In: Operations Management
The partially completed inventory record for the driveshaft subassembly in the table below shows gross requirements, scheduled receipts, lead time, and current on-hand inventory.
a. Complete the last three rows of the record for an FOQ of
60
units. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.)
|
Item: Driveshaft subassembly |
Lot Size:
FOQequals=60 units |
||||||||
|
Lead Time: 3 weeks |
|||||||||
|
Week |
|||||||||
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
||
|
Gross requirements |
30 |
20 |
20 |
25 |
50 |
50 |
55 |
55 |
|
|
Scheduled receipts |
70 |
||||||||
|
Projected on-hand inventory |
10 |
||||||||
|
Planned receipts |
|||||||||
Complete the last three rows of the record by using the L4L lot-sizing rule. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.)
steps for MRP
| repeat these steps for every period | |||
| step 1 | IOH= | PIOH of last week | |
| step 2 | Requirement= | GR-IOH-SR+SS | |
| step 3 | NR= | is equal to requirement (if requirement>0) OR 0 (if requirement is negative) | |
| step 4 | PR= | in L4L PR=NR | in FOQ: more than or equal to NR in multiples of lot size |
| step 5 | PIOH= | IOH+PR-GR-SR | |
A: FOQ based MRP
| safety stock, SS= | 0 | |||||||
| Beginning inventory= | 10 | |||||||
| Q= | 60 | |||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |
| Gross requirements GR | 30 | 20 | 20 | 25 | 50 | 50 | 55 | 55 |
| Scheduled receipts SR | 70 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| On hand at the beginning of period IOH | 10 | 50 | 30 | 10 | 45 | 55 | 5 | 10 |
| Requirement | -50 | -30 | -10 | 15 | 5 | -5 | 50 | 45 |
| Net requirements NR | 0 | 0 | 0 | 15 | 5 | 0 | 50 | 45 |
| Planned order receipts (PR) | 0 | 0 | 0 | 60 | 60 | 0 | 60 | 60 |
| Projected inventory on hand PIOH | 50 | 30 | 10 | 45 | 55 | 5 | 10 | 15 |
B: L4L based MRP
| safety stock, SS= | 0 | |||||||
| Beginning inventory= | 10 | |||||||
| Q= | L4L | |||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |
| Gross requirements GR | 30 | 20 | 20 | 25 | 50 | 50 | 55 | 55 |
| Scheduled receipts SR | 70 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| On hand at the beginning of period IOH | 10 | 50 | 30 | 10 | 0 | 0 | 0 | 0 |
| Requirement | -50 | -30 | -10 | 15 | 50 | 50 | 55 | 55 |
| Net requirements NR | 0 | 0 | 0 | 15 | 50 | 50 | 55 | 55 |
| Planned order receipts (PR) | 0 | 0 | 0 | 15 | 50 | 50 | 55 | 55 |
| Projected inventory on hand PIOH | 50 | 30 | 10 | 0 | 0 | 0 | 0 | 0 |