using the schedule from unit 3 assignment, estimate the cost for each activity.
Unit 3 Case Assignment (Wedding) – Baseline Schedule
of activities.
WBS # DESCRIPTION RESPONSIBLE Duration
1 Budget & Planning Tony 9 days
1.1 Create a Timeline Peggy Sue 2
1.2 Estimate Budget Tony 2
1.3 Evaluate Estimated Budget/Timeline & Actual Cost of Wedding
Tony 5
2 Guest List Peggy Sue 33 days
2.1 Determine Guest List Tony 7
2.2 Create & Mail “Save the Date” Peggy Sue 7
2.3 Send Invitations Peggy Sue 7
2.4 Collect Responses Tony 7
2.5 Finalize Seating Chart Peggy Sue 5
3 Bridal Peggy Sue 55 days
3.1 Determine Bridal Party Peggy Sue & Tony 15
3.2 Purchase Wedding Apparel Carmella 20
3.3 Plan Bridal Party Events Carmella 15
3.4 Purchase Marriage License Tony 5
4 Honeymoon Carmella 10 days
4.1 Confirm Destination & Dates Peggy Sue 5
4.2 Book Travel & Hotel Carmella 3
4.3 Confirm Booking & Payment Details Tony 2
5 Venue & Vendors Peggy Sue 53 days
5.1 Book Venue for Ceremony, Reception & Rehearsal Dinner Peggy
Sue 12
5.2 Select Vendors Tony 6
5.3 Select Officiant Mildred 5
5.4 Hire Photographer/Videographer Peggy Sue 5
5.6 Reserve Hotel Block Mildred 5
5.7 Hire Transportation Mildred 5
5.8 Finalize Catering Menu Tony 5
5.9 Finalize Ceremony, Reception & Rehearsal Dinner Set-up
Mildred 10
Hello, In this project activity case, I would like to introduce to you new way of solving ,i.e. using table (normally these are presented in flow chart).
Description- On header, I have taken name of responsible person of a particular activity.
On left hand side, I have taken time (and sub time for convenience) which are in days.
And in matrix, for ease in reading, I have taken directly activity code (such as 1.1 represents Create a Timeline Peggy Sue 2)
Name--> | Peggy Sue | Tony | Carmella | Mildred | |
Time v | Sub Days | ||||
2 | 1.1 | 1.2 | |||
15 | 3.1 | 3.1 | |||
20 | 1 | 5.1 | 2.1 | 3.2 | |
2 | |||||
3 | |||||
4 | |||||
5 | |||||
6 | |||||
7 | |||||
8 | |||||
9 | |||||
10 | |||||
11 | |||||
12 | |||||
13 | 2.2 | 5.2 | |||
14 | |||||
15 | |||||
16 | |||||
17 | |||||
18 | |||||
19 | 5.3 | ||||
20 | 2.3 | ||||
15 | 1 | 3.3 | |||
2 | |||||
3 | |||||
4 | |||||
5 | |||||
6 | |||||
7 | 5.4 | 2.4 | |||
8 | |||||
9 | |||||
10 | |||||
11 | |||||
12 | 4.1 | 5.6 | |||
13 | |||||
14 | |||||
15 | |||||
5 | 1 | 4.2 | |||
2 | 2.5 | 5.7 | |||
3 | |||||
4 | 4.3 | ||||
5 | |||||
5 | 1 | ||||
2 | 5.8 | ||||
3 | |||||
4 | |||||
5 | |||||
10 | 1 | ||||
2 | 3.4 | 5.9 | |||
3 | |||||
4 | |||||
5 | |||||
6 | |||||
7 | 1.3 | ||||
8 | |||||
9 | |||||
10 | |||||
1 | 1 | ||||
73 | Total |
So the minimum total days cost will be 73 days for completing the wedding case.