In: Finance
Ziege Systems is considering the following independent projects for the coming year:
Project |
Required Investment |
Rate of Return |
Risk |
| A | $4 million | 12.25% | High |
| B | 5 million | 14.75 | High |
| C | 3 million | 10.25 | Low |
| D | 2 million | 9.75 | Average |
| E | 6 million | 13.25 | High |
| F | 5 million | 13.25 | Average |
| G | 6 million | 7.75 | Low |
| H | 3 million | 12.00 | Low |
Ziege's WACC is 10.75%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2% for low-risk projects.
Which projects should Ziege accept if it faces no capital constraints?
| Project A | -Select-AcceptRejectItem 1 |
| Project B | -Select-AcceptRejectItem 2 |
| Project C | -Select-AcceptRejectItem 3 |
| Project D | -Select-AcceptRejectItem 4 |
| Project E | -Select-AcceptRejectItem 5 |
| Project F | -Select-AcceptRejectItem 6 |
| Project G | -Select-AcceptRejectItem 7 |
| Project H | -Select-AcceptRejectItem 8 |
If Ziege can only invest a total of $13 million, which projects should it accept?
| Project A | -Select-AcceptRejectItem 9 |
| Project B | -Select-AcceptRejectItem 10 |
| Project C | -Select-AcceptRejectItem 11 |
| Project D | -Select-AcceptRejectItem 12 |
| Project E | -Select-AcceptRejectItem 13 |
| Project F | -Select-AcceptRejectItem 14 |
| Project G | -Select-AcceptRejectItem 15 |
| Project H | -Select-AcceptRejectItem 16 |
If Ziege can only invest a total of $13 million, what would be the dollar size of its capital budget? Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Round your answer to two decimal places.
$ million
Suppose Ziege can raise additional funds beyond the $13 million, but each new increment (or partial increment) of $5 million of new capital will cause the WACC to increase by 1%. Assuming that Ziege uses the same method of risk adjustment, which projects should it now accept?
| Project A | -Select-AcceptRejectItem 18 |
| Project B | -Select-AcceptRejectItem 19 |
| Project C | -Select-AcceptRejectItem 20 |
| Project D | -Select-AcceptRejectItem 21 |
| Project E | -Select-AcceptRejectItem 22 |
| Project F | -Select-AcceptRejectItem 23 |
| Project G | -Select-AcceptRejectItem 24 |
| Project H | -Select-AcceptRejectItem 25 |
What would be the dollar size of its capital budget? Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Round your answer to two decimal places.
$ million
a) For high risk projects, WACC = 10.75% + 2% = 12.75%
For average risk projects, WACC = 10.75%
For low risk projects, WACC = 10.75% - 2% = 8.75%
WACC (Weighted average cost of capital) is the weighted average cost that is expected to be incurred when a firm raises its capital for a project. For a project to be selected, its expected rate of return should be higher than the cost of capital (adjusted with risk).
For high risk projects
Project B and E should be accepted, since expected rate of return is higher than WACC.
Project A should be rejected, since expected rate of return is lower than WACC.
For average risk projects
Project F should be accepted, since expected rate of return is higher than WACC.
Project D should be rejected, since expected rate of return is lower than WACC.
For low risk projects
Project C and H should be accepted, since expected rate of return is higher than WACC.
Project G should be rejected, since expected rate of return is lower than WACC.
b) As Ziege can invest a total of $ 13 million, all the projects cannot be selected. Therefore projects which have the highest excess over the relative WACC should be given priority.
|
Projects |
Cost ($) In millions |
Rate of Return (%) |
Relative WACC (%) |
Excess (Return – WACC) |
|
B |
5 |
14.75 |
12.75 |
2 |
|
C |
3 |
10.25 |
8.75 |
1.5 |
|
E |
6 |
13.25 |
12.75 |
0.5 |
|
F |
5 |
13.25 |
10.75 |
2.5 |
|
H |
3 |
12 |
8.75 |
3.25 |
The projects with high the excess, from highest to lowest are H, F and B.
|
Projects |
Costs ($) in millions |
|
H |
3 |
|
F |
5 |
|
B |
5 |
|
TOTAL |
13 |
Thus we can accept projects H, F and B with a total of $ 13 million budget.
c) Now it’s been said, Ziege can raise additional fund even beyond $13 million, but with an expense of additional 1% in WACC for every additional $5 million ( or partial increment) of new capital.
Looking at excess over WACC computation in point (b) above, we can see that since the excess (Return – WACC) in project E is of only 0.5% and if additional cost of 1% is added in WACC then the rate of return of Project E will be less than the WACC. Therefore project E is also rejected in this case.
Thus, we are left with projects H, F, B and C.
|
Projects |
Costs ($) in millions |
|
H |
3 |
|
F |
5 |
|
B |
5 |
|
C |
3 |
|
TOTAL |
16 |
Now, the projects accepted are H, F, B and C . With a total dollar size of $16 million capital budget.