Question

In: Accounting

Setting Standards, Materials and Labor Variances Tom Belford and Tony Sorrentino own a small business devoted...

Setting Standards, Materials and Labor Variances

Tom Belford and Tony Sorrentino own a small business devoted to kitchen and bath granite installations. Recently, building contractors have insisted on up-front bid prices for a house rather than the cost-plus system that Tom and Tony had been using. They worry because natural flaws in the granite make it impossible to tell in advance exactly how much granite will be used on a particular job. In addition, granite can be easily broken, meaning that Tom or Tony could ruin a slab and would need to start over with a new one. Sometimes the improperly cut pieces could be used for smaller installations, sometimes not. All their accounting is done by a local certified public accounting firm headed by Charlene Davenport. Charlene listened to their concerns and suggested that it might be time to implement tighter controls by setting up a standard costing system.

Charlene reviewed the invoices pertaining to a number of Tom and Tony's previous jobs to determine the average amount of granite and glue needed per square foot. She then updated prices on both materials to reflect current conditions. The standards she developed for one square foot of counter installed were as follows:

Granite, per square foot $50.00
Glue (10 oz. @ $0.15) 1.50
Direct labor hours:
Cutting labor (0.10 hr. @ $15) 1.50
Installation labor (0.25 hr. @ $25) 6.25

These standards assumed that one seamless counter requires one sink cut (the space into which the sink will fit) as well as cutting the counter to fit the space available.

Charlene tracked the actual costs incurred by Tom and Tony for granite installation for the next 6 months. She found that they completed 50 jobs with an average of 32 square feet of granite installed in each one. The following information on actual amounts used and cost was gathered:

Granite purchased and used (1,640 sq. ft.) $82,948
Glue purchased and used (16,000 oz.) $2,560
Actual hours cutting labor 200
Actual hours installation labor 450

The actual wage rate for cutting and installation labor remained unchanged from the standard rate.

Required:

If an amount is zero, enter "0" and select neither from the dropdown.

1. Calculate the materials price variances and materials usage variances for granite and for glue for the past 6 months.

Granite
Materials price variance $fill in the blank 1 Unfavorable
Materials usage variance $fill in the blank 3 Unfavorable
Glue
Materials price variance $fill in the blank 5 Unfavorable
Materials usage variance $fill in the blank 7 Neither

2. Calculate the labor rate variances and labor efficiency variances for cutting labor and for installation labor for the past 6 months.

Cutting Labor
Labor rate variance $fill in the blank 9 Neither
Labor efficiency variance $fill in the blank 11 Unfavorable
Installation Labor
Labor rate variance $fill in the blank 13 Neither
Labor efficiency variance $fill in the blank 15 Unfavorable

3. Conceptual Connection: Would it be worthwhile for Charlene to establish standards for atypical jobs (such as those with more than one sink cut or wider than normal)?

Solutions

Expert Solution

Equations

Material price variance = (Actual unit cost - Standard unit cost) * Actual quantity purchased

Material usage variance = (Standard quantity of material allowed - actual quantity used) * standard price per unit

Direct labor rate variance = ( Actual rate - Standard rate) * Actual hours

Direct labor efficiency variance = (Actual hours - standard hours) * Actual rate

1)

Granite
Materials price variance =82,948 - (1640 x 50) 948.00 U
Materials usage variance=(1640 - 1600)50 2,000.00 U
Glue
Materials price variance = 2560 - (16000 x 0.15)     160.00 U
Materials usage variance (16000 - 16000) 0.15           -  

2)

Cutting Labor
Labor rate variance = (15 - 15)200         -  
Labor efficiency variance = (200 - 160)15 600.00 U
Installation Labor
Labor rate variance = (25 - 25)390         -  
Labor efficiency variance = (450 - 400)25 1,250.00 U

3) No it Would not be worthwhile for Charlene to establish standards for a typical jobs , the operation is small which can be decided mentally also


Related Solutions

Setting Standards, Materials and Labour Variances Tom Belford and Tony Sorrentino own a small business devoted...
Setting Standards, Materials and Labour Variances Tom Belford and Tony Sorrentino own a small business devoted to kitchen and bath granite installations. Recently, building contractors have insisted on up-front bid prices for a house rather than the cost-plus system that Tom and Tony were used to. They worry because natural flaws in the granite make it impossible to tell in advance exactly how much granite will be used on a particular job. In addition, granite can be easily broken, meaning...
Tom Belford and Tony Sorrentino own a small business devoted to kitchen and bath granite installations....
Tom Belford and Tony Sorrentino own a small business devoted to kitchen and bath granite installations. Recently, building contractors have insisted on up-front bid prices for a house rather than the cost-plus system that Tom and Tony had been using. They worry because natural flaws in the granite make it impossible to tell in advance exactly how much granite will be used on a particular job. In addition, granite can be easily broken, meaning that Tom or Tony could ruin...
Direct Materials and Direct Labor Variances
The following information is for the standard and actual costs for the Happy Corporation.Standard Costs:Budgeted units of production - 16,000 (80% of capacity)Standard labor hours per unit - 4Standard labor rate - $26 per hourStandard material per unit - 8 lbs.Standard material cost - $ 12 per poundStandard variable overhead rate - $15 per labor hourBudgeted fixed overhead - $640,000Fixed overhead rate is based on budgeted labor hours at 80% capacity.Actual Cost:Actual production - 16,500 unitsActual material purchased and used...
Organizations determine standard costs for labor, materials, and overhead. Discuss variances for labor, materials, and overhead....
Organizations determine standard costs for labor, materials, and overhead. Discuss variances for labor, materials, and overhead. How do these variances differ from the standard costs? How is each computed? Why is calculating variances useful to an organization? Please help answer: How do these variances differ from the standard costs?
Organizations determine standard costs for labor, materials, and overhead. Discuss variances for labor, materials, and overhead....
Organizations determine standard costs for labor, materials, and overhead. Discuss variances for labor, materials, and overhead. How do these variances differ from the standard costs? How is each computed? Why is calculating variances useful to an organization?
Tom used to run his own business, a small café. Last year, due to water damage...
Tom used to run his own business, a small café. Last year, due to water damage from a flash flood, not only did he lose a substantial part of his inventory; but his café also sustained damages. In order to carry on the business, he sold the café to his friend, Bill, who invested money to replace/repair damaged shop fixtures and machines, and to purchase new inventory. The small café offers coffee and tea, and light food snacks bought from...
Materials and Labor Variances Deporte Company produces single-colored t-shirts. Materials for the shirts are dyed in...
Materials and Labor Variances Deporte Company produces single-colored t-shirts. Materials for the shirts are dyed in large vats. After dying the materials for a given color, the vats must be cleaned and prepared for the next batch of materials to be colored. The following standards for changeover for a given batch have been established: Direct materials (2.4 lbs. @ $0.95) $2.28 Direct labor (0.75 hr. @ $7.40) 5.55 Standard prime cost $7.83 During the year, 79,500 pounds of material were...
Materials and Labor Variances At the beginning of the year, Craig Company had the following standard...
Materials and Labor Variances At the beginning of the year, Craig Company had the following standard cost sheet for one of its plastic products: Direct materials (5 lbs. @ $4.00) $20.00 Direct labor (2 hrs. @ $15.00) 30.00 Standard prime cost per unit $50.00 The actual results for the year are as follows: Units produced: 490,000. Materials purchased: 3,430,000 pounds @ $5.55. Materials used: 2,891,000 pounds. Direct labor: 1,078,000 hours @ $11.04. Required: 1. Compute price and usage variances for...
Describe who is responsible for the cost and efficiency variances for direct materials, direct labor, and...
Describe who is responsible for the cost and efficiency variances for direct materials, direct labor, and manufacturing overhead?
Materials and Labor Variances At the beginning of the year, Craig Company had the following standard...
Materials and Labor Variances At the beginning of the year, Craig Company had the following standard cost sheet for one of its plastic products: Direct materials (5 lbs. @ $4.00) $20.00 Direct labor (2 hrs. @ $15.00) 30.00 Standard prime cost per unit $50.00 The actual results for the year are as follows: Units produced: 390,000. Materials purchased: 2,730,000 pounds @ $5.65. Materials used: 2,301,000 pounds. Direct labor: 702,000 hours @ $13.68. Required: 1. Compute price and usage variances for...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT