In: Finance
Ziege Systems is considering the following independent projects for the coming year:
Project |
Required Investment |
Rate of Return |
Risk |
A | $4 million | 11.50% | High |
B | 5 million | 14.00 | High |
C | 3 million | 9.50 | Low |
D | 2 million | 9.25 | Average |
E | 6 million | 12.50 | High |
F | 5 million | 12.50 | Average |
G | 6 million | 7.25 | Low |
H | 3 million | 11.50 | Low |
Ziege's WACC is 10.00%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2% for low-risk projects.
Which projects should Ziege accept if it faces no capital constraints?
Project A | Reject 1 |
Project B | Accept 2 |
Project C | Accept 3 |
Project D | Reject 4 |
Project E | Accept 5 |
Project F | Accept 6 |
Project G | Reject 7 |
Project H | Accept 8 |
If Ziege can only invest a total of $13 million, which projects should it accept?
Project A | Reject 9 |
Project B | Accept 10 |
Project C | Reject 11 |
Project D | Reject 12 |
Project E | Reject 13 |
Project F | Accept 14 |
Project G | Reject 15 |
Project H | Accept 16 |
If Ziege can only invest a total of $13 million, what would be the dollar size of its capital budget? Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Round your answer to two decimal places.
$ million
Suppose Ziege can raise additional funds beyond the $13 million, but each new increment (or partial increment) of $5 million of new capital will cause the WACC to increase by 1%. Assuming that Ziege uses the same method of risk adjustment, which projects should it now accept?
Project A | Reject 18 |
Project B | Accept 19 |
Project C | Accept 20 |
Project D | Reject 21 |
Project E | Accept 22 |
Project F | Reject 23 |
Project G | Accept 24 |
Project H | -Select-AcceptRejectItem 25 |
What would be the dollar size of its capital budget? Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Round your answer to two decimal places. $ million
a) Evaluation of Projects-
Project | Required Investment | Risk | WACC | Rate of Return | Rate of Return-WACC | Decision |
A | $4 Million | High | 12% | 11.50% | -0.50% | Reject |
B | $5 Million | High | 12% | 14% | 2% | Accept |
C | $3 Million | Low | 8% | 9.50% | 1.50% | Accept |
D | $2 Million | Average | 10% | 9.25% | -0.75% | Reject |
E | $6 Million | High | 12% | 12.50% | 0.50% | Accept |
F | $5 Million | Average | 10% | 12.50% | 2.50% | Accept |
G | $6 Million | Low | 8% | 7.25% | -0.75% | Reject |
H | $3 Million | Low | 8% | 11.50% | 3.50% | Accept |
b) Evaluation of projects and dollar size of capital budget-
Project | Rate of Return-WACC | Rank | Investment | Decision |
B | 2% | III | $5 Million | Accept |
C | 1.50% | IV | $3 Million | Reject |
E | 0.50% | V | $6 Million | Reject |
F | 2.50% | II | $5 Million | Accept |
H | 3.50% | I | $3 Million | Accept |
Capital Budget
Project H- $3 Million
Project F- $5 Million
Project B- $5 Million
Total- $13 Million
c) Evaluation of incremental raising of funds-
Project | Rate of Return-WACC(A) | Required Invesment | Incremental WACC(B) | Column A- ColumnB | Decision |
C | 1.50% | $3 Million | 1% | 0.50% | Accept |
E | 0.50% | $6 Million | 2% | -1.50% | Reject |
Capital Budget will be-
$13 Million+$3 Million
= $16 Million