Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products.

Blender Electric Mixer
Direct material $ 17 $ 26
Direct labor 10 38
Manufacturing overhead @ $44 per machine hour 44 88
Cost if purchased from an outside supplier 64 132
Annual demand (units) 33,000 38,000

Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $22. Kitchen Magician’s management has a policy of filling all sales orders, even if it means purchasing units from outside suppliers.

Required:

If 70,000 machine hours are available, and management desires to follow an optimal strategy, how many units of each product should the firm manufacture? How many units of each product should be purchased?

With all other things constant, if management is able to reduce the direct material for an electric mixer to $17 per unit, how many units of each product should be manufactured? Purchased?

If 70,000 machine hours are available, and management desires to follow an optimal strategy, how many units of each product should the firm manufacture? How many units of each product should be purchased?

Blender Electric Mixer
Manufacture 33,000 18,500
Purchase 0

With all other things constant, if management is able to reduce the direct material for an electric mixer to $17 per unit, how many units of each product should be manufactured? Purchased?

Blender Electric Mixer
Manufacture 0
Purchase

Solutions

Expert Solution

1)

Bleder Electric Mixer
Price 64 132
less:variable cost
Direct material (17) (26)
direct labor (10) (38)
variable overhead (22)    [44-22fixed) (44)    [88-(22*2)fixed]
contribution margin per unit 15 24
machine hour per unit 44/44 =1 88/44=2
contribution pER HOUR 15/1= $15 24/2 =$ 12
Ranking 1 2
Blender Electric
Manufacture 33000 units    [33000*1 =33000MH used] 18500 units     [37000/2]
purchase 0 38000-18500= 19500

  **machine hours available after manufacturing of blender = 70000-33000 = 37000 hours

2)

Bleder Electric Mixer
Price 64 132
less:variable cost
Direct material (17) (17)
direct labor (10) (38)
variable overhead (22)    [44-22fixed) (44)    [88-(22*2)fixed]
contribution margin per unit 15 33
machine hour per unit 44/44 =1 88/44=2
contribution pER HOUR 15/1= $15 33/2 =$ 16.5
Ranking 2 1
Blender Electric mixer
Manufacture 0 35000 [70000hours /2 per unit ]
Purchase 33000 38000-35000= 3000

Related Solutions

Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender Electric Mixer Direct Material $26 $45 Direct Labor $20 $33 Manufacturing overhead @ $54 per machine hour $54 $108 Cost if purchased from an outside supplier $68 $116 Annual demand (units) $28,000 $34,000 Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $42. Kitchen Magician's management has a policy of filling all sales orders, even...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender Electric Mixer Direct Material $26 $45 Direct Labor $20 $33 Manufacturing overhead @ $54 per machine hour $54 $108 Cost if purchased from an outside supplier $68 $116 Annual demand (units) $28,000 $34,000 Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $42. Kitchen Magician's management has a policy of filling all sales orders, even...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender Electric Mixer Direct material $ 18 $ 28 Direct labor 11 39 Manufacturing overhead @ $46 per machine hour 46 92 Cost if purchased from an outside supplier 65 133 Annual demand (units) 34,000 40,000 Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $23. Kitchen Magician’s management has a policy of filling all sales...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender Electric Mixer Direct material $ 21 $ 30 Direct labor 14 42 Manufacturing overhead @ $52 per machine hour 52 104 Cost if purchased from an outside supplier 71 140 Annual demand (units) 37,000 46,000 Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $26. Kitchen Magician’s management has a policy of filling all sales...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender Electric Mixer Direct material $ 17 $ 26 Direct labor 10 38 Manufacturing overhead @ $44 per machine hour 44 88 Cost if purchased from an outside supplier 64 132 Annual demand (units) 33,000 38,000 Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $22. Kitchen Magician’s management has a policy of filling all sales...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender Electric Mixer Direct material $ 22 $ 32 Direct labor 15 43 Manufacturing overhead @ $54 per machine hour 54 108 Cost if purchased from an outside supplier 75 146 Annual demand (units) 38,000 45,000 Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $27. Kitchen Magician’s management has a policy of filling all sales...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender Electric Mixer Direct material $ 22 $ 37 Direct labor 16 29 Manufacturing overhead @ $46 per machine hour 46 92 Cost if purchased from an outside supplier 64 109 Annual demand (units) 24,000 36,000 Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $34. Kitchen Magician’s management has a policy of filling all sales...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Blender Electric Mixer Direct material $ 22 $ 32 Direct labor 15 43 Manufacturing overhead @ $54 per machine hour 54 108 Cost if purchased from an outside supplier 75 146 Annual demand (units) 38,000 45,000 Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $27. Kitchen Magician’s management has a policy of filling all sales...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Direct...
Kitchen Magician, Inc. has assembled the following data pertaining to its two most popular products. Direct material $ 26 $ 45 Direct labor 20 33 Manufacturing overhead @ $54 per machine hour 54 108 Cost if purchased from an outside supplier 68 116 Annual demand (units) 28,000 34,000 Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $42. Kitchen Magician’s management has a policy of filling all sales orders, even if...
Chef Gourmet, Inc., has assembled the following data pertaining to its two most popular products. Blender...
Chef Gourmet, Inc., has assembled the following data pertaining to its two most popular products. Blender Food Processor   Direct material $ 24 $ 41   Direct labor 18 31   Manufacturing overhead @ $50 per machine hour 50 100   Cost if purchased from an outside supplier 66 114   Annual demand (units) 26,000 30,000      Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages $36. Management has a policy of filling all sales orders, even...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT