In: Finance
An all-equity firm is considering the following
projects:
Project | Beta | IRR | ||||
W | .70 | 9.9 | % | |||
X | .77 | 10.9 | ||||
Y | 1.43 | 14.4 | ||||
Z | 1.54 | 17.4 | ||||
The T-bill rate is 5.4 percent, and the expected return on the
market is 12.4 percent.
a. Compared with the firm's 12.4 percent cost of
capital, Project W has a (Click to select)higherlower expected
return, Project X has a (Click to select)lowerhigher expected
return, Project Y has a (Click to select)higherlower expected
return, and Project Z has a (Click to select)higherlower expected
return.
b. Project W should be (Click to
select)rejectedaccepted , Project X should be (Click to
select)rejectedaccepted , Project Y should be (Click to
select)rejectedaccepted , and Project Z should be (Click to
select)rejectedaccepted .
c. If the firm's overall cost of capital were used
as a hurdle rate, Project W would be (Click to select)incorrectly
rejectedincorrectly acceptedcorrectly rejectedcorrectly accepted ,
Project X would be (Click to select)correctly acceptedincorrectly
acceptedincorrectly rejectedcorrectly rejected , Project Y would be
(Click to select)correctly acceptedcorrectly rejectedincorrectly
acceptedincorrectly rejected , and Project Z would be (Click to
select)correctly rejectedincorrectly rejectedcorrectly
acceptedincorrectly accepted .
a). According to CAPM,
kE = rF + beta[E(rM) - rF]
kEW = 5.4% + 0.70[12.4% - 5.4%] = 5.4% + 4.9% = 10.30%
Compared with the firm's 12.4 percent cost of capital, Project W has a lower expected return.
kEX = 5.4% + 0.77[12.4% - 5.4%] = 5.4% + 5.39% = 10.79%
Compared with the firm's 12.4 percent cost of capital, Project X has a lower expected return.
kEY = 5.4% + 1.43[12.4% - 5.4%] = 5.4% + 10.01% = 15.41%
Compared with the firm's 12.4 percent cost of capital, Project Y has a higher expected return.
kEZ = 5.4% + 1.54[12.4% - 5.4%] = 5.4% + 10.78% = 16.18%
Compared with the firm's 12.4 percent cost of capital, Project Z has a higher expected return.
b). Project W should be accepted, Project X should be rejected, Project Y should be accepted, and Project Z should be rejected.
c). If the firm's overall cost of capital were used as a hurdle rate, Project W would be incorrectly rejected, Project X would be correctly rejected, Project Y would be correctly accepted, and Project Z would be incorrectly accepted.