Question

In: Finance

The net cash flows for project X, Y and Z are shown below. Each project has...

The net cash flows for project X, Y and Z are shown below. Each project has an initial cost of $100, and the company uses a 10% cost of capital (i.e., the discount rate = 10%) for each project. Which project is most sensitive to the change of the cost of capital?

End of Year

Net Cash Flow From Project

X

Y

Z

1

$110

0

0

2

0

$121

0

3

0

0

$133.1

  1. X
  2. Y
  3. Z
  4. All the three are equally sensitive
  5. Need more information to make the judgment

Solutions

Expert Solution

Correct answer: c. Z

Project Z is most sensitive to change in cost of capital because it has higher duration value or in other words it takes longer time to recover its initial cost.

We can check this by changing cost of capital to 9%.

Please refer to below spreadsheet for calculation and answer. Cell reference also provided.

Cell reference -

In above calculation, we can see change in interest rate ( i.e -1%) has largest impact on NPV of Project-Z.


Related Solutions

8. The (net) cash flows of project C and D are shown below: Net Cash Flow...
8. The (net) cash flows of project C and D are shown below: Net Cash Flow ($) Year Project C Project D 0 -2,000 -1,000 1 3,000 650 2 125 1,500 a. Find the crossover rates. (1.5 point) b. The cost of capital is 12 percent. If C and D are mutually exclusive, which project should be accepted? Why? (0.5 point)
Solora Inc. is considering Projects X and Y, whose cash flows are shown below. These projects...
Solora Inc. is considering Projects X and Y, whose cash flows are shown below. These projects are equally risky. Firm;s WACC=10%. Year 0 1 2 3 4 CF-X −$1,100 $375 $375 $375 $375 CF-Y −$2,200 $725 $725 $725 $725 a) Calculate Payback Period for these two projects. Which one do you choose if the Threshold is less than 3 years? b) Calculate NPV for these two projects. Are they acceptable? Why? Which one do you choose if they are independent?...
For each of the formulas below, state whether it is true or false. a) pX,Y,Z(x,y,z)=pY(y)pZ∣Y(z∣y)pX∣Y,Z(x∣y,z)   ...
For each of the formulas below, state whether it is true or false. a) pX,Y,Z(x,y,z)=pY(y)pZ∣Y(z∣y)pX∣Y,Z(x∣y,z)       Select an option         True         False    b) pX,Y∣Z(x,y∣z)=pX(x)pY∣Z(y∣z)       Select an option         True         False    c) pX,Y∣Z(x,y∣z)=pX∣Z(x∣z)pY∣X,Z(y∣x,z)       Select an option         True         False    d) ∑xpX,Y∣Z(x,y∣z)=1       Select an option         True         False    e) ∑x∑ypX,Y∣Z(x,y∣z)=1       Select an option         True   ...
CoveAuklaOoglu, Inc. is considering a project which has net cash flows (the same as free cash flows) given below:
   CoveAuklaOoglu, Inc. is considering a project which has net cash flows (the same as free cash flows) given below:Year                        CF ($)0                             -1,000 (Initial Outlay)1                             5002                             4003                             3004                             100Given that the company’s WACC is 10%, what is the company’s NPV? (Points : 3.4)        $78.82       $109.45       $49.18       $54.06  Garrod Dickens wants to calculate the IRR for the above project (use information in Question 22) for CoveAuklaOoglu, Inc. His answer would be: (Points : 3.4)        11.8%       14.5%       12.45%       13.02%  Garrod Dickens also wants to...
A project has the following total (or net) cash flows.                ________________________________________             
A project has the following total (or net) cash flows.                ________________________________________                 Year         Total (or net) cash flow                ________________________________________ 1 $50,000 2 70,000 3 80,000 4 100,000 _______________________________________    The required rate of return on the project is 13 percent. The initial investment (or initial cost or initial outlay) of the project is $100,000. a) Find the (regular) payback period of the project. b) Compute the discounted payback period of the project. 6. A project has the following...
A four-year financial project has estimates of net cash flows shown in the following table: Year...
A four-year financial project has estimates of net cash flows shown in the following table: Year Net Cash Flow 1 $20,000 2 25,000 3 30,000 4 35,000 It will cost $65,000 to implement the project, all of which must be invested at the beginning of the project. After the fourth year, the project will have no residual value. Using the most likely estimates of cash flows, conduct a discounted cash flow calculation assuming a 20 percent hurdle rate with no...
QUESTION 42 A company has a proposed 2-year project with the cash flows shown below and...
QUESTION 42 A company has a proposed 2-year project with the cash flows shown below and would like to calculate the NPV of this project so that they can decide whether to pursue the project or not. The company has a target capital structure of 60% equity and 40% debt. The beta for this firms stock is 0.8, the risk-free rate is 4.8, and the expected market risk premium is 6%. The bonds for this company pay interest semiannually and...
A company has a proposed 2-year project with the cash flows shown below and would like...
A company has a proposed 2-year project with the cash flows shown below and would like to calculate the NPV of this project so that they can decide whether to pursue the project or not. The company has a target capital structure of 60% equity and 40% debt. The beta for this firms stock is 1.6, the risk-free rate is 4.5, and the expected market risk premium is 6%. The bonds for this company pay interest semiannually and have a...
42. A company has a proposed 2-year project with the cash flows shown below and would...
42. A company has a proposed 2-year project with the cash flows shown below and would like to calculate the NPV of this project so that they can decide whether to pursue the project or not. The company has a target capital structure of 60% equity and 40% debt. The beta for this firms stock is 1.4, the risk-free rate is 4.5, and the expected market risk premium is 6.4%. The bonds for this company pay interest semiannually and have...
A company has a proposed 2-year project with the cash flows shown below and would like...
A company has a proposed 2-year project with the cash flows shown below and would like to calculate the NPV of this project so that they can decide whether to pursue the project or not. The company has a target capital structure of 60% equity and 40% debt. The beta for this firms stock is 1.3, the risk-free rate is 4.6, and the expected market risk premium is 5.5%. The bonds for this company pay interest semiannually and have a...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT