Question

In: Finance

An all-equity firm is considering the following projects: Project Beta IRR W .70 9.9 % X...

An all-equity firm is considering the following projects:

Project Beta IRR
W .70 9.9 %
X .77 10.9
Y 1.43 14.4
Z 1.54 17.4


The T-bill rate is 5.4 percent, and the expected return on the market is 12.4 percent.

a. Compared with the firm's 12.4 percent cost of capital, Project W has a (Click to select)higherlower expected return, Project X has a (Click to select)lowerhigher expected return, Project Y has a (Click to select)higherlower expected return, and Project Z has a (Click to select)higherlower expected return.

b. Project W should be (Click to select)rejectedaccepted , Project X should be (Click to select)rejectedaccepted , Project Y should be (Click to select)rejectedaccepted , and Project Z should be (Click to select)rejectedaccepted .

c. If the firm's overall cost of capital were used as a hurdle rate, Project W would be (Click to select)incorrectly rejectedincorrectly acceptedcorrectly rejectedcorrectly accepted , Project X would be (Click to select)correctly acceptedincorrectly acceptedincorrectly rejectedcorrectly rejected , Project Y would be (Click to select)correctly acceptedcorrectly rejectedincorrectly acceptedincorrectly rejected , and Project Z would be (Click to select)correctly rejectedincorrectly rejectedcorrectly acceptedincorrectly accepted .

Solutions

Expert Solution

a). According to CAPM,

kE = rF + beta[E(rM) - rF]

kEW = 5.4% + 0.70[12.4% - 5.4%] = 5.4% + 4.9% = 10.30%

Compared with the firm's 12.4 percent cost of capital, Project W has a lower expected return.

kEX = 5.4% + 0.77[12.4% - 5.4%] = 5.4% + 5.39% = 10.79%

Compared with the firm's 12.4 percent cost of capital, Project X has a lower expected return.

kEY = 5.4% + 1.43[12.4% - 5.4%] = 5.4% + 10.01% = 15.41%

Compared with the firm's 12.4 percent cost of capital, Project Y has a higher expected return.

kEZ = 5.4% + 1.54[12.4% - 5.4%] = 5.4% + 10.78% = 16.18%

Compared with the firm's 12.4 percent cost of capital, Project Z has a higher expected return.

b). Project W should be accepted, Project X should be rejected, Project Y should be accepted, and Project Z should be rejected.

c). If the firm's overall cost of capital were used as a hurdle rate, Project W would be incorrectly rejected, Project X would be correctly rejected, Project Y would be correctly accepted, and Project Z would be incorrectly accepted.


Related Solutions

An all-equity firm is considering the following projects: Project Beta IRR W .59 8.9 % X...
An all-equity firm is considering the following projects: Project Beta IRR W .59 8.9 % X .86 9.6 Y 1.14 12.0 Z 1.46 15.1 The T-bill rate is 4.1 percent, and the expected return on the market is 11.1 percent. a. Compared with the firm's 11.1 percent cost of capital, Project W has a expected return, Project X has a expected return, Project Y has a expected return, and Project Z has a expected return. b. Project W should be...
An all-equity firm is considering the following projects: Project Beta IRR W .57 9.1 % X...
An all-equity firm is considering the following projects: Project Beta IRR W .57 9.1 % X .88 9.8 Y 1.12 12.2 Z 1.48 15.3 The T-bill rate is 4.3 percent, and the expected return on the market is 11.3 percent. Please select one option in every parenthese. Those are the answers. a. Compared with the firm's 11.3 percent cost of capital, Project W has a (lower or higher) expected return, Project X has a (lower or higher) expected return, Project...
An all-equity firm is considering the following projects: Project Beta IRR W .80 9.3% X .90...
An all-equity firm is considering the following projects: Project Beta IRR W .80 9.3% X .90 10.6 Y 1.10 11.4 Z 1.35 14.1 The T-bill rate is 4 percent, and the expected return on the market is 11 percent. Which projects have a higher expected return than the firm’s 11 percent cost of capital? Which projects should be accepted? Which projects will be incorrectly accepted or rejected if the firm’s overall cost of capital were used as a hurdle rate?
An all-equity firm is considering the following projects: Project Beta IRR W .80       9.3 %...
An all-equity firm is considering the following projects: Project Beta IRR W .80       9.3 % X .90       11.4 Y 1.10       12.1 Z 1.35       15.1 The T-bill rate is 4 percent, and the expected return on the market is 12 percent. a. Which projects have a higher expected return than the firm’s 12 percent cost of capital? b. Which projects should be accepted? c. Which projects will be incorrectly accepted/rejected or correctly accepted/rejected if the firm's overall...
2) An all equity firm is considering the following projects: Project beta Expected Return W 0.75...
2) An all equity firm is considering the following projects: Project beta Expected Return W 0.75 10% X 0.9 10.2 Y 1.2 12.0 Z 1.5 15 Assume that the firm has a overall cost of capital of 11%assume that the T Bill is 5%, and the market return is 11 % expected Which projects should be accepted? Which projects will be incorrectly accepted or rejected if the firm used its overall cost of capital as a hurdle rate?
Porto Berhad is an all-equity firm. The company is considering the following projects: Project Beta Expected...
Porto Berhad is an all-equity firm. The company is considering the following projects: Project Beta Expected return Barcelona 0.70 11% Juventus 0.85 14% PSG 1.30 16% Chelsea 1.50 18% The T-bill rate is 9 percent and the expected return on the market is 12 percent. a.Evaluate which projects have higher expected return than the firm’s 12 percent cost of capital b. Assess which projects would be incorrectly accepted or rejected if the firm’s overall cost of capital were used as...
A firm evaluates all of its projects by applying the IRR rule. A project under consideration...
A firm evaluates all of its projects by applying the IRR rule. A project under consideration has the following cash flows? YearCash Flow0–$28,000 1 -12,000 2 -15,000 3 -11,000
A firm evaluates all of its projects by applying the IRR rule. A project under consideration...
A firm evaluates all of its projects by applying the IRR rule. A project under consideration has the following cash flows:     Year Cash Flow 0 –$ 27,100 1 11,100 2 14,100 3 10,100    1.If the required return is 15 percent, what is the IRR for this project? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) IRR %    2.Should the firm accept the project? No Yes
A firm evaluates all of its projects by applying the IRR rule. A project under consideration...
A firm evaluates all of its projects by applying the IRR rule. A project under consideration has the following cash flows:     Year Cash Flow 0 –$ 27,100 1 11,100 2 14,100 3 10,100    1.If the required return is 15 percent, what is the IRR for this project? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)   IRR %    2. Should the firm accept the project? Yes No
Consider two projects, X and Y. Project X's IRR is 19% and Project Y's IRR is...
Consider two projects, X and Y. Project X's IRR is 19% and Project Y's IRR is 17%. The projects have the same risk and the same lives, and each has constant cash flows during each year of their lives. If the cost of capital is 10%, Project Y has a higher NPV than X. Given this information, which of the following statements is CORRECT?    a. The crossover rate must be greater than 10%. b. If the cost of capital...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT