Question

In: Finance

Solora Inc. is considering Projects X and Y, whose cash flows are shown below. These projects...

Solora Inc. is considering Projects X and Y, whose cash flows are shown below. These projects are equally risky. Firm;s WACC=10%.

Year

0

1

2

3

4

CF-X

−$1,100

$375

$375

$375

$375

CF-Y

−$2,200

$725

$725

$725

$725

a) Calculate Payback Period for these two projects. Which one do you choose if the Threshold is less than 3 years?

b) Calculate NPV for these two projects. Are they acceptable? Why? Which one do you choose if they are independent? What about if they are mutually exclusive?
c) Calculate IRR for these two projects. Are they acceptable? Why? Which one do you choose if they are independent? What about if they are mutually exclusive?
d) Do NPV & IRR reach to the same conclusion? If not, on what basis you choose any of these project and why?

Solutions

Expert Solution

a) Calculation of payback period:-

Here cash flows are same for all years for both project.

Payback period = Initial investment / Cash flows per year

Project X payback period = 1100 / 375 = 2.9333 years

project Y payback period = 2200 / 725 = 3.0345 years

Here Threshold limit is 3 years

So, Project X would be selected, it has payback period less than 3 years.

b) Calculation of NPV :-

here Cash flows are same, so we use present value of annuity factor to bring cash inflows into present value .

NPV of project = present value of cash inflows - initial investment

NPV of Project X = 375 * PVAF ( 10%,4 years) - 1100 = 375 * 3.1699 - 1100

NPV of Project X = $ 88.71

NPV of Project Y = 725 * PVAF ( 10%,4 years) - 2200 = 725 * 3.1699 - 2200

NPV of Project Y = $ 98.1775

NPV of project Y is higher than project X .So, Project Y is Selected.

C) Calculation of the IRR :-

IRR of Project X:-

AT, IRR , NPV = 0

375 / (1+i) + 375 / ( 1+i)2 +375 / ( 1+i)3 +375 / ( 1+i)4 - 1100 = 0

Let Us assume 1+i = x

375 / x + 375/x2 +375/x3 +375/x4 -1100 = 0

-1100x4 +375x3 +375x2 + 375x +375 =0

by using maths equation solver

x= 1.189765

1+i = 1.189765

i = 18.9765%

IRR of project X = 18.9765%

IRR of Project Y:-

AT, IRR , NPV = 0

725 / (1+i) + 725 / ( 1+i)2 +725 / ( 1+i)3 +725 / ( 1+i)4 - 2200 = 0

Let Us assume 1+i = x

725 / x + 725/x2 +725/x3 +725/x4 -2200 = 0

-2200x4 +725x3 +725x2 + 725x +725 =0

by using maths equation solver

x= 1.120448

1+i = 1.120448

i = 12.0448%

IRR of project Y = 12.0448%

IRR of project X is higher than project Y .So, Project X is Selected.

4) As per NPV project Y is selected.

As per IRR ,project X is selected.

Here PRoject Y is selected.

On basis of

NPV is absolute measure where IRR is relative measure.

NPV indicates profitability of company.


Related Solutions

Big Inc. is considering Two Projects X and Y, whose cash flows are shown below. These...
Big Inc. is considering Two Projects X and Y, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO believes the IRR is the best selection criterion, while the CFO advocates other methods. WACC: 8.00% Year 0 1 2 3 4 CFx −$1,100 $450 $500 $100 $100 CFy −$2,750 $625 $725 $800 $1,400 What are the MIRR’s? Discuss the importance of the MIRR method over IRR. If these projects are mutually exclusive...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher MIRR rather than the one with the higher NPV, how much value will be forgone? Note that under some conditions choosing projects on the basis of the MIRR will cause $0.00 value to be lost. WACC: 10.75% 0 1 2 3 4 CFS -$1,100...
Yonan Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Yonan Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the shorter payback, some value may be forgone. How much value will be lost in this instance? Note that under some conditions choosing projects on the basis of the shorter payback will not cause value to be lost WACC 11.75% 0 1 2 3 4 CFs...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher MIRR rather than the one with the higher NPV, how much value will be forgone? Note that under some conditions choosing projects on the basis of the MIRR will cause $0.00 value to be lost. WACC: 10.75% 0 1 2 3 4 CFS -$1,100...
Poston Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Poston Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive (must choose one or the other), equally risky, and not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? You must calculate the IRR and NPV for both projects select the project with the higher IRR and then calculate how much less the NPV is by selecting the project with...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher MIRR rather than the one with the higher NPV, how much value will be forgone? Note that under some conditions choosing projects on the basis of the MIRR will cause $0.00 value to be lost. WACC: 10.75% 0 1 2 3 4 CFS -$1,100...
Sexton Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Sexton Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under certain conditions choosing projects on the basis of the IRR will not cause any value to be lost because the one with the higher IRR will also have the higher NPV, so no value...
Sexton Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Sexton Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under certain conditions choosing projects on the basis of the IRR will not cause any value to be lost because the one with the higher IRR will also have the higher NPV, so no value...
Rumpelstiltskin Inc. is considering Projects K and Z, whose cash flows are shown below. These projects...
Rumpelstiltskin Inc. is considering Projects K and Z, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise Rumpelstiltskin Inc on the best procedure. If the wrong decision criterion is used, how much potential value would Rumpelstiltskin Inc. lose? r. 8.50% Year 0 1 2 3 4 CFS −$1,052 $375 $375 $375 $375 CFL...
Charlestown Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Charlestown Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. WACC: 9.00% 0 1 2 3 4 CFS -$2,000 $950 $950 $950 $950 CFL -$9,000 $3,200 $3,200 $3,200 $3,200 If the decision is made by choosing the project with the higher IRR, how much value will be forgone? What is the payback period for Project S? What is the discounted payback period for Project L? What...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT