In: Accounting
The following information is for the standard and actual costs for the Happy Corporation.
Standard Costs:
Budgeted units of production - 16,000 (80% of capacity)
Standard labor hours per unit - 4
Standard labor rate - $26 per hour
Standard material per unit - 8 lbs.
Standard material cost - $ 12 per pound
Standard variable overhead rate - $15 per labor hour
Budgeted fixed overhead - $640,000
Fixed overhead rate is based on budgeted labor hours at 80% capacity.
Actual Cost:
Actual production - 16,500 units
Actual material purchased and used - 130,000 pounds
Actual total material cost - $1,600,000
Actual labor - 65,000 hours
Actual total labor costs - $1,700,000
Actual variable overhead - $1,000,000
Actual fixed overhead - $640,000
Actual variable overhead - $1,000,000
Determine: (a) the quantity variance, price variance, and total direct materials cost variance; (b) the time variance, rate variance, and total direct labor costvariance; and (c) the volume variance, controllable variance, and total factory overhead cost variance.
(a)
Calculate the quantity variance as shown below:
Quantity variance = Standard price (Actual quantity - Standard quantity)
Thus, the quantity variance is .
Calculate the price variance as shown below:
Thus, the price variance is .
Calculate actual price per pound as shown below:
per pound
Calculate the material cost variance as shown below:
Material cost variance Actual price Actual quantity - Standard price Standard Quantity
Thus, the material cost variance is .
(b)
Calculate the time variance as shown below:
Time variance Standard rate (Actual hours - Standard hours)
Thus, the time variance is .
Calculate the rate variance as shown below:
Rate variance Actual hours (Actual rate - Standard rate)
Thus, the rate variance is .
Note:
Calculate the actual rate as shown below:
Actual rate per
Calculate the labor cost variance as shown below:
Labor cost variance Actual hours Actual rate - Standard hours Standard rate hours units hours
Thus, the labor cost variance is .