Question

In: Finance

CoveAuklaOoglu, Inc. is considering a project which has net cash flows (the same as free cash flows) given below:

 

 CoveAuklaOoglu, Inc. is considering a project which has net cash flows (the same as free cash flows) given below:

Year                        CF ($)
0                             -1,000 (Initial Outlay)
1                             500
2                             400
3                             300
4                             100

Given that the company’s WACC is 10%, what is the company’s NPV? (Points : 3.4)

       $78.82
       $109.45
       $49.18
       $54.06

 Garrod Dickens wants to calculate the IRR for the above project (use information in Question 22) for CoveAuklaOoglu, Inc. His answer would be: (Points : 3.4)

       11.8%
       14.5%
       12.45%
       13.02%

 Garrod Dickens also wants to calculate the MIRR for the above project (use information in Question 22) for CoveAuklaOoglu, Inc. If the reinvestment rate is the WACC in Question 22, his answer would be: (Points : 3.4)

       13.28%
       15.07%
       10.69%
       12.11%

Solutions

Expert Solution

  1. NPV:

Year                cash flows       calculation of NPV

  1. 500                   =500*1/1.1 = 454.55
  2. 400                   =400*1/(1.1)^2 = 330.58
  3. 300                  =300*1/(1.1)^3 = 225.39
  4. 100                   =100*1/(1.1)^4 = 68.30

                    

            Total = 454.55+330.58+225.39+68.30 = 1078.82

            Less: initial outlay of 1000                      = 1000.00

             NPV                                                            = 78.82

  1. IRR:

We can calculate on trial & error basis:

14.5% is the correct answer. We take IRR for which cash flows almost equals zero. Calculations below:

Year              cash flows            calculation of IRR

  1. 500                       =500/1.145 = 436.7
  2. 400                        =500/(1.145)^2 = 305.1
  3. 300                         =500/(1.145)^3 = 199.9
  4. 100                        =500/(1.145)^4 = 58.18

TOTAL = 436.7 + 305.1 + 199.9 + 58.18 = 999.8

Less: initial outlay of 1000                        = 1000

                                                                          -0.18

3) MIRR:

                   YEAR     Cash flows     calculation:

  1. 500                 =(1+10%)(4-1) = 3.3*500 = 1650
  2. 400                  = (1+10%)(4 -2) = 2.2*400 = 880
  3. 300                  =(1+10%)(4-3) = 1.1*300 = 330
  4. 100                  =(1+10%)(4-4) = 0*100 = 0

              Total = 1650 +880+330 = 2860

=square root of 2860/1000 – 1

=1.691 – 13.28%


Related Solutions

Question 22.22. CoveAuklaOoglu, Inc. is considering a project which has net cash flows (the same as...
Question 22.22. CoveAuklaOoglu, Inc. is considering a project which has net cash flows (the same as free cash flows) given below: Year                        CF ($) 0                             -1,000 (Initial Outlay) 1                             500 2                             400 3                             300 4                             100 Given that the company’s WACC is 10%, what is the company’s NPV? (Points : 3.4)        $78.82        $109.45        $49.18        $54.06 Question 23.23. Garrod Dickens wants to calculate the IRR for the above project (use information in Question 22) for CoveAuklaOoglu, Inc....
Lee and Joe are both considering the same project with the cash flows shown below. Lee...
Lee and Joe are both considering the same project with the cash flows shown below. Lee is content earning 8 percent on the project but Joe wants to earn at least 12 percent. Who, if either, should accept this project? Year 0 1 2 3 Cash flow -$67,000 $18,000 $24,000 $42,000 A. neither Lee nor Joe B. both Lee and Joe C. Lee, but not Joe D. Lee, Joe can go either accept or reject as his NPV is zero...
Kinetics is considering a project that has a NINV of $874,000 and generates net cash flows...
Kinetics is considering a project that has a NINV of $874,000 and generates net cash flows of $170,000 per year for 12 years. What is the NPV of this project if Kinetics cost of capital is 14%?
The net cash flows for project X, Y and Z are shown below. Each project has...
The net cash flows for project X, Y and Z are shown below. Each project has an initial cost of $100, and the company uses a 10% cost of capital (i.e., the discount rate = 10%) for each project. Which project is most sensitive to the change of the cost of capital? End of Year Net Cash Flow From Project X Y Z 1 $110 0 0 2 0 $121 0 3 0 0 $133.1 X Y Z All the...
Citrus Company is considering a project that has estimated annual net cash flows of $21,300 for...
Citrus Company is considering a project that has estimated annual net cash flows of $21,300 for six years and is estimated to cost $100,000. Citrus’s cost of capital is 8 percent.     Determine the net present value of the project. (Future Value of $1, Present Value of $1, Future Value Annuity of $1, Present Value Annuity of $1.) (Use appropriate factor(s) from the tables provided. Negative amount should be indicated by a minus sign. Round your final answer to 2...
Citrus Company is considering a project that has estimated annual net cash flows of $21,300 for...
Citrus Company is considering a project that has estimated annual net cash flows of $21,300 for six years and is estimated to cost $100,000. Citrus’s cost of capital is 8 percent.     Determine the net present value of the project. (Future Value of $1, Present Value of $1, Future Value Annuity of $1, Present Value Annuity of $1.) (Use appropriate factor(s) from the tables provided. Negative amount should be indicated by a minus sign. Round your final answer to 2...
Citrus Company is considering a project that has estimated annual net cash flows of $41,535 for...
Citrus Company is considering a project that has estimated annual net cash flows of $41,535 for seven years and is estimated to cost $195,000. Citrus’s cost of capital is 12 percent.     Determine the net present value of the project. (Future Value of $1, Present Value of $1, Future Value Annuity of $1, Present Value Annuity of $1.) (Use appropriate factor(s) from the tables provided. Negative amount should be indicated by a minus sign. Round your final answer to 2...
8. The (net) cash flows of project C and D are shown below: Net Cash Flow...
8. The (net) cash flows of project C and D are shown below: Net Cash Flow ($) Year Project C Project D 0 -2,000 -1,000 1 3,000 650 2 125 1,500 a. Find the crossover rates. (1.5 point) b. The cost of capital is 12 percent. If C and D are mutually exclusive, which project should be accepted? Why? (0.5 point)
A project has the following total (or net) cash flows.                ________________________________________             
A project has the following total (or net) cash flows.                ________________________________________                 Year         Total (or net) cash flow                ________________________________________ 1 $50,000 2 70,000 3 80,000 4 100,000 _______________________________________    The required rate of return on the project is 13 percent. The initial investment (or initial cost or initial outlay) of the project is $100,000. a) Find the (regular) payback period of the project. b) Compute the discounted payback period of the project. 6. A project has the following...
Look at the cash flows for projects F and G given below. Cash Flows($) Project C0...
Look at the cash flows for projects F and G given below. Cash Flows($) Project C0 C1 C2 C3 C4 C5 C6 C7 C8 IRR (%) NPV at 10% F (10,000 ) 6,000 6,000 6,000 0 0 0 0 0 36.3 4,921 G (10,000 ) 3,000 3,000 3,000 3,000 3,000 3,000 3,000 3,000 25.0 6,005 The cost of capital was assumed to be 10%. Assume that the forecasted cash flows for projects of this type are overstated by 8% on...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT