Question

In: Accounting

On March 1, Mocl Co. began construction of a small building. The following expenditures were incurred...

On March 1, Mocl Co. began construction of a small building. The following expenditures were incurred for construction:

March 1 $315,000
April 1 254,000
May 1 751,500
June 1 1,152,000
July 1 391,000


The building was completed and occupied on July 1. To help pay for construction $215,000 was borrowed on March 1 on a 12%, three-year note payable. The only other debt outstanding during the year was a $2,000,000, 10% note issued two years ago.

Calculate the weighted-average accumulated expenditures. (Do not leave any answer field blank. Enter 0 for amounts.)

Date Expenditures Capitalization Period Weighted-Average
Accumulated Expenditure
March 1 $315,000                                                                       1/1204/122/123/12 $
April 1 254,000                                                                       04/122/121/123/12
May 1 751,500                                                                       4/123/121/122/120
June 1 1,152,000                                                                       04/123/121/122/12
July 1 391,000                                                                       3/121/124/122/120
$

  

  

Calculate avoidable interest. (Round answer to 0 decimal places, e.g. 12,515.)

Avoidable interest $

Solutions

Expert Solution

1. Calculation of weighted average accumulated expenditures-Summation of Expense×(No. Of months/12)

= (315,000×4/12)+(254,000×3/12)+(751,500×2/12)+(1,152,000×1/12)+(391,000×0/12)

= $389,750

March 1 $315,000
April 1 254,000
May 1 751,500
June 1 1,152,000
July 1 391,000


2. Avoidable Interest

= Specific Loan × Specific Rate of interest + (Weighted average accumulated expenditures - Specific Loan) × General Rate of interest

= (215,000 × 12% × 4/12) + [( 389,750 - (215,000 × 4/12)) × 10% × 4/12]

= $19,314

Working Notes -

1. The Financial year is assumed to be ending on 30 June every year as it is most common in US.

2. As the last expenditure was made on date of completion of the project, which is very unlikely in reality, the capitalisation of its interest of that expense is zero.

3. As the life of the project was less than a year, so further changes are made in calculation of Avoidable Interest.


​​​


Related Solutions

On March 1, Imhoff Co. began construction of a small building. Payments of $400,000 were made...
On March 1, Imhoff Co. began construction of a small building. Payments of $400,000 were made monthly for four months beginning March 1. The building was completed and ready for occupancy on June 1. In determining the amount of interest cost to be capitalized, the weighted-average accumulated expenditures are? How would I calculate this? You probably will answer that $400,000 * ((3/12)+(2/12)+1/12))=200,000 But Why is that weighted as 3/12, 2/12 and 1/12 if the project was outstanding just for 3...
On April 1, Paine Co. began construction of a small building. Payments of $234,960 were made...
On April 1, Paine Co. began construction of a small building. Payments of $234,960 were made monthly for four months beginning on April 1. The building was completed and ready for occupancy on August 1. For the purpose of determining the amount of interest cost to be capitalized, calculate the weighted-average accumulated expenditures on the building by completing the schedule below: Date Expenditures Capitalization Period Weighted-Ave. Accum. Expend. $ $    $
On April 1, Paine Co. began construction of a small building. Payments of $180,000 were made...
On April 1, Paine Co. began construction of a small building. Payments of $180,000 were made monthly for four months beginning on April 1. The building was completed and ready for occupancy on August 1. For the purpose of determining the amount of interest cost to be capitalized, calculate the weighted-average accumulated expenditures on the building by completing the schedule below:             Date               Expenditures       Capitalization Period      Weighted-Average Expenditures Question 2 On March 1, Mocl Co. began construction of a small...
UVW began construction of a new office building on March 1, Y1. On the day construction...
UVW began construction of a new office building on March 1, Y1. On the day construction began, UVW borrowed $240,000 at 7% and immediately spent it on the project. An additional payment of $60,000 was also made on the day construction began. Additional expenditures of $75,000 were made on May 1 and August 31. Construction was complete and the building was placed in service on December 31, Y1. In addition to the $240,000 borrowed to finance the project, UVW also...
On January 1, 2020, Lawrence Co. began construction of a building to be used as its...
On January 1, 2020, Lawrence Co. began construction of a building to be used as its office headquarters. The building is expected to be completed on December 31, 2020. Expenditures on this project during 2020 were as follows:                 January 1st          $ 160,000 March 1st               420,000 June 1st                  270,000 October 31st           165,000 On Jan. 1, 2020, the company obtained a $600,000 specific construction loan with a 7% interest rate. The loan was outstanding during the entire construction period. The company’s...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on land costing $800,000 (purchased from the contractor and included in the first payment). The construction began on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2019 $ 1,200,000 May 1, 2019 1,680,000 August 1, 2019 3,000,000 September 30, 2019 4,800,000 The building was completed and ready for occupancy on September 30, 2019. To finance purchase...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on land costing $800,000 (purchased from the contractor and included in the first payment). The construction began on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2019 $ 1,200,000 May 1, 2019 1,680,000 August 1, 2019 3,000,000 September 30, 2019 4,800,000 The building was completed and ready for occupancy on September 30, 2019. To finance purchase...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on land costing $800,000 (purchased from the contractor and included in the first payment). The construction began on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2019 $ 1,200,000 May 1, 2019 1,680,000 August 1, 2019 3,000,000 September 30, 2019 4,800,000 The building was completed and ready for occupancy on September 30, 2019. To finance purchase...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on...
On March 1, 2019, Asbah contracted Nabali & Fares Construction Co. to construct a building on land costing $800,000 (purchased from the contractor and included in the first payment). The construction began on the office building on March 1. The following expenditures were incurred for construction: Date Expenditures March 1, 2019 $ 1,200,000 May 1, 2019 1,680,000 August 1, 2019 3,000,000 September 30, 2019 4,800,000 The building was completed and ready for occupancy on September 30, 2019. To finance purchase...
On January 1, 2021, Dreamworld Co. began construction of a new warehouse. The building was finished...
On January 1, 2021, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 326,000 September 1, 2021 $ 477,000 December 31, 2021 $ 477,000 March 31, 2022 $ 477,000 September 30, 2022 $ 326,000 Dreamworld had $5,900,000 in 12% bonds outstanding through both years. What was the final cost of Dreamworld's warehouse?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT