return of 10.30% which is lower than 11% cost of capital and Project Y would be incorrectly rejected as it has expected return of 11.70% which is greater than 11% cost of capital and Project Z would be incorrectly rejected as it has expected return of 13.45% which is greater than 11% cost of capital.


Related Solutions

An all-equity firm is considering the following projects: Project Beta IRR W .59 8.9 % X...
An all-equity firm is considering the following projects: Project Beta IRR W .59 8.9 % X .86 9.6 Y 1.14 12.0 Z 1.46 15.1 The T-bill rate is 4.1 percent, and the expected return on the market is 11.1 percent. a. Compared with the firm's 11.1 percent cost of capital, Project W has a expected return, Project X has a expected return, Project Y has a expected return, and Project Z has a expected return. b. Project W should be...
An all-equity firm is considering the following projects: Project Beta IRR W .57 9.1 % X...
An all-equity firm is considering the following projects: Project Beta IRR W .57 9.1 % X .88 9.8 Y 1.12 12.2 Z 1.48 15.3 The T-bill rate is 4.3 percent, and the expected return on the market is 11.3 percent. Please select one option in every parenthese. Those are the answers. a. Compared with the firm's 11.3 percent cost of capital, Project W has a (lower or higher) expected return, Project X has a (lower or higher) expected return, Project...
An all-equity firm is considering the following projects: Project Beta IRR W .70 9.9 % X...
An all-equity firm is considering the following projects: Project Beta IRR W .70 9.9 % X .77 10.9 Y 1.43 14.4 Z 1.54 17.4 The T-bill rate is 5.4 percent, and the expected return on the market is 12.4 percent. a. Compared with the firm's 12.4 percent cost of capital, Project W has a (Click to select)higherlower expected return, Project X has a (Click to select)lowerhigher expected return, Project Y has a (Click to select)higherlower expected return, and Project Z...
2) An all equity firm is considering the following projects: Project beta Expected Return W 0.75...
2) An all equity firm is considering the following projects: Project beta Expected Return W 0.75 10% X 0.9 10.2 Y 1.2 12.0 Z 1.5 15 Assume that the firm has a overall cost of capital of 11%assume that the T Bill is 5%, and the market return is 11 % expected Which projects should be accepted? Which projects will be incorrectly accepted or rejected if the firm used its overall cost of capital as a hurdle rate?
Porto Berhad is an all-equity firm. The company is considering the following projects: Project Beta Expected...
Porto Berhad is an all-equity firm. The company is considering the following projects: Project Beta Expected return Barcelona 0.70 11% Juventus 0.85 14% PSG 1.30 16% Chelsea 1.50 18% The T-bill rate is 9 percent and the expected return on the market is 12 percent. a.Evaluate which projects have higher expected return than the firm’s 12 percent cost of capital b. Assess which projects would be incorrectly accepted or rejected if the firm’s overall cost of capital were used as...
A firm evaluates all of its projects by applying the IRR rule. A project under consideration...
A firm evaluates all of its projects by applying the IRR rule. A project under consideration has the following cash flows? YearCash Flow0–$28,000 1 -12,000 2 -15,000 3 -11,000
A firm evaluates all of its projects by applying the IRR rule. A project under consideration...
A firm evaluates all of its projects by applying the IRR rule. A project under consideration has the following cash flows:     Year Cash Flow 0 –$ 27,100 1 11,100 2 14,100 3 10,100    1.If the required return is 15 percent, what is the IRR for this project? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) IRR %    2.Should the firm accept the project? No Yes
A firm evaluates all of its projects by applying the IRR rule. A project under consideration...
A firm evaluates all of its projects by applying the IRR rule. A project under consideration has the following cash flows:     Year Cash Flow 0 –$ 27,100 1 11,100 2 14,100 3 10,100    1.If the required return is 15 percent, what is the IRR for this project? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)   IRR %    2. Should the firm accept the project? Yes No
Consider two projects, X and Y. Project X's IRR is 19% and Project Y's IRR is...
Consider two projects, X and Y. Project X's IRR is 19% and Project Y's IRR is 17%. The projects have the same risk and the same lives, and each has constant cash flows during each year of their lives. If the cost of capital is 10%, Project Y has a higher NPV than X. Given this information, which of the following statements is CORRECT?    a. The crossover rate must be greater than 10%. b. If the cost of capital...
GeoGrocers is considering the following independent, average-risk investment projects: Project Size of Project Project IRR Project...
GeoGrocers is considering the following independent, average-risk investment projects: Project Size of Project Project IRR Project A $1.0 million 12.0% Project B 1.2 million 11.5% Project C 1.2 million 11.0% Project D 1.2 million 10.5% Project E 1.0 million 10.0% The company has a target capital structure that consists of 50 percent debt and 50 percent equity. Its after-tax cost of debt is 8 percent, its cost of equity is estimated to be 13.5 percent, and its net income is...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT