Question

In: Finance

Consider the following projects: Cash Flows ($) Project C0 C1 D –11,500 23,000 E –21,500 37,625...

Consider the following projects: Cash Flows ($) Project C0 C1 D –11,500 23,000 E –21,500 37,625 Assume that the projects are mutually exclusive and that the opportunity cost of capital is 10%. a. Calculate the profitability index for each project. Project Profitability Index D E b-1. Calculate the profitability-index using the incremental cash flows. (D Profitability-index b-2. Which project should you choose? Project D Project E

Solutions

Expert Solution

CACULATION OF PRESENT VALUE OF THE PROJECT 1 & PROFITABILITY INDEX OF PROJECT D
Period Particulars Cash Flow PVF of $1 @ 10 % Present Value
0 Outflow $         -11,500.00 $                     1.0000 $             -11,500.00
1 Inflow $          23,000.00 $                     0.9091 $               20,909.09
Total $                 9,409.09
CACULATION OF PROFITABILITY INDEX OF INVESTMENT
Profitability Index = 1 + Net present Value / Initial investment
Profitability Index =          1 + $             9,409.09 "/" By $               11,500.00
Profitability Index =          1 +                         0.82
Profitability Index =                                   1.82
CACULATION OF PRESENT VALUE OF THE PROJECT 1 & PROFITABILITY INDEX OF PROJECT E
Period Particulars Cash Flow PVF of $1 @ 10 % Present Value
0 Outflow $         -21,500.00 $                     1.0000 $             -21,500.00
1 Inflow $          37,625.00 $                     0.9091 $               34,204.55
Total $               12,704.55
CACULATION OF PROFITABILITY INDEX OF INVESTMENT
Profitability Index = 1 + Net present Value / Initial investment
Profitability Index =          1 + $          12,704.55 "/" By $               21,500.00
Profitability Index =          1 +                         0.59
Profitability Index =                                   1.59
Project D Project E
Profitability Index                         1.82                              1.59
On the basis of Profitability index we can select the Project D because the PI of this project is High

Related Solutions

Consider the following projects: Cash Flows ($) Project C0 C1 D –10,300 20,600 E –20,300 35,525...
Consider the following projects: Cash Flows ($) Project C0 C1 D –10,300 20,600 E –20,300 35,525 Assume that the projects are mutually exclusive and that the opportunity cost of capital is 9%. a. Calculate the profitability index for each project. (Do not round intermediate calculations. Round your answers to 2 decimal places.) Consider the following projects: Cash Flows ($) Project C0 C1 D –10,300 20,600 E –20,300 35,525 Assume that the projects are mutually exclusive and that the opportunity cost...
Consider the following two mutually exclusive projects withtheir expected Cash Flows ($)Project C0 C1...
Consider the following two mutually exclusive projects with their expected Cash Flows ($)Project C0 C1   C2 C3A –$100 +$60 +$60 +$60B –$100 ------ ------ +$208.35What is the cross-over rate for these two projects?a. unknown, because the discount rate is unkownb. 28%c. 36%d. 32%e. 15%
Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A...
Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A -$100 +$60 +$60 +$60 B -$100 ---- ---- +$208.35 Calculate the NPV of each project for a discount rate of 14%. What is approximately the IRR for each project individually? Use the IRR cross-over method to determine which of the projects you should accept (describe the correct decision rule describing when you pick A versus B based on what discount rate).
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,000...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,000 2,000 0 0 0 0 B −4,000 2,000 2,000 5,000 2,000 2,000 C −5,000 2,000 1,300 0 2,000 2,000 a. If the opportunity cost of capital is 12%, which project(s) have a positive NPV? Positive NPV project(s) Project A Project B Project C Projects A and B Projects A and C Projects B and C Projects A, B, and C No project b. Calculate...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,500...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,500 2,500 0 0 0 0 B −5,000 2,500 2,500 5,500 2,500 2,500 C −6,250 2,500 2,500 0 2,500 2,500 a. If the opportunity cost of capital is 9%, which project(s) have a positive NPV? Positive NPV project(s) Project A Project B Project C Projects A and B Projects A and C Projects B and C Projects A, B, and C No project b. Calculate...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,800...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,800 2,800 0 0 0 0 B −5,600 2,800 2,800 5,800 2,800 2,800 C −7,000 2,800 2,500 0 2,800 2,800 If the opportunity cost of capital is 12%, which project(s) have a positive NPV? Positive NPV Projects Calculate the payback period for each project. Project A years Project B    years Project C    years Which project(s) would a firm using the payback rule accept...
Consider projects A and B: Cash Flows (dollars) Project C0 C1 C2 NPV at 10% A...
Consider projects A and B: Cash Flows (dollars) Project C0 C1 C2 NPV at 10% A −33,000 23,400 23,400 +$7,612 B −53,000 36,000 36,000 +9,479 a. Calculate IRRs for A and B. (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places.)
Consider two mutually exclusive projects A and B: Cash Flows (dollars) Project C0 C1 C2 NPV...
Consider two mutually exclusive projects A and B: Cash Flows (dollars) Project C0 C1 C2 NPV at 12% A −31,000 21,800 21,800 +$5,843 B −51,000 34,000 34,000 +6,462 a. Calculate IRRs for A and B. (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places.)
1. The following cash flows are given for the Project Z _________________________________________________________             C0            C1&
1. The following cash flows are given for the Project Z _________________________________________________________             C0            C1            C2            C3            C4               C5          -$7000    +$3,000   +$4,000   +$6,000     +$2,500      +$2,000 _________________________________________________________ Calculate the following:     (a) NPV (Net Present Value) at 12% discount rate                                                (b) IRR (Internal Rate of Return)                                                (c) The payback period for Project (Z)
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A...
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A −$ 23,000 +$ 10,120 +$ 10,120 +$ 10,120 B − 23,000 0 0 + 31,050 What is the IRR of each project? (Round your answers to 2 decimal places.)
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT