In: Accounting
1
The Nowra Company has assembled the following data pertaining to
certain costs that cannot be easily identified as either fixed or
variable. Nowra Company has heard about a method of measuring cost
functions called the high-low method and has decided to use it in
this situation.
Month |
Cost |
Hours |
|
January |
$40 000 |
3500 |
|
February |
24 400 |
2000 |
|
March |
31 280 |
2450 |
|
April |
36 400 |
3000 |
|
May |
44 160 |
3900 |
|
June |
42 400 |
3740 |
How is the cost function stated?
a. |
y = $21 360 + $1.52X |
|
b. |
y = $10 112 + $8.64X |
|
c. |
y = $26 672 + $1.84X |
|
d. |
y = $3600 + $10.40X |
|
e. |
No correct answer |
2
The Yeppoon Company uses the high-low method to estimate its
cost function. The information for 2018 is provided
below:
Machine-hours |
Costs |
||
Highest observation of cost driver |
2000 |
$225 000 |
|
Lowest observation of cost driver |
1000 |
$125 000 |
What is the constant for the estimating cost equation?
$0 |
||
$225 000 |
||
$25 000 |
||
$125 000 |
||
No correct answer |
3
The cost components of an air conditioner include $35 for the compressor; $11.50 for the sheet moulded compound frame; and $80 per unit for assembly. The factory machines and tools cost is $55 000. The company expects to produce 1500 air conditioners in the coming year. What cost function best represents these costs?
a. |
y = 55 000 + 126.50X |
|
b. |
y = 55 000 + 1500X |
|
c. |
y = 1500 + 126.5X |
|
d. |
y = 1500 + 55 000X |
|
e. |
No correct answer |
4
V8 Engineering Pty used the following data to evaluate their
current operating system. The company sells items for $14.50 each
and had used a budgeted selling price of $15 per unit.
Actual Budgeted
Units
sold 206
000 units 200 000 units
Variable
costs $965
000 $950
000
Fixed
costs $53
000 $50
000
What is the static-budget variance of variable costs?
a. |
$13 000 unfavourable |
|
b. |
$15 000 favourable |
|
c. |
$13 000 favourable |
|
d. |
$15 000 unfavourable |
|
e. |
No correct answer |
Q.1 |
Correct Option d. y = $3600 + $10.40X |
|||||||
Cost | Hours | |||||||
High LEVEL | 44160 | 3900 | ||||||
Low Level | 24400 | 2000 | ||||||
Change | 19760 | 1900 | ||||||
Change per unit (Variable cost) = Change in total cost / Change in Hours | ||||||||
=(19760/1900) | ||||||||
10.4 | ||||||||
Fixed Cost calculation | ||||||||
Variable Cost + Fixed cost = Total cost | ||||||||
10.4 * 3900 + Fixed Cost = 44160 | ||||||||
Fixed Cost = $3600 | ||||||||
Q.2 | Correct Option C i.e. $25000 | |||||||
Fixed is constant, hence calculate fixed cost | ||||||||
Cost | Hours | |||||||
High LEVEL | 225000 | 2000 | ||||||
Low Level | 125000 | 1000 | ||||||
Change | 100000 | 1000 | ||||||
Change per unit (Variable cost) = Change in total cost / Change in Units Sold | ||||||||
=(100000/1000) | ||||||||
100 | ||||||||
Fixed Cost calculation | ||||||||
Variable Cost + Fixed cost = Total cost | ||||||||
100 * 2000 + Fixed Cost = 225000 | ||||||||
Fixed Cost = $25000 | ||||||||
Q.3 |
Correct Option a. y = 55 000 + 126.50X |
|||||||
Variable Cost | 126.5 | (35+11.50+80) | ||||||
Fixed cost | 55000 | |||||||
Q.4 | Correct Option D i.e. $15000 Unfavorable | |||||||
Static Budget variance = Budgeted variable cost - actual variable cost | ||||||||
=950000 - 965000 | ||||||||
=15000 Unfavorable | ||||||||