Question

In: Accounting

March 1, 2017, Goodman Co. began the manufacture of a new device known as “X”. Goodman...

March 1, 2017, Goodman Co. began the manufacture of a new device known as “X”.

Goodman installed a standard costing system in accounting for manufacturing costs of its product X.

The standard costs for one unit of X are as follows:

Raw materials:              6 lbs. @ $1 per lb.* …………………….         $6.00

Direct labor:                  1 hour @ $4 per hour* …………………. 4.00

Overhead:                     75% of direct labor costs ……………… 3.00

* According to the standard:

- One unit of X requires 6 pounds of raw materials, and the std. cost of raw materials is $1 per pound.

- One unit of X requires 1 hour of direct labor, and the std. direct labor rate is $4 per hour.

During May, 4,000 units of X were manufactured, and 2,500 units of X were sold.

The following data were obtained from Goodman’s records for the month of May:

Sales....................................... $50,000,    Purchases (26,000 pounds) .................................. $27,300

Material price variance (U) ......... 1,300,    Material quantity variance (U)............................................ 1,000

Direct labor rate variance (U) ......     760,    Direct labor efficiency variance (F) ........................................... 800

                             * U (Unfavorable variance): Actual costs > Standard costs.

* F (Favorable variance):      Actual costs < Standard costs.

REQUIRED: (Show your detailed computations!)

Compute each of the following items for Goodman for the month of May:

  1. Standard quantity of raw materials allowed (in pounds).
  2. Actual quantity of raw materials used (in pounds).

                     (Hint: Raw materials purchased (AQp) and used (AQu) are different amounts.)

  1. Actual unit price of raw materials purchased
  2. Standard direct labor hours allowed.
  3. Actual direct labor hours worked.
  4. Actual direct labor rate.
  5. Total labor variance.

Solutions

Expert Solution

Cost card for 4,000 units
Particulars Standard cost for actual production Particulars Actual cost
Quantity & hour Rate($/lb & $/hr) Amount Quantity & hour Rate($/lb & $/hr) Amount
Direct Material 24000.00 1.00 $                24,000 Material purchased 26000 1.05 $                    27,300.00
(4000 units * 6 lb) Material used 25000 1.05 $                    26,250.00
Closing material 1000 $                      1,050.00
Direct labour 4000.00 4.00 $                16,000 Direct labour 3800 4.20 $                    15,960.00
(4000 units *1 hr)
Variable overhead 4000.00 3.00 $                12,000 Variable overhead 3800 27.27 $                 103,610.00
($16,000 *75%) ($ 103610/41000 hr)
Total Standard manufacturing cost $                52,000
Required
1 Standard quantity of raw materials allowed (in pounds).=4000 units * 6lb= 24,000 pounds
2 Actual quantity of raw materials used (in pounds).
Material efficiency variance = (Standard Quantity - Actual Quantity used) * Standard rate
(1000) = (24000 pound-Actual qty used) * $1/lb
Actual qty used= 24000+1000= 25000 pound
3 Actual unit price of raw materials purchased= $27,300/26,000 pound= $1.05/lb
4 Standard direct labor hours allowed= 4000 unit*1 hr/unit= 4,000 hour
5 Actual direct labor hours worked
Labor efficiency variance = (Standard Hours - Actual Hours) * Standard rate
800 = (4000 hr-Actual hr) *$4/hr
Actual direct labor hours worked.= (16000-800)/4= 3800 hour
6 Actual direct labor rate.
Labor Rate variance = (Standard rate - Actual rate) * Actual hours
(760) = ( $4/hr-Actual rate ) * 3800 hr
Actual direct labor rate=(15,200+760)/3800= $4.2/hour
7 Total labor variance.= Labout rate variance+ labour efficiency variance
Total labor variance.= (800-760)=$40 (unfavourable)
Please do upvote if you found the answer useful.
Feel free to reach in the comment section in case of any clarification or queries.

Related Solutions

On May 1, 2019, Goodman Co. began the manufacture of a new device known as “X”....
On May 1, 2019, Goodman Co. began the manufacture of a new device known as “X”. Goodman installed a standard costing system in accounting for manufacturing costs of its product X. The standard costs for one unit of X are as follows: Raw materials: 6 lbs. @ $1 per lb.* ……………………. $6.00 Direct labor: 1 hour @ $4 per hour* …………………. 4.00 Overhead: 75% of direct labor costs ……………… 3.00 * According to the standard: - One unit of X...
Let X be the lifetime of an electronic device. It is known that the average lifetime...
Let X be the lifetime of an electronic device. It is known that the average lifetime of the device is 767 days and the standard deviation is 121 days. Let x¯ be the sample mean of the lifetimes of 157 devices. The distribution of X is unknown, however, the distribution of x¯ should be approximately normal according to the Central Limit Theorem. Calculate the following probabilities using the normal approximation. (a) P(x¯≤754)= Answer (b) P(x¯≥784)= Answer 0.0392 (c) P(749≤x¯≤784)= Answer
Let X be the lifetime of an electronic device. It is known that the average lifetime...
Let X be the lifetime of an electronic device. It is known that the average lifetime of the device is 762 days and the standard deviation is 150 days. Let x¯ be the sample mean of the lifetimes of 156 devices. The distribution of X is unknown, however, the distribution of x¯should be approximately normal according to the Central Limit Theorem. Calculate the following probabilities using the normal approximation. (a) P(x¯≤746) (b) P(x¯≥782) (c) P(738≤x¯≤781)
On March 1, Mocl Co. began construction of a small building. The following expenditures were incurred...
On March 1, Mocl Co. began construction of a small building. The following expenditures were incurred for construction: March 1 $315,000 April 1 254,000 May 1 751,500 June 1 1,152,000 July 1 391,000 The building was completed and occupied on July 1. To help pay for construction $215,000 was borrowed on March 1 on a 12%, three-year note payable. The only other debt outstanding during the year was a $2,000,000, 10% note issued two years ago. Calculate the weighted-average accumulated...
On March 1, Imhoff Co. began construction of a small building. Payments of $400,000 were made...
On March 1, Imhoff Co. began construction of a small building. Payments of $400,000 were made monthly for four months beginning March 1. The building was completed and ready for occupancy on June 1. In determining the amount of interest cost to be capitalized, the weighted-average accumulated expenditures are? How would I calculate this? You probably will answer that $400,000 * ((3/12)+(2/12)+1/12))=200,000 But Why is that weighted as 3/12, 2/12 and 1/12 if the project was outstanding just for 3...
A new company is being established to manufacture and sell an electronic tracking device: the Trackit....
A new company is being established to manufacture and sell an electronic tracking device: the Trackit. The owners are excited about the future profits that the business will generate. They have forecast that sales will grow to 2,600 Trackits per month within five months and will be at that level for the remainder of the first year. The owners will invest a total of $250,000 in cash on the first day of operations (that is the first day of July)....
A new company, is being established to manufacture and sell an electronic tracking device: the Trackit....
A new company, is being established to manufacture and sell an electronic tracking device: the Trackit. The owners are excited about the future profits that the business will generate. They have forecast that sales will grow to 2,600 Trackits per month within five months and will be at that level for the remainder of the first year. The owners will invest a total of $250,000 in cash on the first day of operations (that is the first day of July)....
UVW began construction of a new office building on March 1, Y1. On the day construction...
UVW began construction of a new office building on March 1, Y1. On the day construction began, UVW borrowed $240,000 at 7% and immediately spent it on the project. An additional payment of $60,000 was also made on the day construction began. Additional expenditures of $75,000 were made on May 1 and August 31. Construction was complete and the building was placed in service on December 31, Y1. In addition to the $240,000 borrowed to finance the project, UVW also...
On December 1, 2016, the company began manufacturing a new widget splitter known as the Widgetron....
On December 1, 2016, the company began manufacturing a new widget splitter known as the Widgetron. The company uses a standard costing system to account for manufacturing costs. The standard cost for one Widgetron is as follows: Direct Materials 3lbs at $5 per lb $15.00 Direct Labor 1/2 hour at $20 per hour $10.00 Manufacturing Overhead 75% of Direct Labor Cost $7.50 $32.50 The following data is available from the company's general ledger records for the month of December: Debit...
The Triquel Theater Inc. was recently formed. It began operations in March 2017. The Triquel is...
The Triquel Theater Inc. was recently formed. It began operations in March 2017. The Triquel is unique in that it will show only triple features of sequential theme movies. On March 1, the ledger of The Triquel showed Cash $18,800; Land $40,800; Buildings (concession stand, projection room, ticket booth, and screen) $22,000; Equipment $16,000; Accounts Payable $14,800; and Common Stock $82,800. During the month of March, the following events and transactions occurred: Mar. 2 Rented the first three Star Wars...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT