Question

In: Accounting

An earned value analysis (EVA) is performed after Month 10 on a 15-month commercial building project...

An earned value analysis (EVA) is performed after Month 10 on a 15-month commercial building project with an estimated final cost (BAC) of $8.45 million. The values at the data date are as follows: EV = $5.25M, AC = $4.95M, and PV = $6.50M.

What are the cost and schedule variances and indices?

What is the projected final cost (EAC)?

All things being equal, what will be the final duration (FD)?

It is acceptable to use SPI to estimate the FD.

What can be concluded from the EVA at this point?

PLEASE SHOW STEPS

Solutions

Expert Solution

Estimated final cost = $ 8.45 M
EV = $ 5.25 M
PV= $ 6.5 M
1) Cost and schedule variance indices
Schedule performance indices= EV/PV= 0.807692
Cost performance index= EV/AC= 0.621302
2) All things are euqal what is the final duration
Axtual cost till now = $4.95 m
Duration completed = 10 monhts
Estimated final cost = 8.45 M
Final duration for entire work= 17.07071
Final duration = 17 Months
3) Is it acceptable to use SPI to estimate the FD?
Using the Schedule Performance Index (SPI) and the average Planned Value (PV) per unit of time, the project team can generate a rough estimate of when the project will be completed, if current trends continue, compared to when it was originally supposed to be completed.
The originally estimated completion time for the project was 12 months, so the project manager now knows that if work continues at the current rate the project will take six months longer than originally planned. It is important to note that this method generates a fairly rough estimate and must always be compared with the status reflected by a time-based schedule method such as critical path method. It is possible that an earned value analysis could show no schedule variance and yet the project is still behind schedule; for example, when tasks that are planned to be completed in the future are performed ahead of tasks on the critical path.
4) What can be the concluded from the EVA at this point.
The earned value analysis as on date is showing negative. It indicates the project is going to be delay by 7 months as per the above final duration calculation

Related Solutions

Actual Cost, planned value and earned value of the activities of an ongoing project after 5...
Actual Cost, planned value and earned value of the activities of an ongoing project after 5 months and after 8 months are given below. All values and costs are in Rs lakhs. Comment on status of the a) Activities (Activity delayed/early, activity cost overrun/underrun) b) status of project and estimated total cost at completion at 5 months and at 8 months. After 5 months    Activity. EV PV AC Comment    A 10 10 8    B 18 15 12...
In what ways can the Earned Value Analysis method be used to monitor the project in...
In what ways can the Earned Value Analysis method be used to monitor the project in an integrated way without affecting the overall schedule and budget of a project?
Calculating EVA Brewster Company manufactures elderberry wine. Last year, Brewster earned operating income of $191,000 after...
Calculating EVA Brewster Company manufactures elderberry wine. Last year, Brewster earned operating income of $191,000 after income taxes. Capital employed equaled $2.6 million. Brewster is 40 percent equity and 60 percent 10-year bonds paying 7 percent interest. Brewster’s marginal tax rate is 40 percent. The company is considered a fairly risky investment and probably commands a 12-point premium above the 5 percent rate on long-term Treasury bonds. Jonathan Brewster’s aunts, Abby and Martha, have just retired, and Brewster is the...
Calculating EVA Brewster Company manufactures elderberry wine. Last year, Brewster earned operating income of $195,000 after...
Calculating EVA Brewster Company manufactures elderberry wine. Last year, Brewster earned operating income of $195,000 after income taxes. Capital employed equaled $2.2 million. Brewster is 40 percent equity and 60 percent 10-year bonds paying 6 percent interest. Brewster’s marginal tax rate is 40 percent. The company is considered a fairly risky investment and probably commands a 13-point premium above the 5 percent rate on long-term Treasury bonds. Jonathan Brewster’s aunts, Abby and Martha, have just retired, and Brewster is the...
Calculating EVA Brewster Company manufactures elderberry wine. Last year, Brewster earned operating income of $195,000 after...
Calculating EVA Brewster Company manufactures elderberry wine. Last year, Brewster earned operating income of $195,000 after income taxes. Capital employed equaled $2.4 million. Brewster is 45 percent equity and 55 percent 10-year bonds paying 7 percent interest. Brewster’s marginal tax rate is 40 percent. The company is considered a fairly risky investment and probably commands a 13-point premium above the 5 percent rate on long-term Treasury bonds. Jonathan Brewster’s aunts, Abby and Martha, have just retired, and Brewster is the...
Calculating EVA Brewster Company manufactures elderberry wine. Last year, Brewster earned operating income of $192,000 after...
Calculating EVA Brewster Company manufactures elderberry wine. Last year, Brewster earned operating income of $192,000 after income taxes. Capital employed equaled $2 million. Brewster is 45 percent equity and 55 percent 10-year bonds paying 6 percent interest. Brewster’s marginal tax rate is 40 percent. The company is considered a fairly risky investment and probably commands a 13-point premium above the 4 percent rate on long-term Treasury bonds. Jonathan Brewster’s aunts, Abby and Martha, have just retired, and Brewster is the...
Calculating EVA Brewster Company manufactures elderberry wine. Last year, Brewster earned operating income of $195,000 after...
Calculating EVA Brewster Company manufactures elderberry wine. Last year, Brewster earned operating income of $195,000 after income taxes. Capital employed equaled $2.1 million. Brewster is 40 percent equity and 60 percent 10-year bonds paying 7 percent interest. Brewster’s marginal tax rate is 40 percent. The company is considered a fairly risky investment and probably commands a 12-point premium above the 4 percent rate on long-term Treasury bonds. Jonathan Brewster’s aunts, Abby and Martha, have just retired, and Brewster is the...
Calculating EVA Brewster Company manufactures elderberry wine. Last year, Brewster earned operating income of $189,000 after...
Calculating EVA Brewster Company manufactures elderberry wine. Last year, Brewster earned operating income of $189,000 after income taxes. Capital employed equaled $2.8 million. Brewster is 45 percent equity and 55 percent 10-year bonds paying 6 percent interest. Brewster’s marginal tax rate is 40 percent. The company is considered a fairly risky investment and probably commands a 12-point premium above the 4 percent rate on long-term Treasury bonds. Jonathan Brewster’s aunts, Abby and Martha, have just retired, and Brewster is the...
Demonstrate Earned Value Management for project portfolio analysis. Understand behavioral concepts and other human issues in...
Demonstrate Earned Value Management for project portfolio analysis. Understand behavioral concepts and other human issues in evaluation and control.
A breakeven analysis for net present worth is performed with a MARR of 15% and a...
A breakeven analysis for net present worth is performed with a MARR of 15% and a useful life of 20 years with the following data: Initial Cost: $750,000 Annual Cost (O&M): $60,000/ year with an annual increase of $5,000 each year Annual Revenue: $80,000/ year with an annual increase of $1,000 each year Salvage Value: $475,000 Determine the following: a. If the project is viable (i.e. if the profit is larger than the cost using net present worth). b. The...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT