Question

In: Finance

An all-equity firm is considering the following projects: Project Beta IRR W .80       9.3 %...

An all-equity firm is considering the following projects:
Project Beta IRR
W .80       9.3 %
X .90       11.4
Y 1.10       12.1
Z 1.35       15.1
The T-bill rate is 4 percent, and the expected return on the market is 12 percent.
a. Which projects have a higher expected return than the firm’s 12 percent cost of capital?


b. Which projects should be accepted?


c.

Which projects will be incorrectly accepted/rejected or correctly accepted/rejected if the firm's overall cost of capital were used as a hurdle rate?

Solutions

Expert Solution


Related Solutions

An all-equity firm is considering the following projects: Project Beta IRR W .80 9.3% X .90...
An all-equity firm is considering the following projects: Project Beta IRR W .80 9.3% X .90 10.6 Y 1.10 11.4 Z 1.35 14.1 The T-bill rate is 4 percent, and the expected return on the market is 11 percent. Which projects have a higher expected return than the firm’s 11 percent cost of capital? Which projects should be accepted? Which projects will be incorrectly accepted or rejected if the firm’s overall cost of capital were used as a hurdle rate?
An all-equity firm is considering the following projects: Project Beta IRR W .59 8.9 % X...
An all-equity firm is considering the following projects: Project Beta IRR W .59 8.9 % X .86 9.6 Y 1.14 12.0 Z 1.46 15.1 The T-bill rate is 4.1 percent, and the expected return on the market is 11.1 percent. a. Compared with the firm's 11.1 percent cost of capital, Project W has a expected return, Project X has a expected return, Project Y has a expected return, and Project Z has a expected return. b. Project W should be...
An all-equity firm is considering the following projects: Project Beta IRR W .57 9.1 % X...
An all-equity firm is considering the following projects: Project Beta IRR W .57 9.1 % X .88 9.8 Y 1.12 12.2 Z 1.48 15.3 The T-bill rate is 4.3 percent, and the expected return on the market is 11.3 percent. Please select one option in every parenthese. Those are the answers. a. Compared with the firm's 11.3 percent cost of capital, Project W has a (lower or higher) expected return, Project X has a (lower or higher) expected return, Project...
An all-equity firm is considering the following projects: Project Beta IRR W .70 9.9 % X...
An all-equity firm is considering the following projects: Project Beta IRR W .70 9.9 % X .77 10.9 Y 1.43 14.4 Z 1.54 17.4 The T-bill rate is 5.4 percent, and the expected return on the market is 12.4 percent. a. Compared with the firm's 12.4 percent cost of capital, Project W has a (Click to select)higherlower expected return, Project X has a (Click to select)lowerhigher expected return, Project Y has a (Click to select)higherlower expected return, and Project Z...
2) An all equity firm is considering the following projects: Project beta Expected Return W 0.75...
2) An all equity firm is considering the following projects: Project beta Expected Return W 0.75 10% X 0.9 10.2 Y 1.2 12.0 Z 1.5 15 Assume that the firm has a overall cost of capital of 11%assume that the T Bill is 5%, and the market return is 11 % expected Which projects should be accepted? Which projects will be incorrectly accepted or rejected if the firm used its overall cost of capital as a hurdle rate?
Porto Berhad is an all-equity firm. The company is considering the following projects: Project Beta Expected...
Porto Berhad is an all-equity firm. The company is considering the following projects: Project Beta Expected return Barcelona 0.70 11% Juventus 0.85 14% PSG 1.30 16% Chelsea 1.50 18% The T-bill rate is 9 percent and the expected return on the market is 12 percent. a.Evaluate which projects have higher expected return than the firm’s 12 percent cost of capital b. Assess which projects would be incorrectly accepted or rejected if the firm’s overall cost of capital were used as...
A firm evaluates all of its projects by applying the IRR rule. A project under consideration...
A firm evaluates all of its projects by applying the IRR rule. A project under consideration has the following cash flows? YearCash Flow0–$28,000 1 -12,000 2 -15,000 3 -11,000
A firm evaluates all of its projects by applying the IRR rule. A project under consideration...
A firm evaluates all of its projects by applying the IRR rule. A project under consideration has the following cash flows:     Year Cash Flow 0 –$ 27,100 1 11,100 2 14,100 3 10,100    1.If the required return is 15 percent, what is the IRR for this project? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) IRR %    2.Should the firm accept the project? No Yes
A firm evaluates all of its projects by applying the IRR rule. A project under consideration...
A firm evaluates all of its projects by applying the IRR rule. A project under consideration has the following cash flows:     Year Cash Flow 0 –$ 27,100 1 11,100 2 14,100 3 10,100    1.If the required return is 15 percent, what is the IRR for this project? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)   IRR %    2. Should the firm accept the project? Yes No
GeoGrocers is considering the following independent, average-risk investment projects: Project Size of Project Project IRR Project...
GeoGrocers is considering the following independent, average-risk investment projects: Project Size of Project Project IRR Project A $1.0 million 12.0% Project B 1.2 million 11.5% Project C 1.2 million 11.0% Project D 1.2 million 10.5% Project E 1.0 million 10.0% The company has a target capital structure that consists of 50 percent debt and 50 percent equity. Its after-tax cost of debt is 8 percent, its cost of equity is estimated to be 13.5 percent, and its net income is...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT