In: Finance
You are given the following information about Project Y and Project Z.
Year Proj Y Proj Z
0 ($225,000) ($225,000)
1 210,000 95,000
2 98,000 88,000
3 — 73,000
4 — 87,500
The projects provide a necessary service, so whichever one is selected is expected to be repeated into the foreseeable future. Both projects have an 9% cost of capital.
a. What is each project’s initial NPV without replication? Which project will you choose?
b. What is the IRR of each project?
c. What is each project’s equivalent annual annuity? Which project will you choose?
d. Now apply the replacement chain approach to determine the shorter project’s extended NPV. Which project should be chosen?
e. Now assume that the cost to replicate Project Y in 2 years will increase to $290,000 because of inflationary pressures. How should the analysis be handled now, and which project should be chosen?