Question

In: Finance

Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...

Ziege Systems is considering the following independent projects for the coming year:


Project
Required
Investment
Rate of
Return

Risk
A $4 million 11.50% High
B 5 million 14.00 High
C 3 million 9.50 Low
D 2 million 9.25 Average
E 6 million 12.50 High
F 5 million 12.50 Average
G 6 million 7.25 Low
H 3 million 11.50 Low

Ziege's WACC is 10.00%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2% for low-risk projects.

  1. Which projects should Ziege accept if it faces no capital constraints?

    Project A Reject 1
    Project B Accept 2
    Project C Accept 3
    Project D Reject 4
    Project E Accept 5
    Project F Accept 6
    Project G Reject 7
    Project H Accept 8
  2. If Ziege can only invest a total of $13 million, which projects should it accept?

    Project A Reject 9
    Project B Accept 10
    Project C Reject 11
    Project D Reject 12
    Project E Reject 13
    Project F Accept 14
    Project G Reject 15
    Project H Accept 16

    If Ziege can only invest a total of $13 million, what would be the dollar size of its capital budget? Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Round your answer to two decimal places.

    $    million

  3. Suppose Ziege can raise additional funds beyond the $13 million, but each new increment (or partial increment) of $5 million of new capital will cause the WACC to increase by 1%. Assuming that Ziege uses the same method of risk adjustment, which projects should it now accept?

    Project A Reject 18
    Project B Accept 19
    Project C Accept 20
    Project D Reject 21
    Project E Accept 22
    Project F Reject 23
    Project G Accept 24
    Project H -Select-AcceptRejectItem 25

    What would be the dollar size of its capital budget? Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Round your answer to two decimal places. $    million

Solutions

Expert Solution

a) Evaluation of Projects-

Project Required Investment Risk WACC Rate of Return Rate of Return-WACC Decision
A $4 Million High 12% 11.50% -0.50% Reject
B $5 Million High 12% 14% 2% Accept
C $3 Million Low 8% 9.50% 1.50% Accept
D $2 Million Average 10% 9.25% -0.75% Reject
E $6 Million High 12% 12.50% 0.50% Accept
F $5 Million Average 10% 12.50% 2.50% Accept
G $6 Million Low 8% 7.25% -0.75% Reject
H $3 Million Low 8% 11.50% 3.50% Accept

b) Evaluation of projects and dollar size of capital budget-

Project Rate of Return-WACC Rank Investment Decision
B 2% III $5 Million Accept
C 1.50% IV $3 Million Reject
E 0.50% V $6 Million Reject
F 2.50% II $5 Million Accept
H 3.50% I $3 Million Accept

Capital Budget

Project H- $3 Million

Project F- $5 Million

Project B- $5 Million

Total- $13 Million

c) Evaluation of incremental raising of funds-

Project Rate of Return-WACC(A) Required Invesment Incremental WACC(B) Column A- ColumnB Decision
C 1.50% $3 Million 1% 0.50% Accept
E 0.50% $6 Million 2% -1.50% Reject

Capital Budget will be-

$13 Million+$3 Million

= $16 Million


Related Solutions

Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 13.25% High B 5 million 10.75 High C 3 million 8.75 Low D 2 million 8.00 Average E 6 million 11.75 High F 5 million 11.75 Average G 6 million 6.00 Low H 3 million 10.50 Low Ziege's WACC is 9.25%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 14.75% High B 5 million 12.25 High C 3 million 10.25 Low D 2 million 9.50 Average E 6 million 13.25 High F 5 million 13.25 Average G 6 million 7.50 Low H 3 million 12.75 Low Ziege's WACC is 10.75%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 12.50% High B 5 million 15.00 High C 3 million 10.50 Low D 2 million 9.50 Average E 6 million 13.50 High F 5 million 13.50 Average G 6 million 7.50 Low H 3 million 12.00 Low Ziege's WACC is 11.00%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 11.25% High B 5 million 13.75 High C 3 million 9.25 Low D 2 million 9 Average E 6 million 12.25 High F 5 million 12.25 Average G 6 million 7 Low H 3 million 11 Low Ziege's WACC is 9.75%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 12.25% High B 5 million 14.75 High C 3 million 10.25 Low D 2 million 9.75 Average E 6 million 13.25 High F 5 million 13.25 Average G 6 million 7.75 Low H 3 million 12.00 Low Ziege's WACC is 10.75%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 14.25% High B 5 million 11.75 High C 3 million 9.75 Low D 2 million 9.75 Average E 6 million 12.75 High F 5 million 12.75 Average G 6 million 7.75 Low H 3 million 11.25 Low Ziege's WACC is 10.25%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 14.25% High B 5 million 11.75 High C 3 million 9.75 Low D 2 million 8.75 Average E 6 million 12.75 High F 5 million 12.75 Average G 6 million 6.75 Low H 3 million 12.25 Low Ziege's WACC is 10.25%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
eBook Ziege Systems is considering the following independent projects for the coming year: Project Required Investment...
eBook Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 10.75% High B 5 million 13.25 High C 3 million 8.75 Low D 2 million 7.75 Average E 6 million 11.75 High F 5 million 11.75 Average G 6 million 5.75 Low H 3 million 10.50 Low Ziege's WACC is 9.25%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting...
You are considering two independent projects. The required rate of return is 13.75 percent for Project...
You are considering two independent projects. The required rate of return is 13.75 percent for Project A and 14.25 percent for Project B. Project A has an initial cost of $51,400 and cash inflows of $21,400, $24,900, and $22,200 for Years 1 to 3, respectively. Project B has an initial cost of $38,300 and cash inflows of $23,000 a year for 2 years. Which project(s), if either, should you accept? Accept both A and B Reject both A and B...
Required information For four independent projects, the investment limit is $350, and the following project selection...
Required information For four independent projects, the investment limit is $350, and the following project selection restriction applies: project 2 can be selected only if project 3 is selected. Project Initial Investment, $ 1 250 2 150 3 75 4 235 1) Determine all the acceptable mutually exclusive bundles from the following. 2) Determine all the nonacceptable mutually exclusive bundles from the following.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT