In: Accounting
Ziege Systems is considering the following independent projects for the coming year:
Project |
Required Investment |
Rate of Return |
Risk |
A | $4 million | 11.25% | High |
B | 5 million | 13.75 | High |
C | 3 million | 9.25 | Low |
D | 2 million | 9 | Average |
E | 6 million | 12.25 | High |
F | 5 million | 12.25 | Average |
G | 6 million | 7 | Low |
H | 3 million | 11 | Low |
Ziege's WACC is 9.75%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2% for low-risk projects.
Which projects should Ziege accept if it faces no capital constraints?
Project A | -Select-AcceptRejectItem 1 |
Project B | -Select-AcceptRejectItem 2 |
Project C | -Select-AcceptRejectItem 3 |
Project D | -Select-AcceptRejectItem 4 |
Project E | -Select-AcceptRejectItem 5 |
Project F | -Select-AcceptRejectItem 6 |
Project G | -Select-AcceptRejectItem 7 |
Project H | -Select-AcceptRejectItem 8 |
If Ziege can only invest a total of $13 million, which projects should it accept?
Project A | -Select-AcceptRejectItem 9 |
Project B | -Select-AcceptRejectItem 10 |
Project C | -Select-AcceptRejectItem 11 |
Project D | -Select-AcceptRejectItem 12 |
Project E | -Select-AcceptRejectItem 13 |
Project F | -Select-AcceptRejectItem 14 |
Project G | -Select-AcceptRejectItem 15 |
Project H | -Select-AcceptRejectItem 16 |
If Ziege can only invest a total of $13 million, what would be the dollar size of its capital budget? Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Round your answer to two decimal places.
$ million
Suppose Ziege can raise additional funds beyond the $13 million, but each new increment (or partial increment) of $5 million of new capital will cause the WACC to increase by 1%. Assuming that Ziege uses the same method of risk adjustment, which projects should it now accept?
Project A | -Select-AcceptRejectItem 18 |
Project B | -Select-AcceptRejectItem 19 |
Project C | -Select-AcceptRejectItem 20 |
Project D | -Select-AcceptRejectItem 21 |
Project E | -Select-AcceptRejectItem 22 |
Project F | -Select-AcceptRejectItem 23 |
Project G | -Select-AcceptRejectItem 24 |
Project H | -Select-AcceptRejectItem 25 |
What would be the dollar size of its capital budget? Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Round your answer to two decimal places.
$ million
a. For high risk projects add 2% to given Wacc i.e. 9.75% + 2% = 11.75%
For low risk projects subtract 2% to given Wacc i.e. 9.75% - 2% = 7.75%
For Average the same Wacc is taken i.e. 9.75%
Wacc is the weighted AVerage cost of capital. This is the weighted average cost that is expected to be incurred when a firm raises capital for a project .
For a project to be accepted, its expected rate of return should be higher that cost of capital.
Project | Required Investment (In Millions)($) |
Rate of Return | Risk | Cost of capital | Excess rate |
A | 4 | 11.25% | High | 11.75% | -0.50% |
B | 5 | 13.75% | High | 11.75% | 2.00% |
C | 3 | 9.25% | Low | 7.75% | 1.50% |
D | 2 | 9% | Average | 9.75% | -0.75% |
E | 6 | 12.25% | High | 11.75% | 0.50% |
F | 5 | 12.25% | Average | 9.75% | 2.50% |
G | 6 | 7% | Low | 7.75% | -0.75% |
H | 3 | 11% | Low | 7.75% | 3.25% |
Hence as per the above analysis projects "B,C,E,F,H" should be acepted by Zeige if it faces no capital constraints
b. If zeigi accepts all the projects whose rate of return exceeds the WACC, then the total investment / Project cost should be analysed as under :
Project | Required Investment (In Millions)($) |
Rate of Return | Risk | Cost of capital | Excess rate | Cumulative Capital (In Millions)($) |
H | 3 | 11% | Low | 7.75% | 3.25% | 3 |
F | 5 | 12.25% | Average | 9.75% | 2.50% | 8 |
B | 5 | 13.75% | High | 11.75% | 2.00% | 13 |
C | 3 | 9.25% | Low | 7.75% | 1.50% | 16 |
E | 6 | 12.25% | High | 11.75% | 0.50% | 22 |
A | 4 | 11.25% | High | 11.75% | -0.50% | 0 |
G | 6 | 7% | Low | 7.75% | -0.75% | 0 |
D | 2 | 9% | Average | 9.75% | -0.75% | 0 |
From the above analysis , it can be seen that Projects "H, F, B" can only be selected if it has only $13 Million.
c. To solve this problem consider the computation in part b above.
It is now said that zeigi can raise additional funds beyond $13 Million but with the expense of an additional 1% increase iun Wacc for every 5% Million increase in Cost.
After analysisng the chart in point b it can be seen that project E will now be rejected since the excess rate is only 0.5%. If WACC increase by 1% then the rate of return of Project E will be less than the wacc and will then be rejected . Thus the answer for the question of acceptance of project is now to chose projects "H, F, B, C" and the dollar size will be $16 Million i.e. Required Investment of $3 Million ,$5 Million ,$5 million and $3 million of projects H, F, B & C respectively.