Question

In: Accounting

Calculating Activity-Based Costing Overhead Rates 1. Calculate the cost per unit of activity driver for each...

Calculating Activity-Based Costing Overhead Rates

1. Calculate the cost per unit of activity driver for each activity cost category.
Setup $_____
Production scheduling $______
Production engineering $______
Supervision $_______
Machine maintenance $______

2. Calculate the cost of Job 845 using ABC to assign the overhead costs.

$______

3. Calculate the cost of Job 845 using the plantwide overhead rate based on machine hours. (Round your answer to the nearest dollar.)
$_____


A food company had the following activities and costs:

Setup (1,000 setup hours) $118,000
Production scheduling (400 batches) 60,000
Production engineering (60 change orders) 150,000
Supervision (2,000 direct labor hours) 46,000
Machine maintenance (12,000 machine hours) 60,000
Total activity costs $434,000

The following additional data were provided for Job 845:

Direct materials costs $7,000
Direct labor cost (5 Milling direct labor hours;
35 Finishing direct labor hours)
$1,000
Setup hours 5 hours
Production scheduling 1 batch
Machine hours used (25 Milling machine hours;
5 Finishing machine hours)
30 hours
Production engineering 3 change orders

Solutions

Expert Solution

1. Calculate the cost per unit of activity driver for each activity cost category.

Setup (118000/1000) 118 per setup
Production scheduling (60000/400) 150 per batch
Production engineering (150000/60) 2500 per change order
Supervision (46000/2000) 23 per direct labour hour
Machine maintenance (60000/12000) 5 per machine hour

2. Calculate the cost of Job 845 using ABC to assign the overhead costs.

Direct material cost 7000
Direct labour cost 1000
Setup cost (118*5) 590
Production scheduling (150*1) 150
Production scheduling (2500*3) 7500
Supervision (23*40) 920
Machine maintenance (5*30) 150
Total job cost 17310

3. Calculate the cost of Job 845 using the plantwide overhead rate based on machine hours. (Round your answer to the nearest dollar.)

Overhead rate = 434000/12000 = 36.167 per machine hour

Direct material 7000
Direct labour 1000
Overhead cost 1085
Total job cost 9085

Related Solutions

Using the activity-based costing approach, determine the overhead cost per unit for each product.
Daba Company manufactures two products, Product F and Product G. The company expects to produce and sell 3,300 units of Product F and 3,700 units of Product G during the current year. The company uses activity-based costing to compute unit product costs for external reports. Data relating to the company's three activity cost pools are given below for the current year:EstimatedExpected ActivityActivity Cost PoolOverhead CostProduct FProduct GTotalMachine setups$20,400144setups96setups240setupsPurchase orders$129,320854orders1,586orders2,440ordersOrder size$75,6001,310hours1,210hours2,520hoursRequired:Using the activity-based costing approach, determine the overhead cost per unit...
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following...
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following activities and costs: Setup (1,000 setup hours) $118,000 Production scheduling (400 batches) 30,000 Production engineering (60 change orders) 90,000 Supervision (2,000 direct labor hours) 64,000 Machine maintenance (12,000 machine hours) 84,000 Total activity costs $386,000 The following additional data were provided for Job 845: Direct materials costs $7,000 Direct labor cost (5 Milling direct labor hours;35 Finishing direct labor hours) $1,000 Setup hours 5...
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following...
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following activities and costs: Setup (1,000 setup hours) $150,000 Production scheduling (400 batches) 80,000 Production engineering (60 change orders) 60,000 Supervision (2,000 direct labor hours) 66,000 Machine maintenance (12,000 machine hours) 48,000 Total activity costs $404,000 The following additional data were provided for Job 845: Direct materials costs $7,000 Direct labor cost (5 Milling direct labor hours;35 Finishing direct labor hours) $1,000 Setup hours 5...
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following...
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following activities and costs: Setup (1,000 setup hours) $150,000 Production scheduling (400 batches) 80,000 Production engineering (60 change orders) 60,000 Supervision (2,000 direct labor hours) 66,000 Machine maintenance (12,000 machine hours) 48,000 Total activity costs $404,000 The following additional data were provided for Job 845: Direct materials costs $7,000 Direct labor cost (5 Milling direct labor hours;35 Finishing direct labor hours) $1,000 Setup hours 5...
Selecting the appropriate cost driver is the key to effective activity based costing. Identify three overhead...
Selecting the appropriate cost driver is the key to effective activity based costing. Identify three overhead elements in a simple product your current or former employer makes, and identify what you think the best cost driver would be for each element. 100 words or more. NB/ My place of work is a food processing company
Mastery Problem: Activity-Based Costing (Advanced) Activity-Based Costing Traditionally, Overhead cost: Sometimes referred to as "factory overhead,"...
Mastery Problem: Activity-Based Costing (Advanced) Activity-Based Costing Traditionally, Overhead cost: Sometimes referred to as "factory overhead," this is an indirect cost that is not directly tied to the production of units, yet nonetheless must be built into product cost in order to appropriately price it. Examples are managerial salaries, rent expense, setup costs, and property taxes.overhead costs are assigned based arbitrarily on the rate of either Direct labor: This is a labor cost directly associated with the production of goods...
In activity-based costing, each major activity has its own overhead cost pool, its own activity measure,...
In activity-based costing, each major activity has its own overhead cost pool, its own activity measure, and its own overhead rate. True or False TrueFalse
Gould Corporation uses the following activity rates from its activity-based costing to assign overhead costs to...
Gould Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products:Information is given as Activity Cost Pool; Amount; Activity RateSetting up batches; $59.06; per batchProcessing customer orders; $72.66; per customer orderAssembling products; $3.75; per assembly hourData concerning the two products is below:Product K91B:Number of batches = 84; number of customer orders = 32; number of assembly hours = 483Product F650:Number of batches = 50; number of customer orders = 43; number of assembly hours...
Hane Corporation uses the following activity rates from its activity-based costing to assign overhead costs to...
Hane Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products: Activity Cost Pools Activity Rate Assembling products $8.90 per assembly hour Processing customer orders $31.23 per customer order Setting up batches $43.72 per batch Data for one of the company's products follow: Product U94W Number of assembly hours 389 Number of customer orders 53 Number of batches 61 How much overhead cost would be assigned to Product U94W using the activity-based costing system?
Gould Corporation uses the following activity rates from its activity-based costing to assign overhead costs to...
Gould Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products: Activity Cost Pool Activity Rate Setting up batches $ 59.31 per batch Processing customer orders $ 72.81 per customer order Assembling products $ 4.00 per assembly hour Data concerning two products appear below: Product K91B Product F65O Number of batches 84 55 Number of customer orders 34 48 Number of assembly hours 488 895 How much overhead cost would be assigned to Product...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT