In: Accounting
March 1, 2017, Goodman Co. began the manufacture of a new device known as “X”.
Goodman installed a standard costing system in accounting for manufacturing costs of its product X.
The standard costs for one unit of X are as follows:
Raw materials: 6 lbs. @ $1 per lb.* ……………………. $6.00
Direct labor: 1 hour @ $4 per hour* …………………. 4.00
Overhead: 75% of direct labor costs ……………… 3.00
* According to the standard:
- One unit of X requires 6 pounds of raw materials, and the std. cost of raw materials is $1 per pound.
- One unit of X requires 1 hour of direct labor, and the std. direct labor rate is $4 per hour.
During May, 4,000 units of X were manufactured, and 2,500 units of X were sold.
The following data were obtained from Goodman’s records for the month of May:
Sales....................................... $50,000, Purchases (26,000 pounds) .................................. $27,300
Material price variance (U) ......... 1,300, Material quantity variance (U)............................................ 1,000
Direct labor rate variance (U) ...... 760, Direct labor efficiency variance (F) ........................................... 800
* U (Unfavorable variance): Actual costs > Standard costs.
* F (Favorable variance): Actual costs < Standard costs.
REQUIRED: (Show your detailed computations!)
Compute each of the following items for Goodman for the month of May:
(Hint: Raw materials purchased (AQp) and used (AQu) are different amounts.)
Cost card for 4,000 units | ||||||||
Particulars | Standard cost for actual production | Particulars | Actual cost | |||||
Quantity & hour | Rate($/lb & $/hr) | Amount | Quantity & hour | Rate($/lb & $/hr) | Amount | |||
Direct Material | 24000.00 | 1.00 | $ 24,000 | Material purchased | 26000 | 1.05 | $ 27,300.00 | |
(4000 units * 6 lb) | Material used | 25000 | 1.05 | $ 26,250.00 | ||||
Closing material | 1000 | $ 1,050.00 | ||||||
Direct labour | 4000.00 | 4.00 | $ 16,000 | Direct labour | 3800 | 4.20 | $ 15,960.00 | |
(4000 units *1 hr) | ||||||||
Variable overhead | 4000.00 | 3.00 | $ 12,000 | Variable overhead | 3800 | 27.27 | $ 103,610.00 | |
($16,000 *75%) | ($ 103610/41000 hr) | |||||||
Total Standard manufacturing cost | $ 52,000 | |||||||
Required | ||||||||
1 | Standard quantity of raw materials allowed (in pounds).=4000 units * 6lb= 24,000 pounds | |||||||
2 | Actual quantity of raw materials used (in pounds). | |||||||
Material efficiency variance = (Standard Quantity - Actual Quantity used) * Standard rate | ||||||||
(1000) = (24000 pound-Actual qty used) * $1/lb | ||||||||
Actual qty used= 24000+1000= 25000 pound | ||||||||
3 | Actual unit price of raw materials purchased= $27,300/26,000 pound= $1.05/lb | |||||||
4 | Standard direct labor hours allowed= 4000 unit*1 hr/unit= 4,000 hour | |||||||
5 | Actual direct labor hours worked | |||||||
Labor efficiency variance = (Standard Hours - Actual Hours) * Standard rate | ||||||||
800 = (4000 hr-Actual hr) *$4/hr | ||||||||
Actual direct labor hours worked.= (16000-800)/4= 3800 hour | ||||||||
6 | Actual direct labor rate. | |||||||
Labor Rate variance = (Standard rate - Actual rate) * Actual hours | ||||||||
(760) = ( $4/hr-Actual rate ) * 3800 hr | ||||||||
Actual direct labor rate=(15,200+760)/3800= $4.2/hour | ||||||||
7 | Total labor variance.= Labout rate variance+ labour efficiency variance | |||||||
Total labor variance.= (800-760)=$40 (unfavourable) | ||||||||
Please do upvote if you found the answer useful. | ||||||||
Feel free to reach in the comment section in case of any clarification or queries. | ||||||||