In: Finance
Ziege Systems is considering the following independent projects for the coming year:
Project  | 
Required Investment  | 
Rate of Return  | 
Risk  | 
| A | $4 million | 12.25% | High | 
| B | 5 million | 14.75 | High | 
| C | 3 million | 10.25 | Low | 
| D | 2 million | 9.75 | Average | 
| E | 6 million | 13.25 | High | 
| F | 5 million | 13.25 | Average | 
| G | 6 million | 7.75 | Low | 
| H | 3 million | 12.00 | Low | 
Ziege's WACC is 10.75%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2% for low-risk projects.
Which projects should Ziege accept if it faces no capital constraints?
| Project A | -Select-AcceptRejectItem 1 | 
| Project B | -Select-AcceptRejectItem 2 | 
| Project C | -Select-AcceptRejectItem 3 | 
| Project D | -Select-AcceptRejectItem 4 | 
| Project E | -Select-AcceptRejectItem 5 | 
| Project F | -Select-AcceptRejectItem 6 | 
| Project G | -Select-AcceptRejectItem 7 | 
| Project H | -Select-AcceptRejectItem 8 | 
If Ziege can only invest a total of $13 million, which projects should it accept?
| Project A | -Select-AcceptRejectItem 9 | 
| Project B | -Select-AcceptRejectItem 10 | 
| Project C | -Select-AcceptRejectItem 11 | 
| Project D | -Select-AcceptRejectItem 12 | 
| Project E | -Select-AcceptRejectItem 13 | 
| Project F | -Select-AcceptRejectItem 14 | 
| Project G | -Select-AcceptRejectItem 15 | 
| Project H | -Select-AcceptRejectItem 16 | 
If Ziege can only invest a total of $13 million, what would be the dollar size of its capital budget? Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Round your answer to two decimal places.
$ million
Suppose Ziege can raise additional funds beyond the $13 million, but each new increment (or partial increment) of $5 million of new capital will cause the WACC to increase by 1%. Assuming that Ziege uses the same method of risk adjustment, which projects should it now accept?
| Project A | -Select-AcceptRejectItem 18 | 
| Project B | -Select-AcceptRejectItem 19 | 
| Project C | -Select-AcceptRejectItem 20 | 
| Project D | -Select-AcceptRejectItem 21 | 
| Project E | -Select-AcceptRejectItem 22 | 
| Project F | -Select-AcceptRejectItem 23 | 
| Project G | -Select-AcceptRejectItem 24 | 
| Project H | -Select-AcceptRejectItem 25 | 
What would be the dollar size of its capital budget? Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Round your answer to two decimal places.
$ million
a) For high risk projects, WACC = 10.75% + 2% = 12.75%
For average risk projects, WACC = 10.75%
For low risk projects, WACC = 10.75% - 2% = 8.75%
WACC (Weighted average cost of capital) is the weighted average cost that is expected to be incurred when a firm raises its capital for a project. For a project to be selected, its expected rate of return should be higher than the cost of capital (adjusted with risk).
For high risk projects
Project B and E should be accepted, since expected rate of return is higher than WACC.
Project A should be rejected, since expected rate of return is lower than WACC.
For average risk projects
Project F should be accepted, since expected rate of return is higher than WACC.
Project D should be rejected, since expected rate of return is lower than WACC.
For low risk projects
Project C and H should be accepted, since expected rate of return is higher than WACC.
Project G should be rejected, since expected rate of return is lower than WACC.
b) As Ziege can invest a total of $ 13 million, all the projects cannot be selected. Therefore projects which have the highest excess over the relative WACC should be given priority.
| 
 Projects  | 
 Cost ($) In millions  | 
 Rate of Return (%)  | 
 Relative WACC (%)  | 
 Excess (Return – WACC)  | 
| 
 B  | 
 5  | 
 14.75  | 
 12.75  | 
 2  | 
| 
 C  | 
 3  | 
 10.25  | 
 8.75  | 
 1.5  | 
| 
 E  | 
 6  | 
 13.25  | 
 12.75  | 
 0.5  | 
| 
 F  | 
 5  | 
 13.25  | 
 10.75  | 
 2.5  | 
| 
 H  | 
 3  | 
 12  | 
 8.75  | 
 3.25  | 
The projects with high the excess, from highest to lowest are H, F and B.
| 
 Projects  | 
 Costs ($) in millions  | 
| 
 H  | 
 3  | 
| 
 F  | 
 5  | 
| 
 B  | 
 5  | 
| 
 TOTAL  | 
 13  | 
Thus we can accept projects H, F and B with a total of $ 13 million budget.
c) Now it’s been said, Ziege can raise additional fund even beyond $13 million, but with an expense of additional 1% in WACC for every additional $5 million ( or partial increment) of new capital.
Looking at excess over WACC computation in point (b) above, we can see that since the excess (Return – WACC) in project E is of only 0.5% and if additional cost of 1% is added in WACC then the rate of return of Project E will be less than the WACC. Therefore project E is also rejected in this case.
Thus, we are left with projects H, F, B and C.
| 
 Projects  | 
 Costs ($) in millions  | 
| 
 H  | 
 3  | 
| 
 F  | 
 5  | 
| 
 B  | 
 5  | 
| 
 C  | 
 3  | 
| 
 TOTAL  | 
 16  | 
Now, the projects accepted are H, F, B and C . With a total dollar size of $16 million capital budget.