Question

In: Finance

Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...

Ziege Systems is considering the following independent projects for the coming year:


Project
Required
Investment
Rate of
Return

Risk
A $4 million 12.25% High
B 5 million 14.75 High
C 3 million 10.25 Low
D 2 million 9.75 Average
E 6 million 13.25 High
F 5 million 13.25 Average
G 6 million 7.75 Low
H 3 million 12.00 Low

Ziege's WACC is 10.75%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2% for low-risk projects.

  1. Which projects should Ziege accept if it faces no capital constraints?

    Project A -Select-AcceptRejectItem 1
    Project B -Select-AcceptRejectItem 2
    Project C -Select-AcceptRejectItem 3
    Project D -Select-AcceptRejectItem 4
    Project E -Select-AcceptRejectItem 5
    Project F -Select-AcceptRejectItem 6
    Project G -Select-AcceptRejectItem 7
    Project H -Select-AcceptRejectItem 8
  2. If Ziege can only invest a total of $13 million, which projects should it accept?

    Project A -Select-AcceptRejectItem 9
    Project B -Select-AcceptRejectItem 10
    Project C -Select-AcceptRejectItem 11
    Project D -Select-AcceptRejectItem 12
    Project E -Select-AcceptRejectItem 13
    Project F -Select-AcceptRejectItem 14
    Project G -Select-AcceptRejectItem 15
    Project H -Select-AcceptRejectItem 16

    If Ziege can only invest a total of $13 million, what would be the dollar size of its capital budget? Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Round your answer to two decimal places.

    $    million

  3. Suppose Ziege can raise additional funds beyond the $13 million, but each new increment (or partial increment) of $5 million of new capital will cause the WACC to increase by 1%. Assuming that Ziege uses the same method of risk adjustment, which projects should it now accept?

    Project A -Select-AcceptRejectItem 18
    Project B -Select-AcceptRejectItem 19
    Project C -Select-AcceptRejectItem 20
    Project D -Select-AcceptRejectItem 21
    Project E -Select-AcceptRejectItem 22
    Project F -Select-AcceptRejectItem 23
    Project G -Select-AcceptRejectItem 24
    Project H -Select-AcceptRejectItem 25

    What would be the dollar size of its capital budget? Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Round your answer to two decimal places.

    $    million

Solutions

Expert Solution

a) For high risk projects, WACC = 10.75% + 2% = 12.75%

  For average risk projects, WACC = 10.75%

For low risk projects, WACC = 10.75% - 2% = 8.75%

WACC (Weighted average cost of capital) is the weighted average cost that is expected to be incurred when a firm raises its capital for a project. For a project to be selected, its expected rate of return should be higher than the cost of capital (adjusted with risk).

For high risk projects

Project B and E should be accepted, since expected rate of return is higher than WACC.

Project A should be rejected, since expected rate of return is lower than WACC.

For average risk projects

Project F should be accepted, since expected rate of return is higher than WACC.

Project D should be rejected, since expected rate of return is lower than WACC.

For low risk projects

Project C and H should be accepted, since expected rate of return is higher than WACC.

Project G should be rejected, since expected rate of return is lower than WACC.

b) As Ziege can invest a total of $ 13 million, all the projects cannot be selected. Therefore projects which have the highest excess over the relative WACC should be given priority.

Projects

Cost ($)

In millions

Rate of Return

(%)

Relative WACC

(%)

Excess

(Return – WACC)

B

5

14.75

12.75

2

C

3

10.25

8.75

1.5

E

6

13.25

12.75

0.5

F

5

13.25

10.75

2.5

H

3

12

8.75

3.25

The projects with high the excess, from highest to lowest are H, F and B.

Projects

Costs ($) in millions

H

3

F

5

B

5

TOTAL

13

Thus we can accept projects H, F and B with a total of $ 13 million budget.

c) Now it’s been said, Ziege can raise additional fund even beyond $13 million, but with an expense of additional 1% in WACC for every additional $5 million ( or partial increment) of new capital.

Looking at excess over WACC computation in point (b) above, we can see that since the excess (Return – WACC) in project E is of only 0.5% and if additional cost of 1% is added in WACC then the rate of return of Project E will be less than the WACC. Therefore project E is also rejected in this case.

Thus, we are left with projects H, F, B and C.

Projects

Costs ($) in millions

H

3

F

5

B

5

C

3

TOTAL

16

Now, the projects accepted are H, F, B and C . With a total dollar size of $16 million capital budget.


Related Solutions

Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 13.25% High B 5 million 10.75 High C 3 million 8.75 Low D 2 million 8.00 Average E 6 million 11.75 High F 5 million 11.75 Average G 6 million 6.00 Low H 3 million 10.50 Low Ziege's WACC is 9.25%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 14.75% High B 5 million 12.25 High C 3 million 10.25 Low D 2 million 9.50 Average E 6 million 13.25 High F 5 million 13.25 Average G 6 million 7.50 Low H 3 million 12.75 Low Ziege's WACC is 10.75%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 12.50% High B 5 million 15.00 High C 3 million 10.50 Low D 2 million 9.50 Average E 6 million 13.50 High F 5 million 13.50 Average G 6 million 7.50 Low H 3 million 12.00 Low Ziege's WACC is 11.00%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 11.25% High B 5 million 13.75 High C 3 million 9.25 Low D 2 million 9 Average E 6 million 12.25 High F 5 million 12.25 Average G 6 million 7 Low H 3 million 11 Low Ziege's WACC is 9.75%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 11.50% High B 5 million 14.00 High C 3 million 9.50 Low D 2 million 9.25 Average E 6 million 12.50 High F 5 million 12.50 Average G 6 million 7.25 Low H 3 million 11.50 Low Ziege's WACC is 10.00%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 14.25% High B 5 million 11.75 High C 3 million 9.75 Low D 2 million 9.75 Average E 6 million 12.75 High F 5 million 12.75 Average G 6 million 7.75 Low H 3 million 11.25 Low Ziege's WACC is 10.25%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 14.25% High B 5 million 11.75 High C 3 million 9.75 Low D 2 million 8.75 Average E 6 million 12.75 High F 5 million 12.75 Average G 6 million 6.75 Low H 3 million 12.25 Low Ziege's WACC is 10.25%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 14.75% High B 5 million 12.25 High C 3 million 10.25 Low D 2 million 9.5 Average E 6 million 13.25 High F 5 million 13.25 Average G 6 million 7.5 Low H 3 million 11.75 Low Ziege's WACC is 10.75%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
eBook Ziege Systems is considering the following independent projects for the coming year: Project Required Investment...
eBook Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 10.75% High B 5 million 13.25 High C 3 million 8.75 Low D 2 million 7.75 Average E 6 million 11.75 High F 5 million 11.75 Average G 6 million 5.75 Low H 3 million 10.50 Low Ziege's WACC is 9.25%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting...
You are considering two independent projects. The required rate of return is 13.75 percent for Project...
You are considering two independent projects. The required rate of return is 13.75 percent for Project A and 14.25 percent for Project B. Project A has an initial cost of $51,400 and cash inflows of $21,400, $24,900, and $22,200 for Years 1 to 3, respectively. Project B has an initial cost of $38,300 and cash inflows of $23,000 a year for 2 years. Which project(s), if either, should you accept? Accept both A and B Reject both A and B...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT