In: Accounting
1
The Nowra Company has assembled the following data pertaining to
certain costs that cannot be easily identified as either fixed or
variable. Nowra Company has heard about a method of measuring cost
functions called the high-low method and has decided to use it in
this situation.
| 
 Month  | 
 Cost  | 
 Hours  | 
|
| 
 January  | 
 $40 000  | 
 3500  | 
|
| 
 February  | 
 24 400  | 
 2000  | 
|
| 
 March  | 
 31 280  | 
 2450  | 
|
| 
 April  | 
 36 400  | 
 3000  | 
|
| 
 May  | 
 44 160  | 
 3900  | 
|
| 
 June  | 
 42 400  | 
 3740  | 
How is the cost function stated?
| a. | 
 y = $21 360 + $1.52X  | 
|
| b. | 
 y = $10 112 + $8.64X  | 
|
| c. | 
 y = $26 672 + $1.84X  | 
|
| d. | 
 y = $3600 + $10.40X  | 
|
| e. | 
 No correct answer  | 
2
The Yeppoon Company uses the high-low method to estimate its
cost function. The information for 2018 is provided
below:
| 
 Machine-hours  | 
 Costs  | 
||
| 
 Highest observation of cost driver  | 
 2000  | 
 $225 000  | 
|
| 
 Lowest observation of cost driver  | 
 1000  | 
 $125 000  | 
What is the constant for the estimating cost equation?
| 
 $0  | 
||
| 
 $225 000  | 
||
| 
 $25 000  | 
||
| 
 $125 000  | 
||
| 
 No correct answer  | 
3
The cost components of an air conditioner include $35 for the compressor; $11.50 for the sheet moulded compound frame; and $80 per unit for assembly. The factory machines and tools cost is $55 000. The company expects to produce 1500 air conditioners in the coming year. What cost function best represents these costs?
| a. | 
 y = 55 000 + 126.50X  | 
|
| b. | 
 y = 55 000 + 1500X  | 
|
| c. | 
 y = 1500 + 126.5X  | 
|
| d. | 
 y = 1500 + 55 000X  | 
|
| e. | 
 No correct answer  | 
4
V8 Engineering Pty used the following data to evaluate their
current operating system. The company sells items for $14.50 each
and had used a budgeted selling price of $15 per unit.
                                                                   Actual             Budgeted
        Units
sold                                   206
000 units      200 000 units
        Variable
costs                            $965
000               $950
000
        Fixed
costs                                    $53
000                 $50
000
What is the static-budget variance of variable costs?
| a. | 
 $13 000 unfavourable  | 
|
| b. | 
 $15 000 favourable  | 
|
| c. | 
 $13 000 favourable  | 
|
| d. | 
 $15 000 unfavourable  | 
|
| e. | 
 No correct answer  | 
| Q.1 | 
Correct Option d. y = $3600 + $10.40X  | 
|||||||
| Cost | Hours | |||||||
| High LEVEL | 44160 | 3900 | ||||||
| Low Level | 24400 | 2000 | ||||||
| Change | 19760 | 1900 | ||||||
| Change per unit (Variable cost) = Change in total cost / Change in Hours | ||||||||
| =(19760/1900) | ||||||||
| 10.4 | ||||||||
| Fixed Cost calculation | ||||||||
| Variable Cost + Fixed cost = Total cost | ||||||||
| 10.4 * 3900 + Fixed Cost = 44160 | ||||||||
| Fixed Cost = $3600 | ||||||||
| Q.2 | Correct Option C i.e. $25000 | |||||||
| Fixed is constant, hence calculate fixed cost | ||||||||
| Cost | Hours | |||||||
| High LEVEL | 225000 | 2000 | ||||||
| Low Level | 125000 | 1000 | ||||||
| Change | 100000 | 1000 | ||||||
| Change per unit (Variable cost) = Change in total cost / Change in Units Sold | ||||||||
| =(100000/1000) | ||||||||
| 100 | ||||||||
| Fixed Cost calculation | ||||||||
| Variable Cost + Fixed cost = Total cost | ||||||||
| 100 * 2000 + Fixed Cost = 225000 | ||||||||
| Fixed Cost = $25000 | ||||||||
| Q.3 | 
Correct Option a. y = 55 000 + 126.50X  | 
|||||||
| Variable Cost | 126.5 | (35+11.50+80) | ||||||
| Fixed cost | 55000 | |||||||
| Q.4 | Correct Option D i.e. $15000 Unfavorable | |||||||
| Static Budget variance = Budgeted variable cost - actual variable cost | ||||||||
| =950000 - 965000 | ||||||||
| =15000 Unfavorable | ||||||||